Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
10JUN

PJM cuts backstop target to 9 GW

3 min read
10:06UTC

PJM restructured its September reliability backstop to a bilateral-first model targeting roughly 9 GW, down from 14.9 GW, per a Jefferies estimate published around 19 May.

IndustryDeveloping
Key takeaway

PJM shrank its September backstop to 9 GW, pushing data centres to contract their own firm power.

PJM Interconnection, the largest grid operator in the United States, serving roughly 65 million people across thirteen states, revised its September Reliability Backstop Procurement to a bilateral-first structure targeting roughly 9 GW, down from a prior 14.9 GW target, according to a Jefferies estimate published on or around Tuesday 19 May. 1

The backstop is the mechanism by which PJM secures emergency capacity to keep the lights on when demand outpaces supply. A bilateral-first design pushes large loads to strike their own supply contracts before the grid steps in to procure the remainder centrally, which is how the target shrank by nearly six gigawatts. The change followed directly from the warning PJM's board sent thirteen state governors that grid-reinforcement costs would otherwise drift onto household bills .

For data-centre operators, the revision narrows the pool of capacity the grid will backstop on everyone's behalf and widens the share they must arrange themselves. It is a quieter version of the same cost-allocation fight Oregon settled by tariff: who lines up the power, and who pays when the grid has to fill the gap.

Deep Analysis

In plain English

PJM Interconnection is the company that runs the electricity grid serving 65 million people across 13 US states, from Illinois to New Jersey. Every year it buys a reserve of extra power capacity to cover emergencies, called the Reliability Backstop Procurement (a backup supply purchase). Think of it like buying extra emergency generators for the whole grid. In May 2026, PJM changed how it runs this process. Instead of a competitive auction where power suppliers bid against each other, it switched to a bilateral-first system, meaning it negotiates direct deals with individual generators rather than running an open competition. The target amount of backup power dropped from 14.9 gigawatts to around 9 gigawatts. This reduces the cost that might otherwise land on household electricity bills, but critics say it also reduces price transparency, because direct deals are private rather than openly priced.

What could happen next?
  • Consequence

    PJM's bilateral-first backstop sets a precedent that competitive capacity auctions are politically unacceptable when data-centre load is the primary driver of reliability gaps, potentially reshaping how all 13 PJM-state utilities procure backup capacity.

  • Risk

    Bilateral contracts' confidential pricing removes the cost-attribution transparency that PJM's 19 May governor warning was designed to establish, creating information asymmetry between generators and state regulators at the moment regulators most need cost data.

First Reported In

Update #6 · Oregon bills data centres, not homes

Utility Dive· 10 Jun 2026
Read original
Causes and effects
This Event
PJM cuts backstop target to 9 GW
The shrunken target shows PJM leaning on operators to contract their own firm power rather than the grid procuring it centrally, narrowing the volume households might end up paying for.
Different Perspectives
Data-centre developers and hyperscale operators
Data-centre developers and hyperscale operators
Hill County's rescission on 4 June, seven days after RCM Hill filed a $100 million taking suit, shows the Fifth Amendment threat is faster than any appellate route: the damages clock runs from the day the moratorium passed. Rural counties with no large-load permitting framework face a litigation bill that can exceed their entire annual budget.
Kenya and President Ruto
Kenya and President Ruto
Kenya's suspension of the $1 billion Microsoft-G42 Olkaria project in early May applies raw-capacity logic at national scale: President Ruto stated the full 1 GW build would mean switching off half the country against a 3 GW installed base. A single hyperscale campus can consume a third of a Sub-Saharan grid with no equivalent constraint in Europe.
Denmark and Energinet
Denmark and Energinet
Energinet's 27 May extension of its large-load connection pause, with a 60 GW queue against 7 GW peak demand, demolishes the assumption that surplus renewable generation is a relief valve for compute demand. Denmark has more wind than it can use and still cannot connect data centres, because transmission pace is the binding constraint.
France and EDF
France and EDF
EDF's repurposing of the Bouchain former power-station site for SoftBank's Phase 1 campus gives France a replicable siting instrument, a brownfield nuclear connection bypass, that no other G7 grid operator can match. France's Choose France summit on 30 May secured the boom's largest European bet without a connection-queue fight or community moratorium.
SoftBank Group
SoftBank Group
SoftBank's EUR 75 billion France commitment on 30 May anchors at EDF's Bouchain nuclear baseload, bypassing the UK's four-times-US electricity cost premium (cited by OpenAI as reason to pause Cobalt Park) and Germany's grid-queue delays. EDF's supply relationship is bilateral; SoftBank never enters the French connection queue.
US residential ratepayers and state regulators
US residential ratepayers and state regulators
Portland General Electric's 4 June tariff is the first evidence that PJM's cost-transfer warning to governors on 19 May can run in reverse: Oregon households get a 1.3% bill reduction as data centres absorb their grid costs. The 12 other states carrying active cost-attribution bills now have a filed tariff with actual numbers to cite.