Skip to content
You can now search across every topic, entity and event.What's new
ERCOT
OrganisationUS

ERCOT

Texas grid operator; 438 GW data-centre connection queue as Batch Zero study process begins.

Last refreshed: 28 June 2026 · Appears in 1 active topic

Key Question

After adding 26 GW, why is ERCOT's large-load queue still growing faster than supply?

Timeline for ERCOT

#1019 Jul

Referenced RTO context (not one of the six named RTOs)

Data Centres: Boom and Backlash: Mentioned in: FERC sets a 20 July adequacy deadline
#818 Jun
#64 Jun
#528 May
#627 May
View full timeline →
Common Questions
What is Texas doing about the data centre power demand surge?
On 18 June 2026, the Texas Public Utility Commission approved ERCOT's first formal Batch Zero large-load interconnection study process. A final transmission plan is not due until autumn 2027, with Batch 1 applications opening summer 2027.Source: Texas PUC
How big is ERCOT's data centre connection queue?
ERCOT's large-load interconnection queue stood at 438 GW as of 18 June 2026, approximately 90% attributable to data centres, around five times Texas's current peak demand of 85 GW.Source: Texas PUC / ERCOT
Can ERCOT's isolated grid handle the data-centre demand surge?
ERCOT added ~26 GW since 2025, but its queued large-load demand of 233 GW still dwarfs its current peak of ~85 GW. The grid's isolation from the wider US network means excess load cannot be balanced across regions.Source: ERCOT / FERC

Background

ERCOT (Electric Reliability Council of Texas) operates the electric grid for approximately 90% of Texas, the largest US state electricity market. The organisation is the canonical example of AI-driven grid stress in the United States: its large-load interconnection queue reached 438 GW by 18 June 2026, with roughly 90% attributable to data centres, approximately 5x Texas's current peak demand of 85 GW. On the same date, the Texas Public Utility Commission approved ERCOT's first formal Batch Zero large-load interconnection study process; the final transmission plan is not due until autumn 2027, with Batch 1 applications opening summer 2027.

FERC reported in May 2026 that US summer generating capacity had increased by 75 GW since 2025, with ERCOT alone contributing approximately 26 GW of that addition, the largest single-grid contribution nationally. Despite this capacity build, PJM still triggered emergency protocols in mid-May, and the DOE issued a Section 202(c) curtailment order on 18 May 2026 granting PJM authority to switch off data centres during peak events. ERCOT's 26 GW addition demonstrably has not cleared its own large-load queue backlog; the gap between new supply and queued demand remains structural.

ERCOT is unusual in being isolated from the wider US grid, with limited interconnection capacity to neighbouring regions, which makes its demand-supply balance a localised rather than national problem. The organisation has faced criticism for under-investing in transmission capacity ahead of the AI infrastructure wave. The 2024 HB 1500 large-load notification bill introduced basic disclosure requirements; the Texas PUC's approval of ERCOT's Batch Zero study process on 18 June 2026 is the first formal step toward queue management reform, though a final transmission plan is not expected until autumn 2027.

More questions
Why does Texas have so many data centre and AI facility applications on the grid?
Texas's relatively light regulatory environment, competitive power markets, and abundant land have attracted data centres, AI facilities, and industrial loads. ERCOT's large-load interconnection queue reached 233 GW in early 2026, more than twice current peak demand.Source: ERCOT / Lowdown data-centres
Why is ERCOT isolated from the rest of the US grid?
ERCOT was designed to avoid interstate commerce regulation by the Federal Energy Regulatory Commission (FERC). Texas's grid operates largely independently, with limited interconnection to neighbouring systems. This isolation means Texas cannot easily import power during supply shortfalls.Source: ERCOT
How much new electricity capacity did ERCOT add in 2026?
FERC reported that ERCOT added approximately 26 GW of summer generating capacity since 2025, the largest single-grid contribution to the US's total 75 GW capacity addition. Despite this, ERCOT's large-load queue remained at 233 GW.Source: FERC / Lowdown data-centres update 4
Source Material