Data Centres: Boom and Backlash
15NOV

Norway shuts its grid queue to data centres

4 min read
23:07UTC

Statnett, Norway's grid operator, stopped new reservations for data centres on 9 November, and the government said it will license every site. Spain's revised draft decree would let its grid operator, Red Eléctrica, cut data centres off first and unpaid, Britain will cap post-2030 connections by region, and Finland will register every site above 0.5 MW. The money kept coming: Google pledged US$15bn for Malaysia and to pay for its own power, and Brookfield signed a US$9bn compute deal with Naver.

Key takeaway

Governments are replacing first-come grid queues with conditions on who data centres connect and on what terms.

This briefing mapped
Regulatory
Economic
Domestic
Infrastructure

Statnett took no new grid reservations for data centres from 9 November, after requests reached 32,100 MW in a country whose demand has never passed about 25,000 MW. Norway's government answered the same day with plans for a licence.

Sources profile:This story draws on neutral-leaning sources

Statnett, which runs Norway's power grid, stopped reserving capacity for new data centres on 9 November. Projects connected, reserved, queued and requested now total 32,100 MW, more than Norway has ever drawn at once.

Ministers will also license data centres. Grid access in Norway is moving from a place in a queue to a permit the state can refuse or attach conditions to. 

Spain's revised data-centre decree, now with the Council of State, gives operators until 2031 to match their power hour by hour with renewables. In return, Red Eléctrica could switch them off without paying them.

Sources profile:This story draws on neutral-leaning sources

Spain sent its revised data-centre decree to the Council of State, its top advisory body, in late October, El País and La Vanguardia reported. Sites of 10 MW or more must still cover 80% of their power with new renewables, hour by hour.

Under the briefed terms, operators that let Red Eléctrica, the grid operator, cut them off unpaid would get until 2031 to comply. Factories are paid for the same cuts, so data centres trade reliability for time. 

Sources:Roams·DPL News

DESNZ will let ministers reserve grid capacity for projects a department, devolved government or mayor sponsors. After 2030, data-centre connections will follow regional targets.

Sources profile:This story draws on neutral-leaning sources

Britain's energy department set out how favoured projects can jump the grid queue on 28 October, after 156 consultation replies. A project backed by a department, a devolved government or a mayor can reserve capacity and move up its batch.

With no megawatt test, ministers decide what counts as strategic. After 2030, data-centre connections will follow regional targets for grid, water and land. 

Sources:DESNZ

Five days after the M3 power-line delay cut its guidance, NEXTDC said its chairman will retire and its directors will take less pay. Within a fortnight, Goodman Group and Digital Realty held 9.9% of the company.

Sources profile:This story draws on neutral-leaning sources

NEXTDC said on 26 October that its chairman, Douglas Flynn, will retire and its directors will take a 10% fee cut. Goodman Group and Digital Realty then bought 9.9% of the Australian operator between 3 and 6 November.

The pair paid an average A$9.22 a share and kept the right to bid later. Shareholders meet on 20 November with a board-spill vote still on the agenda. 

Finland's government wants every data centre of 0.5 MW or more on a national register before construction starts. The bill gives the register's keeper no power to refuse anyone.

Sources profile:This story draws on neutral-leaning sources

Finland's government asked Parliament on 29 October to create a national register of data centres. Any site with at least 0.5 MW of computing load must report within 30 days of signing its grid contract.

The register cannot block a project. Finland runs about 285 MW of data centres against grid contracts for more than 3 GW, so ministers want to see which plans are real. 

Google will spend US$15bn on new Malaysian campuses in 2027 and 2028 and says it will pay for all the power they use. Malaysia's trade minister set those terms for data centres three weeks earlier.

Sources profile:This story draws on neutral-leaning sources

Google will invest US$15bn in Malaysia in 2027 and 2028, it said on 4 November as its first Malaysian campus opened. It will pay for all the power its new Selangor and Negeri Sembilan sites use.

That covers part of the terms trade minister Johari Abdul Ghani set out in Parliament in October. Google adds a promise to bring more than 1 GW of clean generation onto the grid. 

Sources:CRN Asia

Naver signed a US$9bn deal under which a Brookfield vehicle owns the chips and buildings and sells it computing time. Naver guarantees the fees for up to eight years.

Sources profile:This story draws on neutral-leaning sources

Naver, South Korea's largest search company, signed a US$9bn computing contract with Brookfield on 27 October, Yonhap reported. A Brookfield company will own the chips and buildings and sell computing time to Naver Cloud.

