Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
ERCOT
AI-generated illustration
OrganisationUS

ERCOT

Texas grid operator; 438 GW data-centre queue as Batch Zero interconnection studies get underway.

As of November 2026, ERCOT holds a 438 GW large-load queue, about 90% of it data centres, and Governor Greg Abbott froze state data-centre permits on 21 September, weeks after his audit order halted its Batch Zero sort.

Last refreshed: 26 November 2026 · Appears in 1 active topic

Key Question

Batch Zero is live at 438 GW queued: is Texas managing growth or watching it?

Timeline for ERCOT

#19 20 Nov
#19 12 Nov
#18 27 Oct
#15 21 Sept

Sent a 130-question survey to more than 400 projects

Data Centres: Boom and Backlash: Abbott halts Texas data centre permits
#14 18 Aug
View full timeline →

Background

ERCOT, the Electric Reliability Council of Texas, runs most of the Texas power grid. Because that grid is largely isolated from its neighbours, the operator cannot lean on imports in a squeeze, and every large new load has to be matched by Texan supply.

That makes it the frontline of America's data-centre demand. The queue handled 40 to 50 large loads at a time before 2025, when 225 new requests arrived in a single year; McKinsey was hired to redesign the process, and West Texas operators began converting 9.1 GW of crypto-mining sites to AI compute.

The state has since moved to police the queue directly. On 21 September Abbott ordered the environmental regulator to halt every data-centre permit, new and pending, until developers show they can pay for the grid and water they need. ERCOT's numbers now drive Texan energy politics as much as its engineering.

Key Issues
Large-load queue

The queue doubled faster than ERCOT planned

ERCOT's queue for big new loads has grown at a pace no planner forecast. It passed 225 GW by April 2026, reached 410 GW within weeks, with 87% from data centres, and stood at 438 GW when Texas approved a formal clearing process on 18 June. The final transmission plan that follows is not due until autumn 2027.

Batch Zero, the first sort, closed to submissions on 24 July with roughly 205 GW across 326 projects, more than double the 100 GW ERCOT had expected. On 7 August, the day Abbott's audit letter arrived, the operator suspended the classification and prepared to ask regulators for more time. His permit freeze followed on 21 September.

Federal oversight

Its new supply trails the demand

ERCOT adds generation faster than most American grids, yet the margin keeps slipping. FERC counted 75 GW of new US summer capacity since 2025 in a May report, with ERCOT responsible for 26 GW of it, about a third. Set against a queue measured in hundreds of gigawatts, that build barely dents the backlog.

FERC wants evidence before it writes rules. FERC required its six regional grid operators, ERCOT included, to file generation-adequacy reports by 20 July under docket RM26-4-000, an evidence-gathering step it chose in June instead of a binding large-load rule. Any enforceable standard is unlikely before 2027, which leaves Texas to manage its queue largely through state politics.

Common Questions

ERCOT faces a 438 GW queue

Has ERCOT's Batch Zero large-load process actually started?
Yes. Batch Zero, approved by the Texas Public Utility Commission on 18 June 2026, took effect on 11 July. Interconnecting large-load entities had to file forms with their transmission provider by 10 July, and providers must submit Batch Zero Load Information Forms to ERCOT by 24 July. A final transmission plan is not due until autumn 2027.Source: ERCOT / Texas PUC
What is Texas doing about the data centre power demand surge?
On 18 June 2026, the Texas Public Utility Commission approved ERCOT's first formal Batch Zero large-load interconnection study process. A final transmission plan is not due until autumn 2027, with Batch 1 applications opening summer 2027.Source: Texas PUC
How big is ERCOT's data centre connection queue?
ERCOT's large-load interconnection queue stood at 438 GW as of 18 June 2026, approximately 90% attributable to data centres, around five times Texas's current peak demand of 85 GW.Source: Texas PUC / ERCOT
Why does Texas have so many data centre and AI facility applications on the grid?
Texas's relatively light regulatory environment, competitive power markets, and abundant land have attracted data centres, AI facilities, and industrial loads. ERCOT's large-load interconnection queue reached 233 GW in early 2026, more than twice current peak demand.Source: ERCOT / Lowdown data-centres

Reference

Why does ERCOT come up in coverage of European gas and power markets?
ERCOT is not a European grid; it operates only within Texas. Analysts occasionally cite it as a comparative case study for how generation switches in and out of merit on the fuel-versus-power price spread, most notably during the February 2021 Winter Storm Uri crisis, when a fuel and equipment shortage rather than a lack of generation capacity drove the blackout.Source: Lowdown analysis
Why is ERCOT isolated from the rest of the US grid?
ERCOT was designed to avoid interstate commerce regulation by the Federal Energy Regulatory Commission (FERC). Texas's grid operates largely independently, with limited interconnection to neighbouring systems. This isolation means Texas cannot easily import power during supply shortfalls.Source: ERCOT
Can ERCOT's isolated grid handle the data-centre demand surge?
ERCOT added ~26 GW since 2025, but its queued large-load demand of 233 GW still dwarfs its current peak of ~85 GW. The grid's isolation from the wider US network means excess load cannot be balanced across regions.Source: ERCOT / FERC
How much new electricity capacity did ERCOT add in 2026?
FERC reported that ERCOT added approximately 26 GW of summer generating capacity since 2025, the largest single-grid contribution to the US's total 75 GW capacity addition. Despite this, ERCOT's large-load queue remained at 233 GW.Source: FERC / Lowdown data-centres update 4
Source Material

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.