Skip to content
You can now search across every topic, entity and event.What's new
PJM Interconnection
OrganisationUS

PJM Interconnection

US grid operator; facing FERC tariff deadline over co-located data-centre loads above 20 MW.

Last refreshed: 28 June 2026 · Appears in 1 active topic

Key Question

PJM just switched off data centres for the first time — is 5% annual demand growth now outrunning even record capacity additions?

Timeline for PJM Interconnection

#1019 Jul

FERC sets a 20 July adequacy deadline

Data Centres: Boom and Backlash
#106 Jul
#1029 Jun

Ireland codes a 900 MW load-loss limit

Data Centres: Boom and Backlash
#822 Jun
#818 Jun

Received show-cause order to justify or reform large-load tariffs across five categories

Data Centres: Boom and Backlash: FERC delays its grid rule to 2027
View full timeline →
Common Questions
What is the FERC show-cause order served on PJM in June 2026?
On 18 June 2026, FERC issued Section 206 show-cause orders to PJM and five other US grid operators, requiring them to justify their large-load interconnection tariffs or propose reforms across five categories, including co-located data-centre load. Responses are due 17 August 2026.Source: FERC
How much new generating capacity has been added to the US grid to handle data-centre growth?
FERC reported a 75 GW increase in US summer generating capacity since 2025, with Texas grid operator ERCOT adding approximately 26 GW alone. Despite this, PJM still triggered emergency curtailment protocols in May 2026, showing that demand growth is outpacing even record supply additions.Source: Lowdown data-centres update 4
Why has PJM's capacity auction cost risen eightfold?
Data-centre-driven demand growth of approximately 5% annually has outrun new generation additions. PJM's most recent forward capacity auction resulted in the first-ever shortfall in the RTO's history — it could not procure 100% of required capacity — and auction clearing prices rose approximately eightfold year-on-year.Source: Lowdown data-centres update 4

Background

PJM Interconnection is the largest regional transmission organisation in the United States, coordinating electricity transmission across a 14-state region plus Washington DC. Its footprint includes Northern Virginia, the world's largest data-centre market, as well as Ohio, Pennsylvania, and New Jersey. In May 2026, PJM became the first RTO in the country to execute a Section 202(c) emergency curtailment order targeting data-centre load: the DOE on 18 May 2026 granted PJM authority to switch off data centres equipped with behind-the-meter backup generation during a heat event, with Maryland and Virginia facing the most acute strain. PJM recorded a peak-load forecast of 135,961 MW with more than 40 GW of plant offline for maintenance.

Despite a 75 GW increase in US generating capacity since 2025, including approximately 26 GW from ERCOT alone, PJM still triggered emergency protocols in mid-May, demonstrating that new supply has not kept pace with data-centre-driven demand growth of approximately 5% annually. PJM's capacity auctions have come under severe pressure, with costs rising approximately eightfold year-on-year in the most recent forward auction, a first-ever shortfall in the RTO's history. On 18 June 2026, FERC issued PJM and five other RTOs Section 206 show-cause orders, requiring tariff justification or reform across five areas including co-located load terms; show-cause responses are due 17 August 2026, public comments 16 September. The anticipated binding June rule was replaced by this slower process, pushing a final large-load standard to 2027 at the earliest.

More questions
Did PJM actually switch off data centres in 2026?
Yes. The US Department of Energy issued a Section 202(c) order on 18 May 2026 granting PJM authority to curtail data centres with behind-the-meter backup generation during a heat emergency. PJM recorded a peak-load forecast of 135,961 MW with more than 40 GW of plant offline for maintenance.Source: Lowdown data-centres update 4
What is PJM Interconnection and why is it important for data centres?
PJM Interconnection is the largest US regional transmission organisation, covering 14 states plus DC including Northern Virginia — the world's largest data-centre market. It manages 182 GW of generating capacity and is the grid operator directly responsible for executing the first-ever Section 202(c) data-centre curtailment order in May 2026.Source: Lowdown data-centres update 4
Why is PJM's electricity grid struggling with data-centre demand?
PJM's region includes Northern Virginia, the world's largest data-centre cluster, and faces 5% annual demand growth from hyperscalers — a reversal after 15 years of flat load from 2005 to 2020. The grid was not built for this growth rate: transformer lead times are five years and interconnection queues run to hundreds of gigawatts.Source: Wikipedia / Lowdown data-centres
What states are in the PJM grid region?
PJM covers all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia, and Washington DC — the core of the US Eastern Interconnection between the Midwest and Atlantic coast.Source: Wikipedia
Source Material