TNB
Tenaga Nasional Berhad, Malaysia's national electricity utility, the largest electricity company in Southeast Asia.
Malaysia's trade minister told Parliament on 15 October that data centres now pay for all the grid capacity they book, moving upgrade costs from TNB to investors; data centres held 43% of TNB's contracted capacity in June.
Last refreshed: 18 October 2026 · Appears in 1 active topic
Can Malaysia's national grid absorb 5.9 GW of data-centre load without degrading household electricity supply?
Timeline for TNB
Mentioned in: Google to pay own power bill in Malaysia
Data Centres: Boom and BacklashMalaysia bills data centres' unused grid
Data Centres: Boom and BacklashJohor operator says it uses no fresh water
Data Centres: Boom and BacklashMalaysia urged to halt data centres
Data Centres: Boom and BacklashBackground
TNB, Tenaga Nasional Berhad, is Malaysia's national electricity utility and the largest electricity company in South-East Asia. Khazanah Nasional, the sovereign wealth fund, owns it outright, and it generates, transmits and distributes power across Peninsular Malaysia. From 15 October 2026, data centres pay TNB for all the grid capacity they book: a site that books 200 MW and draws only 100 MW is billed for the full 200, which shifts upgrade costs onto investors. Some 60 projects still waiting want 11,172 MW, nearly double what the 57 running sites draw.
That rule follows a rapid build-up on TNB's books. By June 2026 data centres held 43% of its contracted grid capacity, 5.9 GW across 38 approved projects, out of roughly 13.7 GW in total. On 26 June former Suaram director Kua Kia Soong called publicly for a moratorium on further approvals.
Operators also seek TNB as a clean-power supplier. In July ZDATA said it was finalising a renewable-supply deal with TNB for its 300 MW Iskandar Puteri facility in Johor, which runs on treated wastewater.
What percentage of Malaysia's electricity grid is taken up by data centres?
Who owns TNB, Malaysia's national electricity company?
Why is Johor rejecting some data-centre electricity applications?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 18 October 2026. Editorial standards.