Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
10JUN

GE Vernova gas backlog hits 80 GW into 2029

3 min read
10:06UTC

GE Vernova's gas-turbine backlog reached 80 GW in December 2025, with deliveries booked into 2029 and reservations on track to sell out through 2030 by year-end.

IndustryDeveloping
Key takeaway

An 80 GW gas-turbine backlog locks hyperscaler power decisions into the 2050s, well past every published net-zero milestone.

GE Vernova's gas-turbine backlog reached 80 GW in December 2025, with deliveries booked into 2029 and reservations on track to sell out through 2030 by year-end. 1 The IEA projects that 15 to 27 GW of onsite natural gas will power US data centres by 2030, principally because grid interconnection cannot absorb load on operators' required timescales. 2

GE Vernova is the power-generation business spun out of General Electric in April 2024, the largest Western manufacturer of utility-scale gas turbines and a primary supplier to the US, European and Gulf gas-fleet build-outs. An 80 GW backlog is roughly equivalent to the entire installed gas-fired capacity of Spain plus Italy combined. The order book is dominated by aero-derivative and heavy-duty F-class machines in the 50-450 MW range, the formats hyperscalers buy for behind-the-meter campuses.

The 2029 delivery date is the operative figure. A turbine ordered today will not produce its first megawatt until late this decade, and once commissioned will run on a depreciation schedule into the 2050s. Hyperscalers signing those contracts now are committing to fossil generation that lasts well past every published net-zero milestone. The 15-27 GW IEA range is the agency's own central scenario for US data centre on-site gas in 2030, conditional on the grid bottleneck persisting at roughly its current severity.

GE Vernova can scale a turbine production line in eighteen months. A 765 kV transmission upgrade in PJM or ERCOT runs five to ten years from preliminary application to energisation, longer in the Northeast. The mismatch is what generates the BTM gas pipeline; turbine factories are answering hyperscaler demand at the speed of capital while public transmission planning runs at the speed of permitting. GE Vernova's 80 GW number is the cleanest single metric for that asymmetry on public record.

Deep Analysis

In plain English

GE Vernova is one of the world's main manufacturers of natural gas power generation equipment, the turbines that turn gas into electricity. By December 2025, it had orders and reservations for 80 GW of turbines, equivalent to about twice the UK's total electricity generating capacity. All its delivery slots are full into 2029. This matters because data centre operators who cannot get a grid connection are trying to build their own gas power stations instead, and now they cannot easily get the turbines either. The IEA expects 15 to 27 GW of this onsite gas to be powering US data centres by 2030. That is roughly the same as adding all of Australia's electricity generation, fuelled entirely by natural gas, to serve one sector.

Deep Analysis
Root Causes

Large-frame gas turbine manufacturing requires specialised castings, high-temperature alloys, and precision rotating components that take 18-24 months to produce per unit. GE, Siemens, Mitsubishi, and their peers cannot rapidly expand production; new manufacturing lines require five to seven years and multi-billion dollar capital commitments that no single manufacturer can justify on the basis of a demand spike they expect to moderate.

The demand spike itself is driven by the combination of BTM data centre orders and legitimate grid-decarbonisation gas peaker replacements, two entirely different demand pools competing for the same factory output. Transmission grid operators in the US and Europe are simultaneously ordering peakers and fast-response units for grid balancing, compressing turbine availability further.

What could happen next?
  • Consequence

    Operators who did not reserve GE Vernova turbines before the backlog closed in late 2025 face a choice between multi-year waits, spot-price premiums of 15-25%, or switching to alternative manufacturers with different performance profiles.

  • Opportunity

    Siemens Energy and Mitsubishi Power, with smaller installed base relationships with data centre operators, stand to capture disproportionate order share in 2026-2027 as GE Vernova delivery slots close.

First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

International Energy Agency· 26 Apr 2026
Read original
Different Perspectives
Data-centre developers and hyperscale operators
Data-centre developers and hyperscale operators
Hill County's rescission on 4 June, seven days after RCM Hill filed a $100 million taking suit, shows the Fifth Amendment threat is faster than any appellate route: the damages clock runs from the day the moratorium passed. Rural counties with no large-load permitting framework face a litigation bill that can exceed their entire annual budget.
Kenya and President Ruto
Kenya and President Ruto
Kenya's suspension of the $1 billion Microsoft-G42 Olkaria project in early May applies raw-capacity logic at national scale: President Ruto stated the full 1 GW build would mean switching off half the country against a 3 GW installed base. A single hyperscale campus can consume a third of a Sub-Saharan grid with no equivalent constraint in Europe.
Denmark and Energinet
Denmark and Energinet
Energinet's 27 May extension of its large-load connection pause, with a 60 GW queue against 7 GW peak demand, demolishes the assumption that surplus renewable generation is a relief valve for compute demand. Denmark has more wind than it can use and still cannot connect data centres, because transmission pace is the binding constraint.
France and EDF
France and EDF
EDF's repurposing of the Bouchain former power-station site for SoftBank's Phase 1 campus gives France a replicable siting instrument, a brownfield nuclear connection bypass, that no other G7 grid operator can match. France's Choose France summit on 30 May secured the boom's largest European bet without a connection-queue fight or community moratorium.
SoftBank Group
SoftBank Group
SoftBank's EUR 75 billion France commitment on 30 May anchors at EDF's Bouchain nuclear baseload, bypassing the UK's four-times-US electricity cost premium (cited by OpenAI as reason to pause Cobalt Park) and Germany's grid-queue delays. EDF's supply relationship is bilateral; SoftBank never enters the French connection queue.
US residential ratepayers and state regulators
US residential ratepayers and state regulators
Portland General Electric's 4 June tariff is the first evidence that PJM's cost-transfer warning to governors on 19 May can run in reverse: Oregon households get a 1.3% bill reduction as data centres absorb their grid costs. The 12 other states carrying active cost-attribution bills now have a filed tariff with actual numbers to cite.