Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
10JUN

FERC commits to June 2026 grid-load order

4 min read
10:06UTC

The Federal Energy Regulatory Commission pledged on 16 April to act by end of June 2026 on Docket RM26-4-000, the rulemaking that will set how electricity loads above 20 MW connect to the US interstate grid.

IndustryDeveloping
Key takeaway

FERC's June order is the only federal counter-escalation to the muni-tier consent freeze.

On 16 April 2026, the Federal Energy Regulatory Commission (FERC, the US federal electricity regulator) pledged to act by end of June 2026 on Docket RM26-4-000, the rulemaking that will standardise how new electricity loads above 20 MW connect to the US interstate transmission grid. The proceeding was opened by Energy Secretary Chris Wright under Section 403 of the DOE Organisation Act in October 2025, and on 16 April Deputy Secretary James Danly issued a statement commending the announcement. FERC said the order would be 'quick, efficient, and legally durable'.

Legal analysis from Mayer Brown identifies three contested questions in the docket: whether hyperscalers can bypass standard interconnection studies for accelerated review, how behind-the-meter solutions are treated for grid-exit cost allocation, and who pays for the upgrades large loads trigger. The behind-the-meter ruling determines whether projects copying Pure DC's Dublin microgrid template still pay their share of transmission upgrades; the cost-allocation ruling determines whether the trigger load pays alone or the wider ratepayer base picks up the bill. Mayer Brown's reading is that cost allocation drives the largest economic effect, and that whichever way the commission lands, the bypass and study-process answers tend to follow that choice.

The proceeding will bind every US RTO and ISO (Regional Transmission Organisation and Independent System Operator). It cannot reach ERCOT, the Texas grid which sits outside both the Eastern and Western Interconnection. That asymmetric reach is exactly why operators trying to escape the federal layer have begun routing capacity into West Texas already. The municipal moratoriums in Maine, Seattle, and Northern Virginia cannot rewrite federal interconnection rules; only FERC can, and the order arrives in eight weeks. For projects facing the UK's structural ceiling, where 50 GW of data-centre demand sits behind 45 GW of national peak , there is no equivalent single-actor lever; for projects in PJM, MISO, SPP, NYISO, ISO-NE, or CAISO, the next eight weeks will define the cost basis for every new application.

Deep Analysis

In plain English

FERC is the US federal agency that oversees the rules for how electricity flows across state lines and how large industrial facilities connect to the national grid. It announced it will set new rules by June 2026 for how large power users, like data centres that need more than 20 megawatts, get connected to that national grid. Before this rulemaking, each utility applied its own interconnection study process, producing timelines that ranged from 18 months (ERCOT) to seven years (PJM) for the same class of applicant. The new rules matter because they could either speed up data centre connections (if they allow shortcuts) or force data centres to pay more of the cost of grid upgrades (if they assign upgrade costs to the new load rather than existing ratepayers).

Deep Analysis
Root Causes

The US interstate transmission grid was designed in an era when large industrial loads grew incrementally (steel mills, aluminium smelters, semiconductor fabs) and were located adjacent to generation sources. Data centres have a fundamentally different location logic: they site near population centres and existing fibre density rather than near generation, which means they connect to distribution-level grid infrastructure not designed for their load profiles.

FERC's existing interconnection queue rules, codified in the pro forma Large Generator Interconnection Agreement, were written for generators connecting to the bulk power system, not for loads. The queue for loads above 20 MW has no equivalent standardised framework. RM26-4-000 is essentially writing the first national load-interconnection rulebook, which is why its three contested questions are genuinely novel and not resolvable by reference to prior FERC precedent.

What could happen next?
  • Opportunity

    A favourable RM26-4-000 outcome on bypass and cost-allocation would reduce interconnection timelines for loads above 20 MW from the current 4-7-year queue to a compressed 18-24-month process, unlocking projects currently parked in the Northern Virginia, PJM, and MISO queues.

  • Risk

    Incumbent utility litigation within 60 days of the final rule, seeking a preliminary stay, is the base-case outcome based on FERC's last three major interconnection reform orders; a successful stay would suspend the rule's effect for 2-4 years.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

FERC· 6 May 2026
Read original
Different Perspectives
Data-centre developers and hyperscale operators
Data-centre developers and hyperscale operators
Hill County's rescission on 4 June, seven days after RCM Hill filed a $100 million taking suit, shows the Fifth Amendment threat is faster than any appellate route: the damages clock runs from the day the moratorium passed. Rural counties with no large-load permitting framework face a litigation bill that can exceed their entire annual budget.
Kenya and President Ruto
Kenya and President Ruto
Kenya's suspension of the $1 billion Microsoft-G42 Olkaria project in early May applies raw-capacity logic at national scale: President Ruto stated the full 1 GW build would mean switching off half the country against a 3 GW installed base. A single hyperscale campus can consume a third of a Sub-Saharan grid with no equivalent constraint in Europe.
Denmark and Energinet
Denmark and Energinet
Energinet's 27 May extension of its large-load connection pause, with a 60 GW queue against 7 GW peak demand, demolishes the assumption that surplus renewable generation is a relief valve for compute demand. Denmark has more wind than it can use and still cannot connect data centres, because transmission pace is the binding constraint.
France and EDF
France and EDF
EDF's repurposing of the Bouchain former power-station site for SoftBank's Phase 1 campus gives France a replicable siting instrument, a brownfield nuclear connection bypass, that no other G7 grid operator can match. France's Choose France summit on 30 May secured the boom's largest European bet without a connection-queue fight or community moratorium.
SoftBank Group
SoftBank Group
SoftBank's EUR 75 billion France commitment on 30 May anchors at EDF's Bouchain nuclear baseload, bypassing the UK's four-times-US electricity cost premium (cited by OpenAI as reason to pause Cobalt Park) and Germany's grid-queue delays. EDF's supply relationship is bilateral; SoftBank never enters the French connection queue.
US residential ratepayers and state regulators
US residential ratepayers and state regulators
Portland General Electric's 4 June tariff is the first evidence that PJM's cost-transfer warning to governors on 19 May can run in reverse: Oregon households get a 1.3% bill reduction as data centres absorb their grid costs. The 12 other states carrying active cost-attribution bills now have a filed tariff with actual numbers to cite.