Maryland county caps campuses at 25 MW

1 min read
11:23UTC

Montgomery County council committees advanced an 18-month freeze and a 25 MW zoning cap on 22 July, the first Maryland jurisdiction to move, with a full council vote on 28 July.

IndustryDeveloping
Key takeaway

Montgomery County is the first Maryland jurisdiction to move, pairing an 18-month pause with a 25 MW cap.

Two council committees in Montgomery County, Maryland voted on 22 July to advance an 18-month freeze on new data centres and a 25 MW zoning cap, a limit barring any single campus from drawing more than 25 megawatts under local land-use rules. It is the first Maryland jurisdiction to act on the beat, and the full council votes on 28 July. 1

The 25 MW threshold outlasts the freeze beside it. A moratorium expires on its own clock; a cap written into the county code stays until it is repealed, and it does not ban campuses outright so much as size them below hyperscale. Montgomery sits in the Washington exurbs, close enough to the Northern Virginia cluster where Prince William supervisors denied the Dulles South campus this month , that its cap sets a marker for neighbouring counties weighing the same load.

Deep Analysis

In plain English

Montgomery County, Maryland, is a large county next to Washington DC. On 22 July, two county council committees voted to advance an 18-month pause on new data centres and a permanent rule capping new ones at 25 megawatts, a measure of power use roughly equivalent to a large factory. The full council votes on 28 July. It builds on a shorter, six-month pause County Executive Marc Elrich had already ordered in June. If passed, Montgomery becomes the first place in Maryland to set binding local limits on data centres, rather than leaving the decision to the state.

Deep Analysis
Root Causes

Montgomery County's 25 MW zoning cap targets a specific structural threshold, the size at which a data centre's power draw begins to require dedicated substation capacity, rather than banning data centres outright; the cap lets small facilities proceed while blocking hyperscale-sized campuses.

Maryland has had no state-level data-centre siting standard, so Montgomery County's committee vote is the first time any Maryland jurisdiction has set binding local limits, a gap other Maryland counties will now have a template to fill.

What could happen next?
  • Consequence

    If the full council ratifies the moratorium on 28 July, Montgomery becomes the first Maryland jurisdiction with a binding data-centre cap, a template other Maryland counties could adopt without waiting for state legislation.

First Reported In

Update #11 · Pipeline vetoed, campus keeps building

Food & Water Watch· 25 Jul 2026
Read original
Different Perspectives
Antel, Uruguay's state telecom
Antel, Uruguay's state telecom
Antel will build a $70m AI data centre in Canelones, announced after an 11-12 August Council of Ministers meeting, with construction from Q1 2027 and roughly 250 direct jobs. Uruguay is putting a sovereign AI facility on the state balance sheet rather than courting a hyperscaler to build one.
Comtel
Comtel
Comtel is building a Figline Valdarno data centre inside the H2-Era Green Valley complex, powered by an 84 MW solar plant and selling waste heat to on-site farming. Co-location with generation and a heat offtaker is the model regulators elsewhere are now writing into connection terms rather than negotiating case by case.
Greg Abbott, Texas Governor
Greg Abbott, Texas Governor
Abbott directed PUCT and ERCOT on 3 August to audit every queued data centre's ownership, incentives and water use, saying projects that fail the state's survey should lose grid access. QTS's co-chief executives welcomed the review; Agriculture Commissioner Sid Miller called it too vague and wants a special legislative session instead.
Government of Gujarat
Government of Gujarat
Gujarat notified a Data Centre Policy on 7 August offering capital, interest, tax and duty subsidies for projects sourcing at least 51% green power, targeting 7.5 GW against a 74 GW installed base. Where other jurisdictions priced or restricted grid access this month, Gujarat is paying developers to come instead.
Taiwan's Legislative Yuan Economics Committee
Taiwan's Legislative Yuan Economics Committee
The committee gave preliminary approval on 5 August to a self-generation mandate for large power users, including data centres, with fines up to NT$750,000. It agreed the obligation in principle while leaving the megawatt threshold that defines its reach to later implementing regulation.
Australian Energy Market Commission
Australian Energy Market Commission
AEMC advised ministers on 5 August that data centres should surrender renewable certificates against actual consumption, prove new demand with new firm capacity, and register as market participants. The advice would turn passive customers into obligated participants inside the market's dispatch and settlement machinery, ahead of an access-standards determination due in late October.