Data Centres: Boom and Backlash
6MAY

PJM cuts backstop target to 9 GW

3 min read
13:52UTC

PJM restructured its September reliability backstop to a bilateral-first model targeting roughly 9 GW, down from 14.9 GW, per a Jefferies estimate published around 19 May.

IndustryDeveloping
Key takeaway

PJM shrank its September backstop to 9 GW, pushing data centres to contract their own firm power.

PJM Interconnection, the largest grid operator in the United States, serving roughly 65 million people across thirteen states, revised its September Reliability Backstop Procurement to a bilateral-first structure targeting roughly 9 GW, down from a prior 14.9 GW target, according to a Jefferies estimate published on or around Tuesday 19 May.⁠1

The backstop is the mechanism by which PJM secures emergency capacity to keep the lights on when demand outpaces supply. A bilateral-first design pushes large loads to strike their own supply contracts before the grid steps in to procure the remainder centrally, which is how the target shrank by nearly six gigawatts. The change followed directly from the warning PJM's board sent thirteen state governors that grid-reinforcement costs would otherwise drift onto household bills.

For data-centre operators, the revision narrows the pool of capacity the grid will backstop on everyone's behalf and widens the share they must arrange themselves. It is a quieter version of the same cost-allocation fight Oregon settled by tariff: who lines up the power, and who pays when the grid has to fill the gap.

Deep Analysis

In plain English

PJM Interconnection is the company that runs the electricity grid serving 65 million people across 13 US states, from Illinois to New Jersey. Every year it buys a reserve of extra power capacity to cover emergencies, called the Reliability Backstop Procurement (a backup supply purchase). Think of it like buying extra emergency generators for the whole grid. In May 2026, PJM changed how it runs this process. Instead of a competitive auction where power suppliers bid against each other, it switched to a bilateral-first system, meaning it negotiates direct deals with individual generators rather than running an open competition. The target amount of backup power dropped from 14.9 gigawatts to around 9 gigawatts. This reduces the cost that might otherwise land on household electricity bills, but critics say it also reduces price transparency, because direct deals are private rather than openly priced.

What could happen next?
  • Consequence

    PJM's bilateral-first backstop sets a precedent that competitive capacity auctions are politically unacceptable when data-centre load is the primary driver of reliability gaps, potentially reshaping how all 13 PJM-state utilities procure backup capacity.

  • Risk

    Bilateral contracts' confidential pricing removes the cost-attribution transparency that PJM's 19 May governor warning was designed to establish, creating information asymmetry between generators and state regulators at the moment regulators most need cost data.

First Reported In

Update #6 · Oregon bills data centres, not homes

Utility Dive· 10 Jun 2026
Read original →
Causes and effects
This Event
PJM cuts backstop target to 9 GW
The shrunken target shows PJM leaning on operators to contract their own firm power rather than the grid procuring it centrally, narrowing the volume households might end up paying for.
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.