PJM faces Monday FERC tariff deadline

4 min read
10:42UTC

PJM Interconnection must file its revised co-located load tariff with FERC on Monday 18 May, the regulatory precursor to RM26-4-000 and the rules that govern the Loudoun, Fairfax and Prince William corridor.

IndustryDeveloping
Key takeaway

PJM's Monday filing sets the co-located generation template for the Loudoun corridor and signals RM26-4-000's June direction.

PJM Interconnection, the regional grid operator covering thirteen states from Illinois to North Carolina, must file its revised co-located load tariff with FERC (Federal Energy Regulatory Commission) on Monday 18 May. The filing follows FERC's 16 April order, which accepted PJM's reformed interconnection pathway but rejected the operator's redefinition of co-located load and its attempt to alter behind-the-meter rules 1. The deadline is the immediate regulatory step before RM26-4-000, the main rulemaking on loads above 20 MW that FERC pledged to act on by end-June .

The specific question PJM must answer is technical but consequential: when a generator (typically a gas turbine or a battery system) sits on the same campus as the data-centre load it serves, how is that arrangement classified for tariff purposes? PJM's preferred definition would have allowed a wider category of behind-the-meter configurations; FERC ruled the definition would let load avoid contributing to grid costs in ways the commission was not prepared to accept. The new filing has to thread between the FERC objection and the operating reality of the Loudoun cluster, where co-located generation is already being designed into 2027-2028 builds.

The stakes sit directly on the Loudoun, Fairfax and Prince William corridor that PJM serves. Operators designing campuses there now face a planning environment where rezoning has narrowed (the Digital Gateway abandonment closes one path, Fairfax's new rules write a tighter one) at the same time as the federal tariff language defining their preferred behind-the-meter configurations is being rewritten. The 18 May filing is the document the colocation engineers in that corridor will read on Tuesday morning to find out which configurations remain viable. RM26-4-000 then becomes the federal template against which ERCOT, CAISO and MISO will be benchmarked over the second half of the year.

Deep Analysis

In plain English

PJM Interconnection manages the electricity grid across 13 US states, from Illinois to North Carolina, including the area around Washington DC where most of America's data centres are located. It had to file new rules with the federal electricity regulator, FERC, by Monday 18 May about how data centres can use their own on-site power generators rather than drawing from the public grid. This matters because the rules determine how much data-centre operators pay toward the costs of the public grid. If they generate their own power on-site, they might avoid contributing to those costs, which could mean other electricity customers pay more. FERC partially rejected PJM's previous attempt to define these arrangements, and the 18 May filing is the revised attempt.

Deep Analysis
Root Causes

Co-located generation inside a hyperscale fence is driven by a single structural constraint: grid interconnection timelines. A campus operator that can commission its own gas turbines or battery arrays in 18-24 months, against a grid connection timeline of 5-15 years in PJM territory, has a powerful economic motive to develop behind the meter rather than wait for grid power.

FERC's resistance to PJM's preferred definition of co-located load is a cost-allocation defence: if behind-the-meter generation does not contribute to transmission costs, the grid-connected load that does pay for the grid subsidises the behind-the-meter operator.

The Loudoun corridor context makes the cost-allocation question acute. Loudoun County hosts the world's densest data-centre cluster; the transmission infrastructure that serves it was built at ratepayer cost. A tariff that allows new campuses to co-locate generation without contributing to those sunk costs shifts the cost recovery burden further onto residential and commercial ratepayers already paying for infrastructure the industry helped necessitate.

What could happen next?
  • Consequence

    PJM's 18 May filing sets the co-located generation template for the Loudoun corridor; if FERC accepts it, data-centre operators can file campus-level generation plans with commissioning in 2027-2028 against a confirmed tariff structure.

    Short term · 0.75
  • Risk

    If FERC rejects PJM's second filing, the RM26-4-000 timeline slips into late 2026, leaving operators in PJM territory in regulatory uncertainty for campus builds already in the design phase.

    Short term · 0.65
  • Precedent

    The RM26-4-000 final rule, expected by end-June, will be the federal template against which CAISO and MISO file their own co-located load tariffs in H2 2026.

    Medium term · 0.8
First Reported In

Update #3 · OpenAI cuts $800bn; rivals double down

National Law Review· 16 May 2026
Read original
Different Perspectives
Singapore / IMDA
Singapore / IMDA
IMDA's Green Data Centre Roadmap releases 500 MW under non-negotiable PUE 1.3, liquid-cooling, and green-energy conditions set before construction, ending a seven-year freeze without triggering the consent or cost fights fragmenting three US regulatory fronts simultaneously.
US residential electricity ratepayers and community residents
US residential electricity ratepayers and community residents
Households in PJM's 13 states face grid-reinforcement costs defaulting to their bills if states miss the September deadline, while Lake Anna residents face a cooling-water permit that can clear Virginia law without any PFAS monitoring. Both costs are externalised at the regulatory stage and disputed only after the fact.
EdgeConneX in Italy (EU market)
EdgeConneX in Italy (EU market)
EdgeConneX committed €3bn to Italian data-centre capacity starting in 2026, routing capital to a jurisdiction where AI Act and NIS2 mandates create structural demand for EU-resident compute and the government actively attracts investment; Virginia's fiscal standoff and US moratoriums are redirecting pipeline offshore.
Enbridge and Baker Hughes (firmed-power and oilfield-services suppliers)
Enbridge and Baker Hughes (firmed-power and oilfield-services suppliers)
Enbridge committed $1.2bn to Wyoming solar-plus-storage for Meta and Baker Hughes redirected oilfield drilling capacity into enhanced geothermal in New Mexico; both companies are routing capital away from fossil infrastructure into data-centre power procurement at precisely the moment BTM gas became a federal curtailment target.
US federal regulators (DOE and FERC)
US federal regulators (DOE and FERC)
DOE reached for Section 202(c) twice in five months naming the same BTM load class, while FERC rejected PJM's bid to redefine the 20 MW co-located load threshold in April; together they have treated private data-centre generation as a dispatchable grid resource before the permanent RM26-4-000 rule settling its legal status has been written.
European energy regulators and climate advocates
European energy regulators and climate advocates
GE Vernova's 100 GW gas-turbine backlog, driven by AI data-centre demand, puts IEA net-zero pathways under pressure: 15-27 GW of onsite gas is forecast for US data centres by 2030. The Amazon Boardman $20.5m pollution settlement gives environmental litigation a financial template it previously lacked.