Naver guarantees the fees for up to eight years. It carries the payment risk while the assets sit with Brookfield, and the signing unlocks a US$1bn stake from Nvidia. 

Sources:Money Today

Lula told Brazil's energy council that data centres will not run on the people's electricity. His ministries are still split over gas and a levy on power bills.

Sources profile:This story draws on neutral-leaning sources

President Lula told Brazil's energy policy council on 6 November that data centres must build their own power. The decree setting rules for the Redata tax break had not been published by 9 November, a Brazilian trade outlet reported.

His ministries are split over whether gas plants count as low-emission supply. A second fight is over whether data centres would escape the levy that funds Brazil's energy subsidies. 

NERC's board adopted three mandatory reliability standards for computing loads of 50 MW or more on 26 October. FERC must approve them before they bind.

Sources profile:This story draws on neutral-leaning sources

The North American Electric Reliability Corporation adopted three grid-safety standards for large computing loads on 26 October. They apply to sites drawing at least 50 MW from lines of 100 kilovolts or more.

Federal regulators must approve them before they bind. The rules target sites that can leave the grid in seconds; in July 2024 about 1,500 MW switched to backup power during a single fault. 

Saudi Aramco now owns 49% of HUMAIN, the kingdom's state AI company, paying about US$2.6bn in cash and folding in its own computing assets. The Public Investment Fund keeps control.

Sources profile:This story draws on neutral-leaning sources

Saudi Aramco now owns 49% of HUMAIN, The Kingdom's state AI company, after its deal with the Public Investment Fund closed on 1 November. Aramco pays about US$2.6bn in cash this year.

It also hands over its own computing and digital assets. The world's largest oil exporter is now co-owner of Saudi Arabia's goal of 3 GW of AI data centres by 2030. 

Sources:Saudi Aramco

Getworks will put a container data centre inside Nippon Paper's Kushiro mill in Hokkaido, running on the mill's own grid link and generating plant. The first 6 MW is due by the end of March 2027.

Sources profile:This story draws on neutral-leaning sources

Three Japanese firms agreed on 5 November to put a container data centre inside Nippon Paper's mill at Kushiro, in Hokkaido. It should open at 6 MW by March 2027 and reach 40 MW that September.

The mill already has a grid connection and its own power plant. That lets Getworks build in about ten months, while sites near Tokyo wait years for grid capacity. 

Mooresville's commissioners voted unanimously to stop taking new data-centre applications for 12 months. A Charlotte TV station counts 56 other North Carolina towns with moratoriums.

Sources profile:This story draws on neutral-leaning sources

Mooresville's town board voted unanimously on 2 November to stop taking new data-centre applications for 12 months. Commissioners cited environmental and electrical impacts, Charlotte public radio reported.

The town north of Charlotte joins a wave of North Carolina pauses. A Charlotte TV station counts 56 other municipalities, Cary among them, so developers face a patchwork of local rules across the state. 

Sources:WFAE
Closing comments

Up. Conditions are spreading from grid operators to ministries: Norway's concession scheme and Spain's decree both move from operator practice into law. Three dated points decide the pace. Spain's government wants its decree approved before the 29 November election. FERC must receive NERC's CLO standards by 31 December 2026, and its approval makes them binding. Statnett's halt ends by 1 August 2027 at the latest, so Norway must have its functional requirements approved by RME, or extend the halt, before then.

Different Perspectives
Statnett
Statnett
Norway's grid operator stopped reserving capacity for data centres on 9 November, citing how fast they can swing their draw. It wants written functional requirements, approved by RME, before signing up more load, and expects to resume by 1 August 2027.
SpainDC
SpainDC
The operators' association says hourly renewable matching could cost 80% to 90% of a planned €66.9bn of investment to 2030. It has won a hearing before the Council of State and threatens litigation.
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
He told the Dewan Rakyat in October that data centres pay for all the grid capacity they reserve and fund upgrades to TNB's network. Google's 4 November pledge repeats those terms as its own.
Brasscom
Brasscom
Sergio Sgobbi of Brazil's technology industry association says investors face uncertainty until the Redata rules are public. Members need rulings on gas and the CDE levy after Lula said data centres must build their own power.
NEXTDC board
NEXTDC board
The board called the Goodman and Digital Realty stake opportunistic and said it had received no takeover proposal. It enters the 20 November meeting with a new chairman search, a 10% fee cut and a spill resolution on the agenda.