Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
EirGrid
AI-generated illustration
OrganisationIE

EirGrid

Ireland's state electricity transmission operator; its adequacy warning puts data centre reconnection on a collision course with grid capacity.

On 30 June, EirGrid and SONI set a 900 MW ceiling on sudden data-centre demand loss, bringing a grid-code limit into force in July as Irish supply forecasts pointed to peak shortfalls through 2028.

Last refreshed: 24 September 2026 · Appears in 1 active topic

Key Question

EirGrid warns supply will fall short through 2028; why is the CRU reconnecting data centres?

Timeline for EirGrid

#15 17 Sept
#16 10 Sept
#12 29 Jul

Proposed fault-ride-through and RoCoF compliance obligations via MPID 345

Data Centres: Boom and Backlash: Ireland writes the grid rules into contracts
#11 15 Jul
#10 29 Jun

Issued a fault-ride-through demand-curtailment procedure with SONI

Data Centres: Boom and Backlash: Ireland codes a 900 MW load-loss limit
View full timeline →

Background

EirGrid plans and operates Ireland's high-voltage electricity transmission network. Its REMIT also covers all-island system planning with Northern Ireland's SONI, placing the operator at the point where new large loads meet physical grid limits.

Ireland's data-centre debate gives that technical role public weight. On 30 June, EirGrid and SONI applied a procedure for sudden data-centre demand loss, while the CRU considered connection obligations for sites on the transmission network on 29 July.

EirGrid does not grant planning consent or set national industrial policy. Its durable function is to model capacity, plan transmission and define the operational conditions needed to maintain a secure electricity system as demand changes.

Key Issues
Grid code limits

EirGrid limits demand loss

On 30 June, EirGrid and SONI issued a procedure limiting instantaneous data-centre demand loss to 900 MW. The procedure took effect in July and warned that loss above 1,150 MW could create a grid imbalance.

For EirGrid, the measure turns an adequacy concern into an operating constraint. The CRU closed consultation on modification 345 on 29 July, covering fault ride-through, rate-of-change-of-frequency and active-power-recovery duties for transmission-connected data centres. Those obligations determine whether EirGrid can keep the wider network stable when large loads disconnect.

Connection pressure

EirGrid faces load outside its queue

On 1 April, a 110 MW Pure DC microgrid entered service in Dublin outside Ireland's grid connection queue. The CRU had required EirGrid and the distribution operator to publish a data-centre connection process by 31 March, but no process appeared in the following 26 days.

For EirGrid, behind-the-meter generation complicates demand planning. A March-commissioned 110 MW Dublin microgrid later became a model for a route under which operators could seek approval with on-site generation while the EirGrid queue cleared. The operating challenge is to assess system adequacy while major prospective loads use alternatives to a normal transmission connection.

Common Questions
What is EirGrid's new 900 MW fault-ride-through limit?
On 30 June 2026, EirGrid and SONI issued a fault-ride-through demand-curtailment procedure capping instantaneous data-centre demand loss at 900 MW, live from July, and warning of imbalance risk above 1,150 MW without mitigation.Source: data-centres update 10
Why is EirGrid warning about a supply shortage in Ireland?
New data-centre applications could require an additional 5.8 GW of capacity, close to Ireland's all-time peak of 6.024 GW. EirGrid's February 2026 assessment found demand will exceed supply at peak across 2026 to 2028.Source: EirGrid
How much of Ireland's electricity do data centres use?
Data centres account for approximately 32% of Ireland's national electricity consumption in 2026, up from 22% in 2024. Dublin campuses alone represent roughly 50% of regional demand.Source: EirGrid All-Island Resource Adequacy Assessment
What did EirGrid's 2026 adequacy assessment find?
EirGrid's All-Island Resource Adequacy Assessment, published February 2026, warned that electricity demand will exceed supply at peak across 2026 to 2028, with data centres now accounting for 32% of national electricity consumption.Source: EirGrid
What is the CRU deadline EirGrid missed on data centre connections?
CRU required EirGrid (jointly with ESB Networks) to publish a data centre engagement and connection process by 31 March 2026. No such process was published 26 days past that Deadline, reinforcing the signal that Ireland's grid is overwhelmed by data-centre demand.Source: CRU / data-centres update 1
Why is EirGrid blocking new data centre connections in Dublin?
EirGrid's Dublin grid lacks capacity to absorb further large-load connections. The informal moratorium is the operational reality behind the CRU's policy requirement that new data centres demonstrate on-site dispatchable generation and meet an 80% renewables target within six years.Source: data-centres update 1 / CRU
What is Ireland's data centre power problem?
Ireland hosts a large share of European data centres relative to grid size. Concentrated demand in Dublin has overwhelmed EirGrid's connection capacity, forcing the CRU to introduce stricter rules and operators to consider behind-the-meter microgrids to bypass the queue entirely.Source: Lowdown data-centres briefing
How does Ireland's EirGrid moratorium compare to the US data centre moratoriums?
EirGrid's Dublin moratorium is grid-capacity driven and informal; it results from the grid being physically unable to accommodate more large-load connections. US moratoriums (Maine, Seattle) are policy-driven and enacted by legislation or executive order. EirGrid's situation predates the US wave and reflects a more extreme grid-capacity constraint.Source: data-centres context
Who owns EirGrid and what does it do?
EirGrid is a state-owned company owned jointly by the Irish and Northern Irish governments. It plans and operates the high-voltage national transmission grid in the Republic of Ireland and holds a stake in the UK-Ireland interconnector. It is distinct from ESB Networks, which operates the distribution grid.Source: EirGrid public record
What is the EirGrid mass exodus warning about data centres?
EirGrid warned the Irish government that operators unable to secure grid connections in Dublin are exiting to other European jurisdictions. The warning accompanied the organisation's failure to meet the CRU's March 2026 Deadline for a new connection process.Source: EirGrid / data-centres context
Source Material