Brazil's electricity regulator, the Agencia Nacional de Energia Eletrica (Aneel), authorised Scala Data Centers to connect its AI City campus at Eldorado do Sul, Rio Grande do Sul, to the national transmission grid1. The order, Despacho 3.506, is dated 3 September and became public in the official gazette, the Diario Oficial da Uniao, on 10 September. It feeds the site through a cut into the 525 kV Guaiba 3 to Nova Santa Rita line.
The national grid operator's access opinion sets the connection for January 2028 at 120 MW, according to Telesintese2. The despacho itself carries no megawatt figure.
The authorisation became public five days before President Lula signed Redata, the tax break the Senate had passed on 1 September. AI City now has a route onto the grid in the same month Brazil fixed the tax terms for qualifying data-centre builds.