Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
2JUN

DOE curtailment order faces taking claim

3 min read
10:42UTC

Parties challenging the DOE's Section 202(c) curtailment order filed a rehearing on 28 May, calling it a physical and regulatory taking of property without compensation.

IndustryDeveloping
Key takeaway

The DOE 202(c) rehearing tests whether emergency curtailment counts as a compensable seizure of property.

Parties challenging the DOE (Department of Energy) Section 202(c) curtailment order, Order 202-26-06, filed a rehearing request on 28 May 2026 arguing it is "both a physical taking and a regulatory taking" of property without just compensation. The order is the same emergency authority that PJM now wields over backup-equipped data-centre generators . The petition lands at FERC (Federal Energy Regulatory Commission), where resolution is not expected before 2027.

This challenge borrows the constitutional weapon RCM Hill aimed at Hill County the same week, but the federal facts cut the other way. A construction moratorium stops a project that never started; curtailment reaches into a running facility and orders its operator to shed load on command, which is why the petitioners frame it as a physical seizure of generating equipment, not merely a limit on use.

The counter-argument rests on a century of utility law. Section 202(c) of the Federal Power Act lets the DOE compel generation and load-shedding during a grid emergency, and courts have long treated emergency curtailment as conditional regulatory power rather than a compensable taking. DOE lawyers argue a data centre running a backup generator accepted that reliability condition the day it interconnected. Whether FERC and the courts accept the seizure framing will set the price of every future emergency order against a data centre.

Deep Analysis

In plain English

The US Department of Energy has the power, under a law called Section 202(c) of the Federal Power Act, to order certain large electricity users to cut their power use during a grid emergency, like an extreme heat event. In May 2026, DOE used this law to allow PJM, the grid operator, to switch off backup generators at data centres if needed. Now, the companies affected are arguing that this is unconstitutional. They say the government is effectively taking their property, the backup generators they own, without paying them compensation. Under the US Constitution's Fifth Amendment, the government must pay fair value when it takes private property. The same constitutional argument appears in the Hill County case (ID:3052), making this a coordinated legal challenge across two different levels of government.

Deep Analysis
Root Causes

Section 202(c) of the Federal Power Act predates the data-centre era by nearly 90 years and was written for fuel-supply and physical-plant emergencies affecting public utilities. It grants the Secretary of Energy authority to order temporary generation and load-curtailment measures during a reliability emergency, but its legislative history contains no reference to private commercial buildings, behind-the-meter backup generation, or AI compute loads.

The absence of a settled statutory framework for managing large dispatchable private loads, precisely the gap that FERC's Docket RM26-4-000 is meant to close, forces the DOE to use emergency authority as a workaround.

The taking challenge will not resolve before 2027 because it depends on FERC's RM26-4-000 rulemaking establishing the permanent framework. Until that rule sets what obligations data-centre operators carry as a condition of grid connection, every 202(c) order is litigable as either an overstep of emergency authority or a regulatory taking of property that was never explicitly made subject to grid-control conditions in the first place.

What could happen next?
  • Risk

    A court ruling that repeated use of Section 202(c) for a structural load-management problem violates procedural requirements would force the DOE to pursue notice-and-comment rulemaking, removing emergency curtailment as a tool until a formal rule is in place, potentially through 2028.

    Medium term · Suggested
  • Precedent

    If the taking theory survives threshold review and reaches a damages assessment, it would set a price for all future grid emergency curtailments applied to private commercial buildings, changing the risk calculus for every future DOE 202(c) order.

    Long term · Suggested
  • Consequence

    Uncertainty over curtailment authority accelerates data-centre operators' investment in physical islanding, where a campus generates and stores its own power and reduces reliance on grid-connected backup, to remove the regulatory handle DOE is using.

    Short term · Suggested
First Reported In

Update #5 · Who pays when the grid bends for AI

PJM Interconnection· 2 Jun 2026
Read original
Different Perspectives
Singapore / IMDA
Singapore / IMDA
IMDA's Green Data Centre Roadmap releases 500 MW under non-negotiable PUE 1.3, liquid-cooling, and green-energy conditions set before construction, ending a seven-year freeze without triggering the consent or cost fights fragmenting three US regulatory fronts simultaneously.
US residential electricity ratepayers and community residents
US residential electricity ratepayers and community residents
Households in PJM's 13 states face grid-reinforcement costs defaulting to their bills if states miss the September deadline, while Lake Anna residents face a cooling-water permit that can clear Virginia law without any PFAS monitoring. Both costs are externalised at the regulatory stage and disputed only after the fact.
EdgeConneX in Italy (EU market)
EdgeConneX in Italy (EU market)
EdgeConneX committed €3bn to Italian data-centre capacity starting in 2026, routing capital to a jurisdiction where AI Act and NIS2 mandates create structural demand for EU-resident compute and the government actively attracts investment; Virginia's fiscal standoff and US moratoriums are redirecting pipeline offshore.
Enbridge and Baker Hughes (firmed-power and oilfield-services suppliers)
Enbridge and Baker Hughes (firmed-power and oilfield-services suppliers)
Enbridge committed $1.2bn to Wyoming solar-plus-storage for Meta and Baker Hughes redirected oilfield drilling capacity into enhanced geothermal in New Mexico; both companies are routing capital away from fossil infrastructure into data-centre power procurement at precisely the moment BTM gas became a federal curtailment target.
US federal regulators (DOE and FERC)
US federal regulators (DOE and FERC)
DOE reached for Section 202(c) twice in five months naming the same BTM load class, while FERC rejected PJM's bid to redefine the 20 MW co-located load threshold in April; together they have treated private data-centre generation as a dispatchable grid resource before the permanent RM26-4-000 rule settling its legal status has been written.
European energy regulators and climate advocates
European energy regulators and climate advocates
GE Vernova's 100 GW gas-turbine backlog, driven by AI data-centre demand, puts IEA net-zero pathways under pressure: 15-27 GW of onsite gas is forecast for US data centres by 2030. The Amazon Boardman $20.5m pollution settlement gives environmental litigation a financial template it previously lacked.