Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
10JUN

Meta buys Wyoming solar from Enbridge

3 min read
10:06UTC

Enbridge will invest $1.2 billion in a 365 MW solar and 200 MW battery storage project in Wyoming serving Meta, entering service by end-2027, as operators chase firmed non-gas power away from the BTM fleet now under federal curtailment scrutiny.

IndustryDeveloping
Key takeaway

Meta is replacing BTM gas exposure with long-term firmed solar-plus-storage to reduce regulatory curtailment risk.

Meta signed an agreement with Enbridge, the Canadian pipeline company, for a 365 MW solar and 200 MW battery storage project in Wyoming, with Enbridge investing $1.2 billion and the project entering service by end-2027. 1 It is Meta's largest renewable procurement to date and secures firmed power outside the behind-the-meter gas fleet.

The contract is the demand-side answer to the gas escape route's own queue. GE Vernova's turbine backlog, with deliveries stretching into 2029 , means an operator ordering BTM gas now waits years for it. With the DOE order also attaching curtailment risk to that fleet, an operator with the scale to contract at 365 MW has reason to switch generation type rather than join the turbine wait. A pipeline major taking the build is the tell: Enbridge is routing capital it would once have committed to gas infrastructure into solar-plus-storage for a single hyperscale customer.

The Wyoming deal does not run all day on its own, which is why the storage tranche matters and why Meta paired it the same fortnight with a gas-free baseload contract in New Mexico. Operators are no longer only moving where the power sits; they are changing what generates it.

Deep Analysis

In plain English

Enbridge is Canada's largest pipeline company, best known for moving crude oil and natural gas across North America. It is now building 365 megawatts of solar panels and a 200 MW battery storage system in Wyoming, enough to power roughly 150,000 homes, with Meta as the customer. Battery storage is the critical piece: solar alone only generates electricity when the sun shines. When you pair it with large batteries, you can store daytime energy and dispatch it at night, making the combination act more like a conventional power plant that runs around the clock. For Meta, this matters because its gas-powered backup generators can now be switched off by the grid in an emergency. Firmed solar-plus-storage cannot be curtailed the same way, so it reduces Meta's regulatory risk while also helping the company meet its carbon commitments.

Deep Analysis
Root Causes

Meta's procurement pivot from BTM gas to firmed renewables has two simultaneous drivers: the DOE 202(c) orders that reclassified BTM gas as interruptible grid reserve, and Meta's own 2030 net-zero commitment, which requires moving away from Scope 2 emissions from purchased electricity.

Enbridge's pivot from pipelines to renewable build reflects the structural demand signal: hyperscalers contracting 365 MW in a single deal with end-2027 delivery justify the capital allocation model of a pipeline company building renewable generation rather than simply transporting fossil fuels.

What could happen next?
  • Opportunity

    Pipeline infrastructure companies with capital allocation models suited to multi-decade energy assets gain a new revenue stream serving hyperscaler renewable procurement at scale.

  • Risk

    Solar-plus-storage reliance for 24/7 AI compute creates a winter reliability gap that may require supplemental gas or nuclear purchase during cold snaps, partially negating the regulatory risk reduction.

First Reported In

Update #4 · Grid wins power to switch off data centres

Utility Dive· 26 May 2026
Read original
Different Perspectives
Data-centre developers and hyperscale operators
Data-centre developers and hyperscale operators
Hill County's rescission on 4 June, seven days after RCM Hill filed a $100 million taking suit, shows the Fifth Amendment threat is faster than any appellate route: the damages clock runs from the day the moratorium passed. Rural counties with no large-load permitting framework face a litigation bill that can exceed their entire annual budget.
Kenya and President Ruto
Kenya and President Ruto
Kenya's suspension of the $1 billion Microsoft-G42 Olkaria project in early May applies raw-capacity logic at national scale: President Ruto stated the full 1 GW build would mean switching off half the country against a 3 GW installed base. A single hyperscale campus can consume a third of a Sub-Saharan grid with no equivalent constraint in Europe.
Denmark and Energinet
Denmark and Energinet
Energinet's 27 May extension of its large-load connection pause, with a 60 GW queue against 7 GW peak demand, demolishes the assumption that surplus renewable generation is a relief valve for compute demand. Denmark has more wind than it can use and still cannot connect data centres, because transmission pace is the binding constraint.
France and EDF
France and EDF
EDF's repurposing of the Bouchain former power-station site for SoftBank's Phase 1 campus gives France a replicable siting instrument, a brownfield nuclear connection bypass, that no other G7 grid operator can match. France's Choose France summit on 30 May secured the boom's largest European bet without a connection-queue fight or community moratorium.
SoftBank Group
SoftBank Group
SoftBank's EUR 75 billion France commitment on 30 May anchors at EDF's Bouchain nuclear baseload, bypassing the UK's four-times-US electricity cost premium (cited by OpenAI as reason to pause Cobalt Park) and Germany's grid-queue delays. EDF's supply relationship is bilateral; SoftBank never enters the French connection queue.
US residential ratepayers and state regulators
US residential ratepayers and state regulators
Portland General Electric's 4 June tariff is the first evidence that PJM's cost-transfer warning to governors on 19 May can run in reverse: Oregon households get a 1.3% bill reduction as data centres absorb their grid costs. The 12 other states carrying active cost-attribution bills now have a filed tariff with actual numbers to cite.