
FERC Docket RM26-4-000
FERC rulemaking to standardise how new US electricity loads above 20 MW connect to the interstate transmission grid; decision due June 2026.
Last refreshed: 6 May 2026 · Appears in 1 active topic
Will the June ruling allow hyperscalers to bypass interconnection queues or impose new costs?
Timeline for FERC Docket RM26-4-000
Mentioned in: PJM cuts backstop target to 9 GW
Data Centres: Boom and Backlash75 GW added, PJM still hit an emergency
Data Centres: Boom and BacklashRemained on track for end-June action as the downstream target of the PJM filing
Data Centres: Boom and Backlash: PJM faces Monday FERC tariff deadlineserved as the pending regulatory docket governing co-located load that the emergency order pre-empted
Data Centres: Boom and Backlash: DOE lets PJM switch off data centresMentioned in: Pure DC Dublin microgrid surfaces as Irish template
Data Centres: Boom and BacklashWhat is FERC Docket RM26-4-000 and why does it matter for data centres?
When will FERC issue the large-load grid interconnection ruling?
What are the contested questions in FERC's RM26-4-000 rulemaking?
Background
FERC Docket RM26-4-000 is the proceeding in which the Federal Energy Regulatory Commission will set new rules for how electricity loads above 20 MW — the threshold at which most data centres sit — connect to the US interstate transmission grid. FERC committed on 16 April 2026 to act by end of June. The proceeding was opened under Section 403 of the DOE Organisation Act by Energy Secretary Chris Wright in October 2025, making it one of the few energy rulemakings in recent history explicitly directed by the executive branch.
The rulemaking will bind every RTO and ISO in the continental US, though not ERCOT. Per legal analysis from Mayer Brown, the three contested questions are: whether hyperscalers can bypass standard interconnection studies; how behind-the-meter generation is treated for grid-exit cost allocation; and who pays for transmission upgrades that large loads trigger. FERC sought a ruling that is "quick, efficient, and legally durable" — language acknowledging prior large-load reforms have been overturned in court.
The June order is the only federal-level mechanism capable of overriding the growing mosaic of municipal moratoriums and county-level restrictions on grid-connected data-centre capacity. Municipal utility boards can block hookups without FERC touching them; RM26-4-000 addresses the upstream layer — how loads access the interstate transmission system. A favourable ruling could accelerate large-load interconnection across all FERC-jurisdictional grids; an unfavourable or legally vulnerable ruling could impose new costs making US grid-connected data-centre projects even less competitive against ERCOT and foreign sites.