Jemena, the electricity distributor for western Melbourne, has halted work on the power line to NEXTDC's M3 data centre at West Footscray. NEXTDC told the ASX on 21 October that Jemena cited "safety concerns and lack of access to work sites arising from community and stakeholder opposition to the works"1. Jemena does not expect to restart before February 2027, and the council, as road authority, has not given consent while further consultation takes place.
NEXTDC, one of Australia's largest data-centre operators, now expects the first increase in grid supply to M3 in its 2028 financial year. Later increases depend on transformer projects at the Brooklyn Terminal Station, which are also delayed.
The company cut underlying EBITDA (earnings before interest, tax, depreciation and amortisation) guidance for its 2027 financial year to A$245m-A$265m from A$385m-A$410m, and net revenue to A$475m-A$500m from A$615m-A$640m. The new guidance excludes about A$140m each of revenue and EBITDA from the affected M3 contracts. Capital spending guidance drops to A$4.5bn-A$5.0bn from A$5.25bn-A$5.75bn, and every new development and land purchase is on hold "for the foreseeable future". The shares fell about 40% when trading resumed, ABC reported, after a halt NEXTDC requested on 19 October2.
The M3 contracts carry service-level credits, refunds owed to customers for late or unpowered capacity, and may give customers the right to terminate. NEXTDC is assessing whether force majeure, a clause excusing delays outside its control, applies3. In August the company presented a 565.1 megawatt (MW) binding order book, of which 197 MW was due to start billing in the year to June 2027; some contracts inside that figure may now carry termination rights. The board will report on capital spending and a possible sale of development sites by its annual meeting on 20 November.
Victoria's planning decision on M3 stages 6 and 7 is not now expected until 2027, because caretaker conventions, which bar major decisions in the run-up to a vote, apply before the 28 November state election. The state already requires new data centres to bring their own renewable power.