Getworks, a Japanese builder of container data centres, Tokyo Gas Engineering Solutions and Nippon Paper Industries signed contracts on 5 November to put a container data centre (prefabricated computing modules the size of shipping containers) inside Nippon Paper's Kushiro mill in Hokkaido1. It opens at 6 MW by the end of March 2027 and reaches 40 MW by September 2027, on a site the companies say could take up to about 150 MW.
The mill supplies the speed. It already has a grid connection and its own generating plant, which Nippon Paper will use to supply the data centre, with a gas-fired hybrid supply from Tokyo Gas Engineering Solutions under study for later. ITmedia put the build at as little as ten months, against grid waits of several years in Inzai-Shiroi, outside Tokyo2.
The Institute of Energy Economics, Japan (IEEJ) set out Japan's tightening grid timetable on 23 October: capacity release and cost settlement for customers of 30 MW and above from April 2027, by IEEJ's account3. Kenichi Onishi's briefing for IEEJ recommends minimum and exit charges so that grid built for data centres that never arrive is not paid for by households. Around Tokyo, the fight has reached the courts, with Akishima residents preparing to sue.