Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
26APR

GE Vernova gas backlog hits 80 GW into 2029

3 min read
09:44UTC

GE Vernova's gas-turbine backlog reached 80 GW in December 2025, with deliveries booked into 2029 and reservations on track to sell out through 2030 by year-end.

IndustryDeveloping
Key takeaway

An 80 GW gas-turbine backlog locks hyperscaler power decisions into the 2050s, well past every published net-zero milestone.

GE Vernova's gas-turbine backlog reached 80 GW in December 2025, with deliveries booked into 2029 and reservations on track to sell out through 2030 by year-end. 1 The IEA projects that 15 to 27 GW of onsite natural gas will power US data centres by 2030, principally because grid interconnection cannot absorb load on operators' required timescales. 2

GE Vernova is the power-generation business spun out of General Electric in April 2024, the largest Western manufacturer of utility-scale gas turbines and a primary supplier to the US, European and Gulf gas-fleet build-outs. An 80 GW backlog is roughly equivalent to the entire installed gas-fired capacity of Spain plus Italy combined. The order book is dominated by aero-derivative and heavy-duty F-class machines in the 50-450 MW range, the formats hyperscalers buy for behind-the-meter campuses.

The 2029 delivery date is the operative figure. A turbine ordered today will not produce its first megawatt until late this decade, and once commissioned will run on a depreciation schedule into the 2050s. Hyperscalers signing those contracts now are committing to fossil generation that lasts well past every published net-zero milestone. The 15-27 GW IEA range is the agency's own central scenario for US data centre on-site gas in 2030, conditional on the grid bottleneck persisting at roughly its current severity.

GE Vernova can scale a turbine production line in eighteen months. A 765 kV transmission upgrade in PJM or ERCOT runs five to ten years from preliminary application to energisation, longer in the Northeast. The mismatch is what generates the BTM gas pipeline; turbine factories are answering hyperscaler demand at the speed of capital while public transmission planning runs at the speed of permitting. GE Vernova's 80 GW number is the cleanest single metric for that asymmetry on public record.

Deep Analysis

In plain English

GE Vernova is one of the world's main manufacturers of natural gas power generation equipment, the turbines that turn gas into electricity. By December 2025, it had orders and reservations for 80 GW of turbines, equivalent to about twice the UK's total electricity generating capacity. All its delivery slots are full into 2029. This matters because data centre operators who cannot get a grid connection are trying to build their own gas power stations instead, and now they cannot easily get the turbines either. The IEA expects 15 to 27 GW of this onsite gas to be powering US data centres by 2030. That is roughly the same as adding all of Australia's electricity generation, fuelled entirely by natural gas, to serve one sector.

Deep Analysis
Root Causes

Large-frame gas turbine manufacturing requires specialised castings, high-temperature alloys, and precision rotating components that take 18-24 months to produce per unit. GE, Siemens, Mitsubishi, and their peers cannot rapidly expand production; new manufacturing lines require five to seven years and multi-billion dollar capital commitments that no single manufacturer can justify on the basis of a demand spike they expect to moderate.

The demand spike itself is driven by the combination of BTM data centre orders and legitimate grid-decarbonisation gas peaker replacements, two entirely different demand pools competing for the same factory output. Transmission grid operators in the US and Europe are simultaneously ordering peakers and fast-response units for grid balancing, compressing turbine availability further.

What could happen next?
  • Consequence

    Operators who did not reserve GE Vernova turbines before the backlog closed in late 2025 face a choice between multi-year waits, spot-price premiums of 15-25%, or switching to alternative manufacturers with different performance profiles.

  • Opportunity

    Siemens Energy and Mitsubishi Power, with smaller installed base relationships with data centre operators, stand to capture disproportionate order share in 2026-2027 as GE Vernova delivery slots close.

First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

International Energy Agency· 26 Apr 2026
Read original
Causes and effects
This Event
GE Vernova gas backlog hits 80 GW into 2029
Equipment manufacturers are moving faster than transmission planners; the IEA expects 15-27 GW of US data centre load on private gas by 2030.
Different Perspectives
Johor state authority and Malaysian community
Johor state authority and Malaysian community
Johor halted Tier 1 and Tier 2 approvals after Malaysia's first water-rights protest; applicants face a mid-2027 floor on connections. The Diplomat's framing under UN Guiding Principles on Business and Human Rights imports a disclosure regime that ASEAN regulators had not previously applied to data-centre water consumption.
G42 and UAE sovereign programme
G42 and UAE sovereign programme
G42 confirmed all long-lead equipment procured for the 200 MW Stargate UAE first phase targeting Q3 2026; sovereign demand pull from the UAE government as anchor tenant provides cost patience commercial capital cannot replicate despite year-round mechanical cooling raising PUE to 1.35-1.50.
OpenAI and UK government
OpenAI and UK government
OpenAI cited UK industrial electricity at 'more than four times' US and Nordic rates as a co-equal Cobalt Park barrier alongside NESO's 50 GW grid queue. The named multiplier drops the UK off the global top-10 for new greenfield builds independent of any queue reform NESO can deliver in the near term.
Ecologistas en Acción and community challengers
Ecologistas en Acción and community challengers
Ecologistas en Acción's TSJ Aragón challenge to Amazon's 30-building expansion produced no ruling in the window, leaving Aragón's third-place global ranking under judicial cloud. The Virginia Court of Appeals precedent on inadequate public notice gives European community groups a template to apply to Spanish regional planning law.
FERC and US state regulators (NESO, EirGrid)
FERC and US state regulators (NESO, EirGrid)
FERC pledged on 16 April to act by end of June on RM26-4-000, the first federal rulebook for loads above 20 MW. Ireland's CRU on-site-generation rule, now templated by Pure DC's 110 MW Dublin microgrid, shows that a freeze paired with a defined compliance route can reopen a closed market.
Hyperscaler operators (Microsoft, Alphabet, Amazon, Meta)
Hyperscaler operators (Microsoft, Alphabet, Amazon, Meta)
All four reported Q1 2026 earnings with no downward revision to combined 2026 capex of $725 billion, treating the moratorium wave as a routing problem rather than a demand signal. Microsoft's $37 billion AI annual run rate confirms that capital allocation runs on quarterly board cycles that five-to-eight-year consent timelines cannot disrupt.