Skip to content
You can now search across every topic, entity and event.What's new
Data Centres: Boom and Backlash
10JUN

ERCOT large-load queue passes 225 GW

3 min read
10:06UTC

ERCOT disclosed in April that its large-load process has 225 GW of capacity in study, with over 70 per cent from data centres; West Texas operators want to convert 9.1 GW of crypto-mining brownfield to AI compute.

IndustryDeveloping
Key takeaway

ERCOT's process is overrun because every operator wanting out of FERC jurisdiction is routing through it.

ERCOT, the Texas grid operator, told an April 2026 state Senate hearing that more than 225 GW of large electricity loads are in formal interconnection study, with over 70 per cent from data centres. A further 137 unposted requests totalling roughly 140,000 MW would push the working total toward 380 GW if and when they hit the public queue chart. ERCOT received 225 new large-load requests during 2025 alone against an interconnection process designed to handle 40 to 50 at a time.

ERCOT is not synchronised with the Eastern or Western Interconnection, which means it falls outside FERC jurisdiction. Operators looking to escape the federal layer have begun routing capacity through West Texas already, and the 9.1 GW of crypto-mining brownfield infrastructure across the Midland-Abilene corridor is the brownfield route. Crypto sites already have grid connections, building shells, and cooling rated for high-density compute; converting that load class to AI inference and training is faster than greenfield construction by 18 to 24 months. xAI's 41 turbines at Memphis sit on the same behind-the-meter logic, but operators copying that play now have to find a turbine slot before they find a site, and the queue runs to 2031.

McKinsey has been contracted to deliver a short- and mid-term solutions framework for ERCOT, with a streamlined batch-study implementation expected to follow. The March 2026 Large Load Working Group meeting focused on flexible-interconnection models that allow loads to come online with curtailment commitments instead of full firm-capacity rights. The interaction with the FERC June order is straightforward: every operator who can route through ERCOT is doing so, every operator who cannot is waiting to see whether RM26-4-000 cuts the wait or extends it. The queue grows in either case, because the structural attractiveness of a non-FERC grid does not turn on a single rule cycle.

Deep Analysis

In plain English

ERCOT runs the Texas electricity grid, which operates independently from the rest of the US national grid. Companies wanting to connect large facilities to the Texas grid apply to ERCOT for permission. The queue currently holds more than 225,000 megawatts of applications waiting for approval, more than four times the total capacity Texas currently uses at peak. More than 70 per cent of those applications are from data centres. ERCOT hired McKinsey to work out how to process them faster. Meanwhile, companies in West Texas are trying a shortcut: convert existing Bitcoin mining facilities, which already have grid connections, into AI computing centres. This avoids the queue entirely because the electricity connection is already built.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

ERCOT· 6 May 2026
Read original
Different Perspectives
Indian data-centre investors
Indian data-centre investors
Amazon, CPPIB and Google committed billions to Indian data-centre capacity within a single week in June, a market absorbing hyperscale investment while New Mexico and Maryland tighten permitting this fortnight. Every US moratorium makes that alternative more attractive, not less.
Gulf sovereign capital and hyperscale infrastructure investors
Gulf sovereign capital and hyperscale infrastructure investors
GE Vernova's turbine backlog grew to 116 GW and Synergy counted a 45 GW US pipeline the same week New Mexico killed a pipeline outright. Capital keeps moving toward campuses that can secure power fastest, in the Gulf as much as Texas or Virginia.
New Mexico and Virginia regulators, and the counties opposing the build-out
New Mexico and Virginia regulators, and the counties opposing the build-out
Garcia Richard killed Energy Transfer's Green Chili lateral for a second time on 15 July, and Sierra, Santa Fe and Socorro counties layered moratoria on top; Virginia's DEQ, lacking a PFAS rule, issued Amazon's Lake Anna permit regardless. Consent belongs in statute, and New Mexico's 2027 bill is the next test of whether that principle spreads.
Global hyperscale operators
Global hyperscale operators
Operators are still filing gigawatt-scale campuses and Meta is proceeding with its $10bn Lebanon, Indiana site despite the county-level bans nearby, betting Q2 capex outruns the patchwork of restrictions. Industry framing casts New York's freeze, Oregon's surcharge and Indiana's bans as taxes and levies that push build-out toward faster-permitting jurisdictions such as India and the Gulf.
EirGrid
EirGrid
EirGrid set a 900 MW instantaneous demand-loss ceiling because a single voltage dip can trip many data centres onto backup power at once, risking imbalance above 1,150 MW. It wrote the limit into a standing procedure rather than waiting for an emergency to force one.
US host communities and ratepayers
US host communities and ratepayers
Prince William residents backed the 8-0 denial of Dulles South over the Occoquan watershed, drinking water for eight million people, while Oregon's approved tariff cuts residential bills 1.3% by charging large loads 29% more. Their position: consent and cost-attribution belong in law, not left to a developer's or a utility's discretion.