PJM cuts backstop target to 9 GW

3 min read
13:06UTC

PJM restructured its September reliability backstop to a bilateral-first model targeting roughly 9 GW, down from 14.9 GW, per a Jefferies estimate published around 19 May.

IndustryDeveloping
Key takeaway

PJM shrank its September backstop to 9 GW, pushing data centres to contract their own firm power.

PJM Interconnection, the largest grid operator in the United States, serving roughly 65 million people across thirteen states, revised its September Reliability Backstop Procurement to a bilateral-first structure targeting roughly 9 GW, down from a prior 14.9 GW target, according to a Jefferies estimate published on or around Tuesday 19 May. 1

The backstop is the mechanism by which PJM secures emergency capacity to keep the lights on when demand outpaces supply. A bilateral-first design pushes large loads to strike their own supply contracts before the grid steps in to procure the remainder centrally, which is how the target shrank by nearly six gigawatts. The change followed directly from the warning PJM's board sent thirteen state governors that grid-reinforcement costs would otherwise drift onto household bills .

For data-centre operators, the revision narrows the pool of capacity the grid will backstop on everyone's behalf and widens the share they must arrange themselves. It is a quieter version of the same cost-allocation fight Oregon settled by tariff: who lines up the power, and who pays when the grid has to fill the gap.

Deep Analysis

In plain English

PJM Interconnection is the company that runs the electricity grid serving 65 million people across 13 US states, from Illinois to New Jersey. Every year it buys a reserve of extra power capacity to cover emergencies, called the Reliability Backstop Procurement (a backup supply purchase). Think of it like buying extra emergency generators for the whole grid. In May 2026, PJM changed how it runs this process. Instead of a competitive auction where power suppliers bid against each other, it switched to a bilateral-first system, meaning it negotiates direct deals with individual generators rather than running an open competition. The target amount of backup power dropped from 14.9 gigawatts to around 9 gigawatts. This reduces the cost that might otherwise land on household electricity bills, but critics say it also reduces price transparency, because direct deals are private rather than openly priced.

What could happen next?
  • Consequence

    PJM's bilateral-first backstop sets a precedent that competitive capacity auctions are politically unacceptable when data-centre load is the primary driver of reliability gaps, potentially reshaping how all 13 PJM-state utilities procure backup capacity.

  • Risk

    Bilateral contracts' confidential pricing removes the cost-attribution transparency that PJM's 19 May governor warning was designed to establish, creating information asymmetry between generators and state regulators at the moment regulators most need cost data.

First Reported In

Update #6 · Oregon bills data centres, not homes

Utility Dive· 10 Jun 2026
Read original
Causes and effects
This Event
PJM cuts backstop target to 9 GW
The shrunken target shows PJM leaning on operators to contract their own firm power rather than the grid procuring it centrally, narrowing the volume households might end up paying for.
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.