Finland's government sent Parliament a bill (government proposal HE 282/2026) on Thursday 29 October, creating a national register of data centres at the National Emergency Supply Agency (Huoltovarmuuskeskus)1. Any site with at least 0.5 MW of IT load must notify the agency within 30 days of signing its grid connection agreement, and always before construction starts.
The bill says plainly that the register "would not be an operating licence". The agency cannot approve, refuse or attach conditions to a project. The register is due to take effect on 1 April 2027, with a transition for existing sites; Germany's equivalent starts at 0.3 MW.
The bill's own figures show why Helsinki wants to see the pipeline. About 285 MW of data centres operate in Finland, against connection agreements with Fingrid, the national grid operator, for more than 3 GW (gigawatts) of projects. Fingrid's quarterly review, published the same day, says about a third of its 50-plus new agreements in the past year went to data centres, and that if every current agreement is built, Finnish consumption could rise by up to 40% on 20252.
Fingrid warned in August that a signed agreement guarantees nothing. Finland's answer is to count the contracts before anyone pours concrete, and leave the grid queue as it stands.