DESNZ (the Department for Energy Security and Net Zero) published its response to the strategic-demand consultation on Wednesday 28 October, after 156 replies1. Grid capacity can now be reserved for named government-backed projects, capacity freed when others leave the queue can be handed to them, and they can be accelerated within a connection batch.
"Strategic" will not be defined in regulation. A project qualifies through sponsorship by a UK department, a devolved government or a mayoral authority, with no megawatt threshold. That leaves the queue order to ministerial judgement: a project's place depends on who sponsors it. The response came out the same day as the Treasury's Data Centre Covenant.
After 2030, a cap follows: data-centre connections will be aligned to regional targets set on grid capacity, expected demand, water and land, at a future application window run by NESO (the National Energy System Operator), after another consultation. Moving existing contracts to strategic projects is only "under consideration", and the government is "not committing to an auction mechanism".
Most of the response is about speed. It is built to connect favoured sites faster. At Loughton in Essex, Microsoft pulled out as anchor tenant of the AI data-centre developer Nscale. UK press reports said grid officials had warned the site might not get power until the 2030s, and Nscale blamed "this unfortunate London-wide grid issue". Microsoft said only that its decision related to a single site. The regional cap, the one part that restricts data centres, applies only from 2030.