Kushiro will host a container data centre inside Nippon Paper's mill under contracts signed on 5 November 2026. The first 6 MW should run by late March 2027, with 40 MW due that September.
Last refreshed: 16 November 2026 · Appears in 1 active topic
Can a Hokkaido paper mill beat Tokyo's years-long grid queue for data centres?
Timeline for Kushiro
Nippon Paper's mill to host data centre
Data Centres: Boom and BacklashBackground
Kushiro is a port city on the Pacific coast of south-eastern Hokkaido, with about 152,000 residents. Fishing, the port and paper-making have long anchored its economy.
On 5 November 2026 Getworks, Tokyo Gas Engineering Solutions and Nippon Paper Industries signed contracts to put a container data centre, built from prefabricated modules the size of shipping containers, inside Nippon Paper's Kushiro mill. Getworks plans 6 MW in service by late March 2027 and 40 MW six months later; the partners reckon the plot could eventually hold around 150 MW.
Nippon Paper's mill supplies the speed. The site already has a grid connection and its own generating plant, which Nippon Paper will use to supply the data centre, and a gas-fired hybrid supply is under study for later growth. ITmedia put the build at as little as ten months, against grid waits of several years in Inzai-Shiroi, outside Tokyo.
Where is the Kushiro data centre being built?
When will the Kushiro data centre open?
Why build a data centre at a paper mill in Hokkaido?