Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
SPP
AI-generated illustration
OrganisationUS

SPP

Southwest Power Pool, the regional transmission organisation covering 14 US central states.

As of November 2026, SPP has offered data centres interruptible power at $25 per megawatt-hour, the lowest trip price filed by any US grid operator in The Week to 20 November.

Last refreshed: 26 November 2026 · Appears in 1 active topic

Key Question

Can SPP's wind corridor absorb data-centre demand flowing away from Texas's congested ERCOT queue?

Timeline for SPP

#19 20 Nov

Filed a $25/MWh non-firm service and 40-year upgrade cost assignment

Data Centres: Boom and Backlash: Four US grids price data-centre cut-offs
#12 23 Jul

Targeted a 16 November filing

Data Centres: Boom and Backlash: Six US grid operators file, none say yes
#8 18 Jun

Received show-cause order to justify or reform large-load tariffs

Data Centres: Boom and Backlash: FERC delays its grid rule to 2027
View full timeline →

Background

SPP, the Southwest Power Pool, is the regional transmission organisation for 14 central US states. Data centres seeking a connection anywhere in that footprint deal with SPP's rules, under oversight from the Federal Energy Regulatory Commission.

Those rules came under federal scrutiny in 2026. All six regional operators had to file generation-adequacy reports on 20 July, and none of them, SPP included, said it could serve its queue under existing rules. the Commission had already put binding large-load standards back to 2027 at the earliest.

SPP's $25 trip price now gives the clearest test of whether a low price draws data centres into accepting cut-offs in exchange for a quicker hook-up.

Key Issues
Interruptible service

SPP files the cheapest cut-off price

SPP lodged its non-firm large-load service plan on 20 November 2026, pricing power that can be curtailed at $25 per megawatt-hour. Four operators named a trip price that week, across a span of $25 to $250, and SPP's figure sat at the bottom. A site taking SPP's terms trades the risk of being cut off for a faster connection, once federal approval arrives.

SPP's filing came out of the federal review launched on 18 June 2026, when show-cause questions went to all six regional operators and binding rules slipped to 2027. By early August SPP was working to a 16 November filing date. Its 20 July adequacy report, like the other five, stopped short of promising capacity for its data-centre queue.

Common Questions

Reference

What is the Southwest Power Pool and which states does it cover?
SPP (Southwest Power Pool) manages electricity transmission across 14 US states in the central Plains, including Kansas, Oklahoma, Nebraska, Missouri, and North Dakota. It is a non-profit, member-owned organisation and one of six RTOs under FERC oversight.
How would SPP charge data centres for grid upgrades?
SPP proposed assigning upgrade costs above a safe harbour of $500,000 per MW, capped at $25m per request, to the customer for up to 40 years. Its non-firm service would cut load to zero when the price passes $25/MWh.Source: SPP filing to FERC
What did FERC require from SPP in June 2026 on data-centre connections?
FERC issued SPP a Section 206 show-cause order on 18 June 2026, directing it to justify or Reform its large-load tariffs. SPP's answer was among the six filed between 13 and 20 November 2026. FERC had accepted none of the six grid operators' plans by 20 November.Source: FERC
Why are data centres moving into SPP's territory instead of ERCOT?
Operators are routing builds into SPP's Kansas and Oklahoma wind corridor partly to avoid ERCOT's 438 GW Texas interconnection queue, drawn by lower-carbon, competitively priced power in SPP's footprint.Source: Lowdown
Source Material

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.