
PJM Interconnection
US grid operator; 2027/28 capacity auction cleared 6,623 MW short of its reserve target.
PJM Interconnection, the largest US grid operator, opened a backstop capacity auction on 31 July at a $555/MW-day cap to close a 6,831 MW shortfall against its 2028/29 reliability requirement.
Last refreshed: 4 August 2026 · Appears in 1 active topic
PJM's capacity auction fell short years ahead of delivery - is the grid already overcommitted?
Timeline for PJM Interconnection
Filed a curtailment rule for 50 MW-plus loads at FERC under docket ER26-3380-000
Data Centres: Boom and Backlash: PJM wants 50 MW loads curtailablePJM's backstop auction opens at $555
Data Centres: Boom and BacklashFell 6,623 MW short in its 2027/28 capacity auction, setting a 21 July procurement deadline
Data Centres: Boom and Backlash: PJM auction falls 6,623 MW shortFERC sets a 20 July adequacy deadline
Data Centres: Boom and BacklashMentioned in: MISO's second grid emergency in July
Data Centres: Boom and BacklashBackground
PJM Interconnection is the largest regional transmission organisation in the United States, coordinating electricity transmission across a 14-state region plus Washington DC, including Northern Virginia, the world's largest data-centre market. Founded in 1927 as the Pennsylvania-New Jersey Interconnection and designated an RTO by FERC in 2001, it now manages roughly 182 GW of generating capacity over 88,333 miles of transmission line.
Data-centre demand has driven roughly 5% annual load growth across PJM's territory since 2024, straining a grid built for slower growth. The Department of Energy has invoked emergency Section 202(c) authority three times in 2026 to force large PJM-area data centres onto backup generation during heat emergencies, the first such curtailment of data-centre load in RTO history.
That pressure has pushed PJM into the centre of a federal reckoning over who pays for grid expansion driven by co-located computing load, with FERC's RM26-4-000 rulemaking treating PJM's tariff filings as the template other US grid operators will be measured against.
PJM opens a backstop capacity auction
PJM's 2027/28 capacity auction cleared 6,623 MW short of its reliability requirement, so on 31 July it filed with FERC for a one-time backstop auction running 30 September to 21 October at a $555/MW-day price cap, well above the $325 base cap. The backstop targets a 6,831 MW gap against the 2028/29 delivery year, a shortfall Utility Dive separately estimated could cost up to $20bn through 2027.
The shortfall sits inside a wider federal process: FERC's RM26-4-000 docket required PJM and five peer grid operators to file generation-adequacy reports by 20 July, and PJM's own show-cause response on large-load tariffs is due 17 August. PJM's board separately warned 13 governors in May that reinforcement costs could land on household bills unless states set cost-allocation rules first.