26NOV

FERC delays its grid rule to 2027

3 min read
18:00UTC

FERC met its end-June deadline on 18 June, then chose its slowest tool: show-cause orders to all six US grid operators instead of the connection rule it promised in April. Any binding standard now slips to 2027 at the earliest.

IndustryDeveloping
Key takeaway

FERC's slowest tool pushes any binding large-load connection rule to 2027, after most near-term capacity is committed.

The Federal Energy Regulatory Commission (FERC), the US regulator for interstate power transmission, met its end-June deadline on 18 June and then reached for its slowest instrument. Rather than issue the large-load connection rule it pledged in April, FERC sent Section 206 show-cause orders, which compel each operator to justify or change its existing rules, to all six US regional transmission organisations (RTOs): PJM, MISO, SPP, CAISO, ISO-NE and NYISO⁠1.

Each RTO must now defend or reform its tariffs across five areas, from study processes to co-location terms, the same co-located load question PJM was ordered to file on in May. Resource-adequacy reports are due 20 July, show-cause responses 17 August, and public comments 16 September, with the RM26-4-000 docket left open and no rule attached. Industry lawyers expect six to eighteen months from a show-cause order to a final order, which puts any binding standard in 2027 at the earliest.

Show-cause puts the burden on each operator to prove its existing rules are just and reasonable, which reads as aggressive but actually buys time: FERC can let six separate proceedings run rather than defend one nationwide rule through the appeal courts. Six dockets also multiply the points where reform can stall or be litigated, and connection-side certainty slips past the window in which most near-term capacity is being committed. FERC counted 75 GW of new summer capacity since 2025, yet PJM still declared a grid emergency in May.

Deep Analysis

In plain English

FERC is the US Federal Energy Regulatory Commission, the federal agency that sets the rules for how electricity flows across state lines. In April 2026, FERC promised it would publish new rules by the end of June on how data centres get connected to the national grid, since the existing queue was taking years to clear. On 18 June, FERC met that deadline, but only barely: instead of publishing new rules, it sent formal questions to the six companies that run different regions of the US electricity grid, asking them to explain or reform their own existing rules. Those six companies, called RTOs (Regional Transmission Organisations), manage the grid in different regions: PJM covers the eastern US, MISO the Midwest, SPP the central plains, CAISO California, ISO-NE New England, and NYISO New York. Each has its own rules for how data centres connect. The responses are due through September 2026, meaning no binding new rule can arrive before 2027 at the earliest.

Deep Analysis
Root Causes

FERC's procedural choice reflects two structural problems it cannot solve by rulemaking alone.

First, the six US RTOs operate under different state utility commissions with different regulatory priorities. PJM's co-location problem, driven by Northern Virginia's hyperscale density, is structurally different from CAISO's, where BTM generation is already restricted under California air-quality rules. A single FERC rule must accommodate that variance, which requires the show-cause process to surface each RTO's specific constraints before FERC can write a standard.

Second, FERC has no authority over behind-the-meter generation that never crosses the interstate transmission system. The fastest-growing segment of data-centre power, captive co-located gas plants like Project Kilby, sits outside FERC's primary jurisdiction entirely. Show-cause orders to RTOs cannot reach that category of demand; they address only the grid-connection queue for facilities that do use the transmission system.

Escalation

FERC's choice of show-cause over direct rulemaking signals institutional caution rather than escalation. The direction is toward slower resolution, not faster. Three of the six RTOs face Fifth Amendment challenges to their curtailment authority, which may have influenced FERC's choice to build a stronger evidentiary record through show-cause before issuing a rule that could face the same legal exposure.

What could happen next?
  • Consequence

    Binding large-load connection standards across all six US RTOs will not arrive before 2027 at the earliest, leaving the period of maximum data-centre investment without a federal framework for the most contested terms.

    Medium term · Assessed
  • Risk

    Six separate show-cause responses may produce six divergent tariff reforms, creating regulatory arbitrage between grid territories that operators can exploit by choosing connection location.

    Medium term · Suggested
  • Opportunity

    The 20 July resource-adequacy reports due from RTOs will produce the first official disclosure of each region's data-centre load forecast, creating a public data baseline the industry has previously had only through unofficial ERCOT disclosures.

    Immediate · Assessed
First Reported In

Update #8 · Data centres build their own power plants

FERC· 28 Jun 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.