Timeline

FERC

US grid regulator; ordered six RTOs to file grid-adequacy reports by 20 July 2026.

24 of 24 entries (23 events, 1 interactions)

Filters
#13 3 Aug

Opened public comment on PJM's Interim Resource Adequacy Service filing

Data Centres: Boom and Backlash: PJM wants 50 MW loads curtailable
#12 31 Jul
#13 31 Jul
filed with
Data Centres: Boom and Backlash · source event
#12 24 Jul
#12 23 Jul

Six US grid operators file, none say yes

Data Centres: Boom and Backlash
#10 19 Jul

Required six RTOs to file generation-adequacy reports by 20 July

Data Centres: Boom and Backlash: FERC sets a 20 July adequacy deadline
#11 15 Jul

Set the 20 July generation-adequacy filing deadline the emergency preceded

Data Centres: Boom and Backlash: MISO's second grid emergency in July
#8 22 Jun
#8 18 Jun

Mentioned in: Texas queue swells to 438 GW

Data Centres: Boom and Backlash
#8 18 Jun

Issued Section 206 show-cause orders to six RTOs instead of a final large-load rule

Data Centres: Boom and Backlash: FERC delays its grid rule to 2027
#7 15 Jun
#7 10 Jun
#5 28 May

Received the rehearing petition against the DOE 202(c) order

Data Centres: Boom and Backlash: DOE curtailment order faces taking claim
#5 19 May

Set the 18 May tariff-filing deadline that contextualised the PJM action

Data Centres: Boom and Backlash: PJM warns 13 governors on grid costs
#6 19 May

Mentioned in: PJM cuts backstop target to 9 GW

Data Centres: Boom and Backlash
#4 18 May

DOE lets PJM switch off data centres

Data Centres: Boom and Backlash
#4 18 May
#4 18 May

reported 75 GW of new US summer generating capacity added since 2025

Data Centres: Boom and Backlash: 75 GW added, PJM still hit an emergency
#2 6 May
#2 16 Apr

FERC commits to June 2026 grid-load order

Data Centres: Boom and Backlash
#5 9 Apr

Mentioned in: Texas grid queue hits 410 GW

Data Centres: Boom and Backlash
#2 1 Apr