
FERC
US energy regulator; weighing six grid operators' November 2026 plans for connecting data centres.
In late November 2026 FERC had six grid operators' plans for cheaper, interruptible data-centre power on its desk, with cut-off prices from $25 to $250 per MWh, and NERC's computing-load standards due before it by 31 December.
Last refreshed: 26 November 2026 · Appears in 1 active topic
FERC's adequacy deadline landed days after MISO's second emergency - is supply already behind?
Timeline for FERC
Received the six grid operators' large-load filings
Data Centres: Boom and Backlash: Four US grids price data-centre cut-offsNERC adopts first data-centre grid rules
Data Centres: Boom and BacklashIssued Order 636, the gas-pipeline reservation-charge precedent
Data Centres: Boom and Backlash: Mentioned in: Malaysia bills data centres' unused gridLeft the 50 MW/100 kV threshold to NERC
Data Centres: Boom and Backlash: NERC large-load rules pass first ballotGranted abeyance to 16 November after five operators missed its deadline
Data Centres: Boom and Backlash: Five grid operators miss FERC deadlineBackground
FERC, the Federal Energy Regulatory Commission, regulates US interstate electricity transmission and wholesale power markets. By late November 2026 its desk held the plans six grid operators filed for interruptible data-centre power, and NERC's first computing-load standards were due before it by 31 December.
The docket traces back to 23 October 2025, when FERC received a directive from Energy Secretary Chris Wright, under Section 403 of the Department of Energy Organization Act, to write large-load rules. FERC answered in June 2026 with Section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO New England and NYISO, its slowest procedural route, which pushed any binding standard to 2027 at the earliest. It then told the same six to report by 20 July whether their supply could keep up with forecast demand.
Reliability rules also run through the Commission. NERC's board adopted standards CLO-001 to CLO-003 on 26 October for computing loads of 50 MW or more on lines of 100 kV and above. Five days earlier NERC had asked FERC to create registration categories for the owners and operators of such sites. None of these rules binds until FERC approves it.
FERC weighs six interruptible-power plans
FERC promised on 16 April 2026 to decide by June how loads above 20 MW join the interstate grid, under docket RM26-4-000. On 18 June it chose show-cause orders over a national rule, making each of its six regional operators defend or Reform its own tariff. Five of them then missed its 17 August deadline and won more time, to 16 November.
The answers came in between 13 and 20 November. Each operator offers data centres a non-firm tier that can be switched off. SPP would cut that load to zero once the local price passes $25 per MWh, MISO at $100, NYISO caps non-firm bids at $200 and ISO New England orders cutbacks at $250. PJM and CAISO named no price. FERC has accepted none of the six, and states and utilities can still contest them.
FERC extends its large-load inquiry
Has FERC approved the grid operators' data-centre connection plans?
Did FERC issue a final rule on data centre grid connections in June 2026?
Why did MISO's grid emergency happen just before FERC's adequacy deadline?
What generation-adequacy reports did FERC require by 20 July 2026?
What is FERC and what powers does it have over data centres?
Why are hyperscalers fighting the FERC interconnection queue?
How will FERC's large load rulemaking affect data centres?
Can FERC force data centres to switch off during a grid emergency?
Reference
Does FERC have authority over the Texas ERCOT grid?
What is FERC and what does it regulate?
Who directs FERC and how are its commissioners appointed?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.