Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
FERC
AI-generated illustration
OrganisationUS

FERC

US energy regulator; weighing six grid operators' November 2026 plans for connecting data centres.

In late November 2026 FERC had six grid operators' plans for cheaper, interruptible data-centre power on its desk, with cut-off prices from $25 to $250 per MWh, and NERC's computing-load standards due before it by 31 December.

Last refreshed: 26 November 2026 · Appears in 1 active topic

Key Question

FERC's adequacy deadline landed days after MISO's second emergency - is supply already behind?

Timeline for FERC

#19 20 Nov

Received the six grid operators' large-load filings

Data Centres: Boom and Backlash: Four US grids price data-centre cut-offs
#18 26 Oct

NERC adopts first data-centre grid rules

Data Centres: Boom and Backlash
#16 15 Oct

Issued Order 636, the gas-pipeline reservation-charge precedent

Data Centres: Boom and Backlash: Mentioned in: Malaysia bills data centres' unused grid
#15 18 Sept

Left the 50 MW/100 kV threshold to NERC

Data Centres: Boom and Backlash: NERC large-load rules pass first ballot
#14 17 Aug

Granted abeyance to 16 November after five operators missed its deadline

Data Centres: Boom and Backlash: Five grid operators miss FERC deadline
View full timeline →

Background

FERC, the Federal Energy Regulatory Commission, regulates US interstate electricity transmission and wholesale power markets. By late November 2026 its desk held the plans six grid operators filed for interruptible data-centre power, and NERC's first computing-load standards were due before it by 31 December.

The docket traces back to 23 October 2025, when FERC received a directive from Energy Secretary Chris Wright, under Section 403 of the Department of Energy Organization Act, to write large-load rules. FERC answered in June 2026 with Section 206 show-cause orders to PJM, MISO, SPP, CAISO, ISO New England and NYISO, its slowest procedural route, which pushed any binding standard to 2027 at the earliest. It then told the same six to report by 20 July whether their supply could keep up with forecast demand.

Reliability rules also run through the Commission. NERC's board adopted standards CLO-001 to CLO-003 on 26 October for computing loads of 50 MW or more on lines of 100 kV and above. Five days earlier NERC had asked FERC to create registration categories for the owners and operators of such sites. None of these rules binds until FERC approves it.

Key Issues
Large-load docket

FERC weighs six interruptible-power plans

FERC promised on 16 April 2026 to decide by June how loads above 20 MW join the interstate grid, under docket RM26-4-000. On 18 June it chose show-cause orders over a national rule, making each of its six regional operators defend or Reform its own tariff. Five of them then missed its 17 August deadline and won more time, to 16 November.

The answers came in between 13 and 20 November. Each operator offers data centres a non-firm tier that can be switched off. SPP would cut that load to zero once the local price passes $25 per MWh, MISO at $100, NYISO caps non-firm bids at $200 and ISO New England orders cutbacks at $250. PJM and CAISO named no price. FERC has accepted none of the six, and states and utilities can still contest them.

Common Questions

FERC extends its large-load inquiry

Has FERC approved the grid operators' data-centre connection plans?
Not yet. The six grid operators FERC regulates filed their answers to its large-load show-cause orders between 13 and 20 November 2026, after five of them won an abeyance from the 17 August deadline. FERC had accepted none of the six grid operators' plans by 20 November. States and utilities can still contest them.Source: FERC
Did FERC issue a final rule on data centre grid connections in June 2026?
No. On 18 June 2026 FERC issued Section 206 show-cause orders to all six US regional transmission organisations instead of a final rule. The operators filed their answers between 13 and 20 November 2026. FERC had accepted none of the six grid operators' plans by 20 November.Source: FERC
Why did MISO's grid emergency happen just before FERC's adequacy deadline?
MISO declared its second maximum-generation emergency of July on 15 July 2026 as a heat dome pushed demand to a 122 GW peak, five days before the 20 July deadline FERC set for RTOs to certify generation adequacy, exposing the exact supply gap the docket was opened to examine.Source: Lowdown data-centres update 11
What generation-adequacy reports did FERC require by 20 July 2026?
FERC's Docket RM26-4-000 required all six US regional transmission organisations, PJM, MISO, SPP, CAISO, ISO-NE and NYISO, to file reports by 20 July 2026 explaining how they intend to ensure adequate generation for existing and new large loads such as data centres.Source: FERC RM26-4-000
What is FERC and what powers does it have over data centres?
FERC is the US Federal Energy Regulatory Commission, which regulates interstate electricity transmission and wholesale power markets. Its large-load proceeding, Docket RM26-4-000, decides how data centres connect to the grid. Emergency Section 202(c) orders, such as the one PJM received on 18 May 2026, come from the Department of Energy.Source: FERC
Why are hyperscalers fighting the FERC interconnection queue?
Standard interconnection studies can delay grid connections by years and impose large cost-allocation charges on the connecting customer. Hyperscalers are seeking a fast-tracked large-load pathway that RM26-4-000 is intended to create; the contested question is whether that pathway shifts upgrade costs to existing ratepayers.Source: Mayer Brown / data-centres update 2
How will FERC's large load rulemaking affect data centres?
The RM26-4-000 order will determine whether hyperscalers can bypass standard interconnection studies, how behind-the-meter gas is treated for cost allocation, and who pays for grid upgrades triggered by large loads.Source: Mayer Brown legal analysis
Can FERC force data centres to switch off during a grid emergency?
Not directly. Emergency Section 202(c) orders come from the Department of Energy, which on 18 May 2026 let PJM curtail data centres with behind-the-meter backup generation. FERC acts through tariffs: the grid operators' November 2026 filings propose non-firm service that is cut off at set prices.Source: Department of Energy

Reference

Does FERC have authority over the Texas ERCOT grid?
No. ERCOT operates as an island grid outside both the Eastern and Western Interconnection, so it is not subject to FERC jurisdiction over interstate transmission. Data centre operators in West Texas can therefore avoid FERC's interconnection queue entirely.Source: FERC jurisdictional scope
What is FERC and what does it regulate?
The Federal Energy Regulatory Commission (FERC) is a US Independent agency that regulates the interstate transmission of electricity, natural gas, and oil, and oversees wholesale electricity markets run by RTOs and ISOs across the continental US.Source: FERC official website
Who directs FERC and how are its commissioners appointed?
FERC has five commissioners appointed by the President and confirmed by the Senate, serving staggered terms. The chair is Swett. FERC is Independent of the executive branch but can be directed to open specific proceedings under Section 403 of the DOE Organisation Act.Source: FERC governance
Source Material

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.