Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
CAISO
AI-generated illustration
OrganisationUS

CAISO

California Independent System Operator, managing electricity transmission across California and a small part of Baja California.

CAISO and PJM were the two of six US grid operators whose November 2026 plans for interruptible data-centre power named no price at which a site would be cut off; FERC had accepted none by 20 November.

Last refreshed: 26 November 2026 · Appears in 1 active topic

Key Question

How will CAISO balance California's clean-energy mandates with FERC's demand for large-load tariff reforms?

Timeline for CAISO

#19 20 Nov

Filed a non-firm plan with no price threshold

Data Centres: Boom and Backlash: Four US grids price data-centre cut-offs
#14 17 Aug
#12 23 Jul

Targeted a 16 November filing

Data Centres: Boom and Backlash: Six US grid operators file, none say yes
#10 19 Jul
#8 18 Jun

Received show-cause order to justify or reform large-load tariffs

Data Centres: Boom and Backlash: FERC delays its grid rule to 2027
View full timeline →

Background

CAISO, the California Independent System Operator, runs the high-voltage grid and wholesale electricity market for most of California and a small part of Baja California in Mexico. It is one of the six regional transmission organisations that answer to the Federal Energy Regulatory Commission, alongside PJM, MISO, SPP, ISO New England and NYISO.

That status puts it inside the federal effort to set rules for connecting data centres and other loads above 20 MW, docket RM26-4-000. In May 2026 PJM's co-location filing was framed as the template against which CAISO, ERCOT and MISO would be judged. When the six operators filed generation-adequacy reports in July, none said it could serve its data-centre queue under current rules.

Because FERC answered with six separate orders rather than one rule, CAISO's own tariff choices decide how California's data centres connect, and any binding federal standard is unlikely before 2027.

Key Issues
Large-load rules

CAISO names no cut-off price

FERC chose show-cause orders over a single national rule on 18 June 2026, telling CAISO and the other five regulated operators to justify or Reform their large-load tariffs, from study processes to co-location terms. CAISO filed a generation-adequacy report on 20 July and, with SPP, was the slowest of the six, aiming for a 16 November answer.

The answers that arrived between 13 and 20 November each offered data centres cheaper power that can be interrupted. Four operators set a trigger price, from $25 to $250 per megawatt-hour. CAISO, like PJM, set none, so the point at which a California data centre would lose supply stays undefined while FERC weighs the plans.

Common Questions

Reference

How do California's air-quality rules affect data-centre co-location at CAISO?
California's state air-quality rules restrict certain forms of behind-the-meter generation, which makes CAISO's approach to data-centre co-location structurally different from other US RTOs handling the same FERC show-cause order.
What is CAISO and which grid does it manage?
CAISO (California Independent System Operator) manages high-voltage electricity transmission across approximately 80% of California and a small part of Baja California. It is one of six US Regional Transmission Organisations under FERC jurisdiction.
Does CAISO set a price at which data centres lose power?
No. CAISO proposed a cheaper non-firm service for large loads but, like PJM, set no price threshold. SPP, MISO, NYISO and ISO New England each named one.Source: CAISO filing to FERC
Why did FERC send CAISO a show-cause order in June 2026?
FERC issued CAISO a Section 206 show-cause order on 18 June 2026 as part of a six-operator proceeding, directing each to justify or Reform its large-load tariffs. CAISO's answer was filed between 13 and 20 November 2026. FERC had accepted none of the six grid operators' plans by 20 November.Source: FERC
Why is FERC's RM26-4-000 rulemaking not one single national rule?
FERC chose to issue six separate show-cause orders rather than a single national rule, letting CAISO and its peer RTOs tailor large-load tariff reforms to their own regional regulatory environments, but leaving operators without a harmonised standard until at least 2027.Source: FERC
Source Material

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.