
EirGrid
Ireland's state electricity transmission operator; its adequacy warning puts data centre reconnection on a collision course with grid capacity.
As of November 2026, EirGrid reports that no new data centre has applied under the rules that reopened Irish grid connections, while the High Court weighs a challenge to them after reserving judgment on 18 November.
Last refreshed: 26 November 2026 · Appears in 1 active topic
EirGrid warns supply will fall short through 2028; why is the CRU reconnecting data centres?
Timeline for EirGrid
Mentioned in: Irish court reserves ruling on CRU rules
Data Centres: Boom and BacklashMentioned in: Finland plans a register of data centres
Data Centres: Boom and BacklashMentioned in: NERC adopts first data-centre grid rules
Data Centres: Boom and BacklashMentioned in: Norwegian MPs seek data-centre grid halt
Data Centres: Boom and BacklashSet the derogation route for non-compliant data centres
Data Centres: Boom and Backlash: CRU makes Irish sites ride through dipsBackground
EirGrid is the state-owned operator of Ireland's high-voltage transmission network. It balances supply and demand in real time, forecasts whether the system can meet peak load, and sets the technical conditions that large users must meet to connect.
Few grids in Europe carry as heavy a data-centre load. New applications could require 5.8 GW against an all-time national peak of 6.024 GW, which makes each new campus a system-level decision rather than a local one. EirGrid's warnings about supply margins have therefore become the main brake on the sector, whatever the connection policy says.
Operators have looked for ways round the queue. Pure DC's 110 MW microgrid in Dublin went live in April 2026, bypassing the grid queue altogether. The more sites generate their own power, the less EirGrid's queue decides who builds.
The reopened route has drawn no applicants
EirGrid sits between a regulator that reopened large-load connections early in 2026 and its own forecasts, which say the grid cannot carry much more. Its February adequacy report warned that peak demand would exceed supply through 2028, even as data centres reached roughly 32% of national electricity use, up from 22% in 2024.
The operator had been told to publish a data-centre connection process by 31 March 2026; nothing appeared in the following weeks, and Pure DC went its own way with a 110 MW on-site microgrid in Dublin. By 18 November, when the High Court reserved judgment on a challenge brought by three environmental groups, EirGrid said no new data centre had applied under the reopened framework at all.
EirGrid caps how much load can vanish
Large data centres can drop off the grid in an instant when voltage dips, and on a system of Ireland's size that threatens the balance. EirGrid and SONI published a fault-ride-through procedure on 30 June: from July, no more than 900 MW of data-centre load may drop off the system at once, and the operators flagged imbalance risk above 1,150 MW.
The operator then wrote the obligations into its grid code. Modification 345 set ride-through and recovery duties, with a 24-month group derogation for sites that could not comply at once. The regulator approved the change on 22 September, effective around 27 October, and any site that cannot meet it must first ask EirGrid for a temporary exemption.
EirGrid warns supply will fall short
Why is EirGrid warning about a supply shortage in Ireland?
How much of Ireland's electricity do data centres use?
What did EirGrid's 2026 adequacy assessment find?
What is the CRU deadline EirGrid missed on data centre connections?
Why is EirGrid blocking new data centre connections in Dublin?
What is Ireland's data centre power problem?
Reference
Who owns EirGrid and what does it do?
What is EirGrid's new 900 MW fault-ride-through limit?
How does Ireland's EirGrid moratorium compare to the US data centre moratoriums?
What is the EirGrid mass exodus warning about data centres?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.