South Korea's largest internet company, running search, commerce and cloud services.

South Korea's largest internet company signed a US$9bn contract with Brookfield on 27 October 2026 to rent AI computing rather than own it, guaranteeing the fees for up to eight years. The signing unlocked a US$1bn equity stake from Nvidia.

Last refreshed: 16 November 2026 · Appears in 1 active topic

Key Question

Why is Naver renting its AI chips instead of buying them?

Timeline for Naver

#18 27 Oct

Signed a US$9bn compute contract and guaranteed the fees

Data Centres: Boom and Backlash: Naver rents AI capacity from Brookfield
View full timeline →

Background

Naver runs South Korea's leading search engine, alongside businesses in commerce, fintech, cloud computing and AI. It was founded in 1999 and is based in Seongnam, south of Seoul. Its cloud Arm, Naver Cloud, sells computing to businesses and the public sector.

On 27 October 2026 Naver turned a July term sheet with Brookfield into a binding US$9bn (12 trillion won) contract. A Brookfield vehicle buys the GPUs and data-centre buildings and sells computing capacity to Naver Cloud; Naver guarantees the fees for up to eight years. The chips sit off Naver's balance sheet, while the payment risk stays with it.

The contract met the condition for Nvidia's US$1bn equity investment in Naver. The first site is a campus in Sejong, planned at 55 MW in the first half of 2027 and 200 MW by 2028. Renting capacity lets Naver compete for AI compute with US hyperscalers without carrying the hardware itself.

Common Questions
What is the Naver and Brookfield deal?
Naver signed a US$9bn computing contract with Brookfield on 27 October 2026. A Brookfield vehicle owns the GPUs and data centres and sells computing capacity to Naver Cloud.Source: Money Today
Why is Nvidia investing in Naver?
Nvidia agreed to invest US$1bn in Naver once Naver secured at least US$9bn of financing for its AI infrastructure. The Brookfield contract met that condition.Source: Nvidia
Where is Naver building its AI data centre?
The first site is a campus in Sejong, due to reach 55 MW in the first half of 2027 and 200 MW by 2028.Source: Money Today
Does Naver own the GPUs in the Brookfield deal?
No. A Brookfield vehicle owns the chips and buildings, but Naver guarantees the fees for up to eight years, so the payment risk stays with Naver.Source: Money Today