Data Centres: Boom and Backlash
17JUN

Virginia taxes power behind the meter

4 min read
10:13UTC

Virginia's two-year budget, passed 22 June, charges data centres $0.011 for every kilowatt-hour they burn, including power they generate on site. No US state had taxed power generated behind the meter until now.

IndustryDeveloping
Key takeaway

Virginia is the first US state to tax data centres on the power they make themselves.

Virginia passed a two-year budget on 22 June that charges data centres $0.011 for every kilowatt-hour (kWh) they consume, including the power they generate themselves on site 1. The Senate carried it 23 to 16 and the House 71 to 22. It is the first US levy to reach past the meter, taxing the same self-generated power the Department of Energy (DOE) ordered curtailed twice in 2026 in PJM territory .

The tax is capped at $600m a year and sunsets on 1 July 2028. To get there, lawmakers dropped the $35 to $45 per kilowatt backup-generator fee floated in mid-June and kept the sales-and-use exemption the Senate had wanted to end. Compass Datacenters, which walked away from two Virginia sites when the tax outlook was unclear , now has a number to plan around, even if it is a higher one.

Charging per kilowatt-hour consumed, rather than per kilowatt of generator nameplate, ties the levy to actual compute use, so it captures AI inference growth directly instead of capacity that may sit idle. For operators the squeeze now comes from three directions at once: the DOE can switch the on-site plant off, Virginia charges for what it produces, and the turbines that run it sit in a multi-year supply queue. The data-centre lobby says the levy will deter investment; the counter-view is that a known cost restarts projects that uncertainty had frozen.

Deep Analysis

In plain English

Virginia is home to the world's largest cluster of data centres, mostly concentrated in Loudoun County in Northern Virginia. Until now, data centres in Virginia paid very little state tax because the state wanted to attract the investment. But that created a growing problem: data centres use so much electricity that they put pressure on the power grid, yet they paid almost nothing toward grid upgrades. On 22 June, Virginia's legislature passed a new state budget that includes a small tax on every unit of electricity that data centres consume: $0.011 for each kilowatt-hour (kWh), whether that electricity comes from the public grid or from a private generator the data centre owns. The tax is capped at $600m per year and expires in July 2028, giving the state two years of revenue while the longer-term framework is debated. Compass Datacenters, which had cancelled two planned Virginia sites because of tax uncertainty {{EVREF:/t/data-centres/4/tax-fight-kills-virginia-projects-early/}}, now has a number it can include in its financial projections.

Deep Analysis
Root Causes

Virginia's budget standoff produced a consumption tax rather than the capacity-based generator fee the Senate originally proposed for two structural reasons.

First, a per-kWh consumption tax is legally defensible as a general excise levy on electricity use; a per-kW fee on installed backup-generator capacity would have been challenged as a targeted levy on specific equipment, which courts in other states have found unconstitutional when applied only to one industrial category.

Second, the legislature needed the tax to reach behind-the-meter generation because FERC's jurisdiction does not; state consumption taxes apply to power drawn for any purpose on state territory, regardless of whether it crosses the interstate transmission system. The $0.011/kWh levy on self-generated power is thus the only instrument available to a state government that wants to capture fiscal value from the BTM generation trend that federal regulators cannot reach.

What could happen next?
  • Precedent

    Virginia's two-year sunset and annual cap is the first US state tax to reach past the electricity meter to BTM generation, creating a template other high-density data-centre states (Texas, Georgia, Ohio) will study before their own fiscal reviews.

  • Risk

    The two-year sunset means Virginia's fiscal framework is unresolved from July 2028; operators signing 10-20 year leases now carry future-levy uncertainty into their site economics.

First Reported In

Update #8 · Data centres build their own power plants

Cardinal News· 28 Jun 2026
Read original
Different Perspectives
Government of Odisha
Government of Odisha
Odisha signed a $1.5bn agreement with HCLTech and Sarvam AI on 24 July for a sovereign AI data centre in Bhubaneswar, targeting 2028 operations. While regulators elsewhere price developers out of the queue, Odisha is bidding state financial assistance to bring capacity in, betting the AI infrastructure boom is worth courting rather than rationing.
Switch Datacenters and Uithoorn
Switch Datacenters and Uithoorn
The developer, the municipality, Liander and dozens of greenhouse growers signed a waste-heat agreement letting a 60 MVA facility proceed under a provincial rule that bans sites above 5 MVA. The public-interest exception argues the site relieves rather than adds to grid congestion, working around a standing ban from inside rather than waiting for it to change.
Iskandar Puteri residents
Iskandar Puteri residents
Residents protested in February over falling water pressure they attribute to ZDATA's 300 MW construction; ZDATA disputes causation and has not yet resolved the dispute with its wastewater-only pivot. The complaint sits unadjudicated while the operator advertises compliance to state authorities the residents cannot address directly.
Microsoft
Microsoft
DC Byte reports Microsoft looking to the Nordics for new capacity while Dublin's regional share falls to 15 per cent, though this is a market-intelligence inference rather than a company statement. Microsoft keeps its existing Dublin cloud region, which is costly to relocate, while directing new investment where power is cheaper and the queue is shorter.
ISO New England
ISO New England
ISO-NE proposed excluding new large loads from its Installed Capacity Requirement entirely, forcing data centres to bring their own generation or accept curtailment, even though New England's demand has been flat or falling for a decade. The reform is pre-emptive, written before the region has felt the strain PJM and MISO already report.
Ofgem
Ofgem
Ofgem opened its Data Centre Commitment Fee consultation on 29 July, arguing that free options on grid capacity let developers bank places on ten sites and abandon nine, crowding out projects that would build. It expects the deposit to filter the queue before the rule even takes final form.