HE 282/2026
AI-generated illustration
LegislationFI

HE 282/2026

Finnish Government bill creating a register of data centres from 0.5 MW.

Finland's data-centre register bill went to Parliament on 29 October 2026. Any site with at least 0.5 MW of IT load would notify the National Emergency Supply Agency within 30 days of signing its grid connection agreement.

Last refreshed: 16 November 2026 · Appears in 1 active topic

Key Question

What must Finnish data centres report under HE 282/2026?

Timeline for HE 282/2026

#18 29 Oct

Set a 0.5 MW notification duty

Data Centres: Boom and Backlash: Finland plans a register of data centres
View full timeline →

Background

HE 282/2026 is the Finnish Government's bill for an act on a data-centre register (laki datakeskusrekisteristä). It went to the Eduskunta on 29 October 2026 and is due to take effect on 1 April 2027 if passed.

The National Emergency Supply Agency (Huoltovarmuuskeskus) would hold and supervise The Register. Sites with at least 0.5 MW of installed IT load must report within 30 days of signing a grid connection agreement, and always before building starts. The bill says plainly that notification is not an operating licence: the agency cannot block a project or set terms for it.

The bill sets Finland's threshold above Germany's equivalent, which starts at 0.3 MW. Parliament can still amend its scope and start date in committee.

Key Issues
Grid pipeline

Signed contracts dwarf built capacity

The numbers behind HE 282/2026 explain why it exists. The bill puts Finland's operating data-centre capacity at about 285 MW, against Fingrid connection agreements for more than 3 GW.

Fingrid's quarterly review, published the same day the bill went to Parliament, said about a third of its 50-plus new agreements in the past year went to data centres. If every current agreement were built, Finnish electricity consumption could rise by up to 40% on 2025. The Register is meant to show which of those projects are real before anyone pours concrete. Sites must notify before construction starts, and existing ones get a transition period after the planned start of 1 April 2027.

Common Questions
What is HE 282/2026?
A Finnish Government bill, sent to Parliament on 29 October 2026, creating a national register of data centres with at least 0.5 MW of IT load at the National Emergency Supply Agency.Source: HE 282/2026
When does Finland's data-centre register start?
The bill is due to take effect on 1 April 2027, with a transition for existing sites, if Parliament passes it.Source: HE 282/2026 (Edilex)
Which data centres must register in Finland?
Any site with at least 0.5 MW of installed IT load. It must notify within 30 days of signing a grid connection agreement and before construction starts.Source: HE 282/2026