Skip to content
You can now search across every topic, entity and event.What's new
Data Centres: Boom and Backlash
6MAY

Texas queue swells to 438 GW

3 min read
13:52UTC

Texas approved its first formal large-load study process on 18 June, even as ERCOT's connection queue climbed to 438 GW, about 90% of it data centres. The plan to clear it is not due until autumn 2027.

IndustryDeveloping
Key takeaway

ERCOT's queue has nearly doubled to 438 GW while the plan to clear it runs to autumn 2027.

The Public Utility Commission of Texas approved the state's first formal Batch Zero large-load study process on 18 June, the cohort method ERCOT will use to work through its connection requests 1. ERCOT, the Electric Reliability Council of Texas, which runs about 90% of the state grid, reported its large-load queue at 438 GW (gigawatts), roughly 90% of it data centres.

The queue climbed from 410 GW in April in about six weeks, and Texas first tried to clear it when it stood at 225 GW . It has nearly doubled since. ERCOT's final transmission plan is not due until autumn 2027, with the next application round, Batch 1, opening in summer 2027.

Intake runs at tens of gigawatts a quarter while the study meant to clear it takes years, so the backlog grows faster than any single cohort can be processed. A connection cleared through Batch Zero still cannot switch on without the transformers to serve it, and those are running years behind for new grid links. A transformer ordered today arrives after both the FERC show-cause responses and the Batch Zero plan are already on the table.

Deep Analysis

In plain English

ERCOT (Electric Reliability Council of Texas) is the company that operates the electricity grid for about 90% of Texas. When a company wants to connect a new power user, like a data centre, to the Texas grid, it has to apply for a connection and join a queue. ERCOT then studies whether the local grid can handle the extra load without causing problems for existing customers. That queue has now reached 438 GW, meaning companies have applied to connect 438 GW of new electricity demand, roughly five times Texas's actual peak electricity use of about 85 GW. About 90% of those applications are from data centres. On 18 June, Texas approved the first formal batch process to work through the queue, called Batch Zero. But the final plan is not due until autumn 2027, and the next round of applications does not open until summer 2027, meaning new data centres approved through this process will not have confirmed grid connections for at least two more years.

What could happen next?
  • Consequence

    ERCOT's Batch Zero timeline locks the Texas data-centre grid-connection question to 2027-28, a 12-18 month gap that will be filled by BTM generation deals like Project Kilby rather than utility connections.

  • Risk

    If queue growth continues at the 28 GW per two-month pace observed between April and June 2026, the queue will exceed 600 GW before Batch Zero's autumn 2027 plan is delivered, making any single batch process insufficient.

First Reported In

Update #8 · Data centres build their own power plants

Utility Dive· 28 Jun 2026
Read original
Causes and effects
Different Perspectives
Global hyperscale operators
Global hyperscale operators
Operators are still filing gigawatt-scale campuses and Meta is proceeding with its $10bn Lebanon, Indiana site despite the county-level bans nearby, betting Q2 capex outruns the patchwork of restrictions. Industry framing casts New York's freeze, Oregon's surcharge and Indiana's bans as taxes and levies that push build-out toward faster-permitting jurisdictions such as India and the Gulf.
EirGrid
EirGrid
EirGrid set a 900 MW instantaneous demand-loss ceiling because a single voltage dip can trip many data centres onto backup power at once, risking imbalance above 1,150 MW. It wrote the limit into a standing procedure rather than waiting for an emergency to force one.
US host communities and ratepayers
US host communities and ratepayers
Prince William residents backed the 8-0 denial of Dulles South over the Occoquan watershed, drinking water for eight million people, while Oregon's approved tariff cuts residential bills 1.3% by charging large loads 29% more. Their position: consent and cost-attribution belong in law, not left to a developer's or a utility's discretion.
Hassan Allam Digital Infrastructure
Hassan Allam Digital Infrastructure
Hassan Allam Digital Infrastructure, an Egyptian conglomerate rather than a foreign hyperscaler, reportedly secured a domestic hyperscale licence with a $400m first phase, per single-source reporting still to be verified. It reads as home-grown sovereign compute ambition, building national capacity rather than importing a US or Gulf operator's campus.
Damac Digital
Damac Digital
Damac Digital keeps building toward roughly 6,000 megawatts of hyperscale capacity across 13 countries while Virginia taxes power and New York weighs a freeze. Every dollar or month of delay a US state adds is capacity a Gulf developer can site somewhere with faster permitting and no equivalent levy.
Acequia communities, Santa Fe County
Acequia communities, Santa Fe County
Santa Fe County commissioners voted unanimously on 2 July to freeze any data centre over one megawatt, citing the acequia irrigation commons that has shared scarce water since Spanish colonial rule. They expect the low threshold to draw the same Fifth Amendment challenge RCM Hill brought against Hill County, Texas.