PJM cuts backstop target to 9 GW

3 min read
10:48UTC

PJM restructured its September reliability backstop to a bilateral-first model targeting roughly 9 GW, down from 14.9 GW, per a Jefferies estimate published around 19 May.

IndustryDeveloping
Key takeaway

PJM shrank its September backstop to 9 GW, pushing data centres to contract their own firm power.

PJM Interconnection, the largest grid operator in the United States, serving roughly 65 million people across thirteen states, revised its September Reliability Backstop Procurement to a bilateral-first structure targeting roughly 9 GW, down from a prior 14.9 GW target, according to a Jefferies estimate published on or around Tuesday 19 May. 1

The backstop is the mechanism by which PJM secures emergency capacity to keep the lights on when demand outpaces supply. A bilateral-first design pushes large loads to strike their own supply contracts before the grid steps in to procure the remainder centrally, which is how the target shrank by nearly six gigawatts. The change followed directly from the warning PJM's board sent thirteen state governors that grid-reinforcement costs would otherwise drift onto household bills .

For data-centre operators, the revision narrows the pool of capacity the grid will backstop on everyone's behalf and widens the share they must arrange themselves. It is a quieter version of the same cost-allocation fight Oregon settled by tariff: who lines up the power, and who pays when the grid has to fill the gap.

Deep Analysis

In plain English

PJM Interconnection is the company that runs the electricity grid serving 65 million people across 13 US states, from Illinois to New Jersey. Every year it buys a reserve of extra power capacity to cover emergencies, called the Reliability Backstop Procurement (a backup supply purchase). Think of it like buying extra emergency generators for the whole grid. In May 2026, PJM changed how it runs this process. Instead of a competitive auction where power suppliers bid against each other, it switched to a bilateral-first system, meaning it negotiates direct deals with individual generators rather than running an open competition. The target amount of backup power dropped from 14.9 gigawatts to around 9 gigawatts. This reduces the cost that might otherwise land on household electricity bills, but critics say it also reduces price transparency, because direct deals are private rather than openly priced.

What could happen next?
  • Consequence

    PJM's bilateral-first backstop sets a precedent that competitive capacity auctions are politically unacceptable when data-centre load is the primary driver of reliability gaps, potentially reshaping how all 13 PJM-state utilities procure backup capacity.

  • Risk

    Bilateral contracts' confidential pricing removes the cost-attribution transparency that PJM's 19 May governor warning was designed to establish, creating information asymmetry between generators and state regulators at the moment regulators most need cost data.

First Reported In

Update #6 · Oregon bills data centres, not homes

Utility Dive· 10 Jun 2026
Read original
Causes and effects
This Event
PJM cuts backstop target to 9 GW
The shrunken target shows PJM leaning on operators to contract their own firm power rather than the grid procuring it centrally, narrowing the volume households might end up paying for.
Different Perspectives
Antel, Uruguay's state telecom
Antel, Uruguay's state telecom
Antel will build a $70m AI data centre in Canelones, announced after an 11-12 August Council of Ministers meeting, with construction from Q1 2027 and roughly 250 direct jobs. Uruguay is putting a sovereign AI facility on the state balance sheet rather than courting a hyperscaler to build one.
Comtel
Comtel
Comtel is building a Figline Valdarno data centre inside the H2-Era Green Valley complex, powered by an 84 MW solar plant and selling waste heat to on-site farming. Co-location with generation and a heat offtaker is the model regulators elsewhere are now writing into connection terms rather than negotiating case by case.
Greg Abbott, Texas Governor
Greg Abbott, Texas Governor
Abbott directed PUCT and ERCOT on 3 August to audit every queued data centre's ownership, incentives and water use, saying projects that fail the state's survey should lose grid access. QTS's co-chief executives welcomed the review; Agriculture Commissioner Sid Miller called it too vague and wants a special legislative session instead.
Government of Gujarat
Government of Gujarat
Gujarat notified a Data Centre Policy on 7 August offering capital, interest, tax and duty subsidies for projects sourcing at least 51% green power, targeting 7.5 GW against a 74 GW installed base. Where other jurisdictions priced or restricted grid access this month, Gujarat is paying developers to come instead.
Taiwan's Legislative Yuan Economics Committee
Taiwan's Legislative Yuan Economics Committee
The committee gave preliminary approval on 5 August to a self-generation mandate for large power users, including data centres, with fines up to NT$750,000. It agreed the obligation in principle while leaving the megawatt threshold that defines its reach to later implementing regulation.
Australian Energy Market Commission
Australian Energy Market Commission
AEMC advised ministers on 5 August that data centres should surrender renewable certificates against actual consumption, prove new demand with new firm capacity, and register as market participants. The advice would turn passive customers into obligated participants inside the market's dispatch and settlement machinery, ahead of an access-standards determination due in late October.