
Batch Zero
Texas's first cohort-based study for ERCOT's 438 GW large-load interconnection queue, approved June 2026.
Last refreshed: 28 June 2026 · Appears in 1 active topic
Can Batch Zero process Texas's 438 GW queue before the backlog outgrows its autumn 2027 transmission plan?
Timeline for Batch Zero
Texas queue swells to 438 GW
Data Centres: Boom and BacklashWhat is Batch Zero in Texas and how does it work?
When will Texas complete the Batch Zero interconnection study?
How big is the Texas ERCOT large-load queue?
Background
Texas Public Utility Commission approved ERCOT's first formal Batch Zero large-load interconnection study on 18 June 2026, with a final transmission plan not due until autumn 2027 and the next application round (Batch 1) opening in summer 2027. ERCOT's large-load queue stood at 438 GW at the time of approval, roughly five times Texas's peak electricity demand and approximately 90% data centres. Texas first tried to clear this backlog when the queue stood at 225 GW; it has nearly doubled since.
Batch Zero is a cohort-based study method: instead of processing each large-load interconnection application individually, ERCOT groups all current applicants into a single cohort and models the transmission impact of the whole batch together. This approach reduces duplicated engineering work and produces a coordinated transmission plan, but it extends the timeline for individual applicants who must wait for the cohort study to complete before their connection can proceed. The autumn 2027 plan date means most 2026 and early 2027 data-centre build programmes will be committed before any Batch Zero outcome is known. Queue intake runs at tens of gigawatts per quarter; the study process takes years; the backlog therefore grows faster than any cohort can be processed.