Data Centres: Boom and Backlash
6MAY

Four US grids price data-centre cut-offs

5 min read
13:52UTC

SPP would cut a data centre's cheaper power once prices pass $25/MWh, and ISO New England at $250, in plans FERC has yet to accept.

IndustryDeveloping
Key takeaway

Four US grid operators proposed the prices at which data centres on cheaper service lose power.

SPP (Southwest Power Pool, the grid for the central Plains states) would cut a data centre's cheaper power to zero whenever the local price passes $25 per megawatt-hour (MWh)⁠1. That price is one of the answers the six grid operators regulated by FERC (the Federal Energy Regulatory Commission) filed between 13 and 20 November to its orders on large loads. Each would offer data centres a cheaper "non-firm" service that can be cut off. Four name the price at which that happens, while PJM Interconnection and CAISO (the California Independent System Operator) set no price threshold.

MISO (the Midcontinent Independent System Operator) would interrupt non-firm load when the local price passes $100/MWh. NYISO (the New York Independent System Operator) would cap non-firm bids at $200/MWh. ISO New England, the region's independent system operator, would order non-firm load to cut back at $250/MWh, a price its grid reached in about 1% of hours from 2021 to 2025. In principle, the lower the trip price, the more hours a data centre gives up, and the less the households sharing its grid pay to build for it.

Firm power costs more. MISO would charge a nonrefundable $250,000 application fee and a $100,000 study deposit, while SPP would assign any upgrade cost above a "safe harbor" of $500,000 per megawatt (MW), capped at $25m per request, to the customer for up to 40 years. NYISO's queue shows why the operators want a cheaper tier: it holds 51 large-load projects totalling about 12,670 MW, against forecasts that at most about 2,880 MW of it is built by 2040. FERC has accepted none of the six plans, and states and utilities can still contest them.

PJM, the grid that serves Northern Virginia's data-centre cluster, filed its plan on Monday 16 November and says it already serves about 10 gigawatts (GW) of large computational load. On 22 July nearly 3.9 GW of data-centre load dropped onto onsite generation in a single event, the kind of sudden swing PJM's separate ride-through filing (ER27-522-000) is written to prevent. The push for all six filings came from the Trump administration: Energy Secretary Chris Wright directed FERC on 23 October 2025, under Section 403 of the Department of Energy Organization Act, to start rulemaking on large-load connections, and FERC's "show cause" orders of 18 June followed. Britain rations grid places by sponsorship and caps instead, since ministers can now reserve capacity for sponsored projects and data-centre connections after 2030 will be capped by region.

On the reliability side, the North American Electric Reliability Corporation (NERC) asked FERC to create two new registered-entity types for data-centre owners and operators⁠2. They cover sites of 50 MW or more supplied at 100 kilovolts (kV) or above, which NERC estimates capture 68,288 MW, roughly 86% of the computational load projected by the end of 2027. Registration would make a data-centre owner answerable to NERC, where today it is only a utility's customer. The standards those owners would answer to, adopted by NERC's board in October on the threshold set at the first ballot, must reach FERC by 31 December.

Deep Analysis

In plain English

America's big regional grids are run by non-profit operators that schedule power plants and plan new lines. Six of them answer to FERC, the Federal Energy Regulatory Commission, which ordered each in June to explain how it will connect very large users such as data centres. Their answers offer a deal. A data centre can take a cheaper connection, sooner, if it agrees to be switched off when power gets scarce and expensive. Four of the six named the price that triggers the switch-off. None of the plans applies until FERC approves it. A separate body, NERC (the North American Electric Reliability Corporation), wants big data centres registered so that they must follow grid safety rules directly, as power stations do.

Deep Analysis
Root Causes

Federal law splits the job. FERC governs transmission and wholesale markets, while states and their utilities decide who connects to retail service, so the June orders could only make each operator fix its own tariff rather than impose one national rule.

Filing a request costs a developer little, but every one must be studied. A queue several times larger than any forecast build clogs the engineering work for everyone, which is why MISO's nonrefundable fee prices speculation as much as it recovers study costs.

Reliability rules lag behind the machines. On 10 July 2024 a single line fault in Northern Virginia tipped about 1,500 MW of data centres onto backup power at once, a NERC incident review found. No NERC standard yet binds the owner of that load, which is the gap the registration petition targets.

Escalation

Up, slowly. The next markers are NERC's standards filing, due at FERC by 31 December, and MISO's first large-load review deadline on 1 March 2027. SPP does not expect its price-adaptive service to start before the second quarter of 2028, so the first switch-offs under any of these tiers are more than a year away.

What could happen next?
  • Consequence

    If FERC accepts the non-firm tiers, data centres willing to be cut off could connect well ahead of rivals waiting for firm service.

    Medium term · Suggested
  • Risk

    Sites tripped off the grid would run onsite gas or diesel generators, moving the local fight from power lines to air-quality permits.

    Medium term · Assessed
  • Precedent

    NERC registration would make data-centre owners answerable for grid reliability in their own right, as generators already are.

    Long term · Reported
First Reported In

Update #19 · US grids set a price to cut off data centres

Power Magazine· 26 Nov 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.