Skip to content
You can now search across every topic, entity and event.What's new
GE Vernova
OrganisationUS

GE Vernova

GE's energy spin-off with an 80 GW gas turbine backlog; its BTM gas is now a DOE curtailment target.

Last refreshed: 28 June 2026 · Appears in 1 active topic

Key Question

Will the DOE curtailment order slow demand for GE Vernova's behind-the-meter gas turbines?

Timeline for GE Vernova

#822 Jun

Supplied large gas turbines drawn from backlog already booked into 2029

Data Centres: Boom and Backlash: Chevron builds Microsoft a gas plant
#420 May
#418 May

DOE lets PJM switch off data centres

Data Centres: Boom and Backlash
#418 May
#811 May

Transformer waits stretch to four years

Data Centres: Boom and Backlash
View full timeline →
Common Questions
How long is the wait for a GE Vernova gas turbine?
As of December 2025, GE Vernova's gas turbine backlog stood at 80 GW with deliveries booked into 2029. New orders placed in early 2026 could face waits of three years or more.Source: Lowdown data-centres briefing
Why are gas turbine orders surging in 2025 and 2026?
Data centres and AI facilities are ordering gas turbines to power behind-the-meter generation, bypassing grid-connection queues. xAI's 41-turbine order for Colossus is the most prominent example; GE Vernova says hyperscalers are its fastest-growing customer segment.Source: Lowdown data-centres briefing
What did GE Vernova spin off from?
GE Vernova was spun off from General Electric in April 2024 as an independent energy technology company focused on gas turbines, wind turbines, and grid equipment.Source: GE Vernova

Background

GE Vernova was spun off from General Electric in April 2024 as an independent energy technology company. Its gas turbine division is now the clearest single indicator of AI infrastructure demand's physical scale: the backlog reached 80 GW in December 2025, with deliveries booked into 2029 and beyond. By Q1 2026 its total backlog had grown to $163 billion, up $13 billion in a single quarter, driven by power-generation and grid equipment orders. At that backlog level, a new order placed in early 2026 would wait three or more years for hardware delivery.

The driver is explicit: data centres and AI facilities requiring behind-the-meter generation are the fastest-growing customer segment. xAI's 41-turbine, 1.2 GW Colossus order is the most prominent individual example. However, the DOE Section 202(c) emergency curtailment order of 18 May 2026, which granted PJM authority to shut down data centres running on BTM backup generation during a heat event, directly recontextualises GE Vernova's BTM gas pipeline. Facilities powered by GE Vernova turbines inside PJM's footprint are now curtailment targets in emergencies, adding regulatory risk to a segment that had previously been presented as a near-unlimited growth market.

On 22 June 2026, Chevron's Energy Forge One signed a 20-year Power Purchase Agreement with Microsoft to build a 2.67 GW co-located gas plant in West Texas, branded Project Kilby, using GE Vernova turbines from the same backlog already booked into 2029 at approximately $7bn capex, with first power delivery expected in 2028. At 2.67 GW it is the largest dedicated-generation deal struck for a data centre in 2026. Project Kilby is sited in ERCOT territory, outside FERC curtailment authority, signalling that operators are increasingly routing BTM gas builds to jurisdictions beyond the federal reach that twice curtailed PJM-territory data centres in 2026. GE Vernova's turbine portfolio spans heavy-duty and aeroderivative gas turbines; the company also manufactures wind turbines and grid equipment, though current order flow is dominated by gas.

More questions
Why is GE Vernova's gas turbine backlog growing so fast?
Data centres and AI facilities needing behind-the-meter generation are the fastest-growing customer segment. xAI ordered 41 turbines (1.2 GW) for its Colossus complex, and hyperscalers are booking hardware years ahead of construction in some cases.Source: GE Vernova / Lowdown data-centres
How large is GE Vernova's gas turbine backlog in 2026?
GE Vernova's gas turbine backlog reached 80 GW in December 2025, with deliveries booked into 2029 and beyond. Its total backlog across all divisions reached $163 billion at the end of Q1 2026.Source: GE Vernova
Does the DOE curtailment order affect GE Vernova gas turbines?
Yes, indirectly. The DOE's 18 May 2026 Section 202(c) order grants PJM authority to curtail data centres with behind-the-meter backup generation during emergencies. GE Vernova supplies that category of gas turbines, making the BTM segment a regulatory risk as well as a demand opportunity.Source: DOE / Lowdown data-centres update 4
What is Project Kilby and who is building it?
Project Kilby is a 2.67 GW co-located gas plant in West Texas being built by Chevron's Energy Forge One under a 20-year Power Purchase Agreement with Microsoft, using GE Vernova turbines. At approximately $7bn capex, it is the largest dedicated data-centre generation deal of 2026, with first power delivery expected in 2028.Source: Chevron / GE Vernova
Source Material