
ERCOT
Texas grid operator; 438 GW data-centre queue as Batch Zero interconnection studies get underway.
As of November 2026, ERCOT holds a 438 GW large-load queue, about 90% of it data centres, and Governor Greg Abbott froze state data-centre permits on 21 September, weeks after his audit order halted its Batch Zero sort.
Last refreshed: 26 November 2026 · Appears in 1 active topic
Batch Zero is live at 438 GW queued: is Texas managing growth or watching it?
Timeline for ERCOT
Mentioned in: Four US grids price data-centre cut-offs
Data Centres: Boom and BacklashMentioned in: Fermi signs 600 MW tenant, no lease yet
Data Centres: Boom and BacklashMentioned in: Spain's draft lets grid cut data centres
Data Centres: Boom and BacklashSent a 130-question survey to more than 400 projects
Data Centres: Boom and Backlash: Abbott halts Texas data centre permitsMentioned in: Fingrid warns 5 GW may not be built
Data Centres: Boom and BacklashBackground
ERCOT, the Electric Reliability Council of Texas, runs most of the Texas power grid. Because that grid is largely isolated from its neighbours, the operator cannot lean on imports in a squeeze, and every large new load has to be matched by Texan supply.
That makes it the frontline of America's data-centre demand. The queue handled 40 to 50 large loads at a time before 2025, when 225 new requests arrived in a single year; McKinsey was hired to redesign the process, and West Texas operators began converting 9.1 GW of crypto-mining sites to AI compute.
The state has since moved to police the queue directly. On 21 September Abbott ordered the environmental regulator to halt every data-centre permit, new and pending, until developers show they can pay for the grid and water they need. ERCOT's numbers now drive Texan energy politics as much as its engineering.
The queue doubled faster than ERCOT planned
ERCOT's queue for big new loads has grown at a pace no planner forecast. It passed 225 GW by April 2026, reached 410 GW within weeks, with 87% from data centres, and stood at 438 GW when Texas approved a formal clearing process on 18 June. The final transmission plan that follows is not due until autumn 2027.
Batch Zero, the first sort, closed to submissions on 24 July with roughly 205 GW across 326 projects, more than double the 100 GW ERCOT had expected. On 7 August, the day Abbott's audit letter arrived, the operator suspended the classification and prepared to ask regulators for more time. His permit freeze followed on 21 September.
Its new supply trails the demand
ERCOT adds generation faster than most American grids, yet the margin keeps slipping. FERC counted 75 GW of new US summer capacity since 2025 in a May report, with ERCOT responsible for 26 GW of it, about a third. Set against a queue measured in hundreds of gigawatts, that build barely dents the backlog.
FERC wants evidence before it writes rules. FERC required its six regional grid operators, ERCOT included, to file generation-adequacy reports by 20 July under docket RM26-4-000, an evidence-gathering step it chose in June instead of a binding large-load rule. Any enforceable standard is unlikely before 2027, which leaves Texas to manage its queue largely through state politics.
ERCOT faces a 438 GW queue
Has ERCOT's Batch Zero large-load process actually started?
What is Texas doing about the data centre power demand surge?
How big is ERCOT's data centre connection queue?
Why does Texas have so many data centre and AI facility applications on the grid?
Reference
Why does ERCOT come up in coverage of European gas and power markets?
Why is ERCOT isolated from the rest of the US grid?
Can ERCOT's isolated grid handle the data-centre demand surge?
How much new electricity capacity did ERCOT add in 2026?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.