Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Data Centres: Boom and Backlash
15NOV

Transformer waits stretch to four years

3 min read
23:07UTC

US transformer lead times reached three to four years by May, and only about 5 GW of the 12 GW of data-centre capacity announced for 2026 is under construction. The rest is delayed or cancelled because the hardware cannot be built fast enough.

IndustryDeveloping
Key takeaway

A three-to-four-year wait for transformers has stalled about half the 2026 US data-centre pipeline.

US large-power transformer lead times reached 36 to 48 months, three to four years, as of May, PV Magazine reported, up from a 128-week wait recorded only two months earlier⁠1. Of the 12 GW of new US data-centre capacity announced for 2026, only about 5 GW is under active construction; the rest is delayed or cancelled on supply-chain grounds, not planning refusals.

Hardware no zoning vote can release has stalled roughly half the 2026 US pipeline. Large power transformers are bespoke builds, and the bottleneck sits in two inputs, grain-oriented electrical steel and high-voltage bushings, rather than in assembly capacity. That is what sets the multi-year clock, and it is why a fully consented, construction-ready site can still sit idle waiting to energise.

The binding constraint has rotated in under two years: capital in 2024, community consent in early 2026, and physical hardware now, each shift arriving faster than regulators can respond. Demand is migrating toward markets with existing transformer stock or captive generation, and a grey market in refurbished units is forming as buyers chase anything that ships sooner.

Deep Analysis

In plain English

A large power transformer is the piece of equipment that connects a new electricity user, like a data centre, to the grid. Transformers step electricity up or down to the right voltage for transmission or use. They are custom-built, and building one takes about a year to 18 months after the order is placed. Data-centre construction has accelerated so quickly in 2025-2026 that US transformer manufacturers cannot keep up. The wait time for a large transformer has grown from about two and a half years to three or four years. This means that of the 12 GW (gigawatts) of data-centre capacity that companies announced they would build in 2026, only about 5 GW is actually under construction. The other 7 GW is waiting for hardware. This is different from the planning fight that attracts public attention: it is a factory bottleneck, not a protest or a government refusal, that is slowing down roughly half the 2026 US data-centre pipeline.

Deep Analysis
Root Causes

Three structural constraints underlie the 36-48 month lead time.

First, each large-power transformer is custom-wound to match a substation's local grid voltage, impedance class, and cooling requirements; a data-centre substation transformer takes 12 to 18 months to produce after the order is placed, and manufacturers will not hold units in inventory against uncertain future demand.

Second, US domestic manufacturing capacity has not kept pace with demand growth because transformer manufacturers face the same grid-connection uncertainty as data-centre developers: a manufacturing plant built to serve a demand wave that arrives two years later than forecast carries stranded-asset risk that privately held manufacturers are unwilling to absorb unilaterally.

Third, the transformer shortage interacts with the grid-connection queue to create a lock: operators cannot get a grid connection quote without knowing transformer availability, and transformer manufacturers will not accept orders without a confirmed grid connection. Operators without a cleared site are therefore stuck in a two-sided bottleneck that neither FERC's docket RM26-4-000 nor ERCOT's Batch Zero process directly resolves.

What could happen next?
  • Consequence

    The 7 GW stall defers approximately $14bn in annual cloud revenue across US hyperscalers, creating earnings risk for the 2027-28 guidance cycles that management has not yet flagged publicly.

    Medium term · Suggested
  • Opportunity

    Domestic transformer manufacturers who can credibly commit to 18-month delivery on a 10-unit minimum order will command premium pricing; GE Vernova and ABB's US operations are positioned to capture that margin if they invest in additional winding capacity in 2026.

    Medium term · Suggested
  • Risk

    The two-sided bottleneck (no grid quote without confirmed transformer, no transformer order without grid quote) may require a federal procurement intermediary, similar to the US Strategic Transformer Reserve proposed under the 2021 Infrastructure Investment and Jobs Act, to break the deadlock.

    Medium term · Suggested
First Reported In

Update #8 · Data centres build their own power plants

PV Magazine USA· 28 Jun 2026
Read original →
Causes and effects
This Event
Transformer waits stretch to four years
A multi-year wait for the giant transformers that connect data centres has decoupled planning approval from actual construction.
Different Perspectives
Mooresville Board of Commissioners
Mooresville Board of Commissioners
The town board north of Charlotte voted unanimously on 2 November to stop taking data-centre applications for 12 months. Commissioners cited environmental and electrical impacts, joining other North Carolina towns that have paused new projects.
Naver
Naver
Naver signed a US$9bn contract under which a Brookfield vehicle owns the GPUs and buildings and sells computing to Naver Cloud. It guarantees the fees for up to eight years, which also unlocked Nvidia's US$1bn equity investment.
Saudi Aramco
Saudi Aramco
Aramco closed its purchase of 49% of HUMAIN on 1 November, paying about US$2.6bn in cash and adding its own AI, compute and digital assets. Chief executive Amin Nasser cast the deal as a gain in technology standing.
NEXTDC board
NEXTDC board
The board called the Goodman and Digital Realty stake opportunistic and said it had received no takeover proposal. It enters the 20 November meeting with a new chairman search, a 10% fee cut and a spill resolution on the agenda.
Brasscom
Brasscom
Sergio Sgobbi of Brazil's technology industry association says investors face uncertainty until the Redata rules are public. Members need rulings on gas and the CDE levy after Lula said data centres must build their own power.
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
He told the Dewan Rakyat in October that data centres pay for all the grid capacity they reserve and fund upgrades to TNB's network. Google's 4 November pledge repeats those terms as its own.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.