Data Centres: Boom and Backlash
15NOV

ERCOT large-load queue passes 225 GW

3 min read
23:07UTC

ERCOT disclosed in April that its large-load process has 225 GW of capacity in study, with over 70 per cent from data centres; West Texas operators want to convert 9.1 GW of crypto-mining brownfield to AI compute.

IndustryDeveloping
Key takeaway

ERCOT's process is overrun because every operator wanting out of FERC jurisdiction is routing through it.

ERCOT, the Texas grid operator, told an April 2026 state Senate hearing that more than 225 GW of large electricity loads are in formal interconnection study, with over 70 per cent from data centres. A further 137 unposted requests totalling roughly 140,000 MW would push the working total toward 380 GW if and when they hit the public queue chart. ERCOT received 225 new large-load requests during 2025 alone against an interconnection process designed to handle 40 to 50 at a time.

ERCOT is not synchronised with the Eastern or Western Interconnection, which means it falls outside FERC jurisdiction. Operators looking to escape the federal layer have begun routing capacity through West Texas already, and the 9.1 GW of crypto-mining brownfield infrastructure across the Midland-Abilene corridor is the brownfield route. Crypto sites already have grid connections, building shells, and cooling rated for high-density compute; converting that load class to AI inference and training is faster than greenfield construction by 18 to 24 months. xAI's 41 turbines at Memphis sit on the same behind-the-meter logic, but operators copying that play now have to find a turbine slot before they find a site, and the queue runs to 2031.

McKinsey has been contracted to deliver a short- and mid-term solutions framework for ERCOT, with a streamlined batch-study implementation expected to follow. The March 2026 Large Load Working Group meeting focused on flexible-interconnection models that allow loads to come online with curtailment commitments instead of full firm-capacity rights. The interaction with the FERC June order is straightforward: every operator who can route through ERCOT is doing so, every operator who cannot is waiting to see whether RM26-4-000 cuts the wait or extends it. The queue grows in either case, because the structural attractiveness of a non-FERC grid does not turn on a single rule cycle.

Deep Analysis

In plain English

ERCOT runs the Texas electricity grid, which operates independently from the rest of the US national grid. Companies wanting to connect large facilities to the Texas grid apply to ERCOT for permission. The queue currently holds more than 225,000 megawatts of applications waiting for approval, more than four times the total capacity Texas currently uses at peak. More than 70 per cent of those applications are from data centres. ERCOT hired McKinsey to work out how to process them faster. Meanwhile, companies in West Texas are trying a shortcut: convert existing Bitcoin mining facilities, which already have grid connections, into AI computing centres. This avoids the queue entirely because the electricity connection is already built.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

ERCOT· 6 May 2026
Read original →
Different Perspectives
Mooresville Board of Commissioners
Mooresville Board of Commissioners
The town board north of Charlotte voted unanimously on 2 November to stop taking data-centre applications for 12 months. Commissioners cited environmental and electrical impacts, joining other North Carolina towns that have paused new projects.
Naver
Naver
Naver signed a US$9bn contract under which a Brookfield vehicle owns the GPUs and buildings and sells computing to Naver Cloud. It guarantees the fees for up to eight years, which also unlocked Nvidia's US$1bn equity investment.
Saudi Aramco
Saudi Aramco
Aramco closed its purchase of 49% of HUMAIN on 1 November, paying about US$2.6bn in cash and adding its own AI, compute and digital assets. Chief executive Amin Nasser cast the deal as a gain in technology standing.
NEXTDC board
NEXTDC board
The board called the Goodman and Digital Realty stake opportunistic and said it had received no takeover proposal. It enters the 20 November meeting with a new chairman search, a 10% fee cut and a spill resolution on the agenda.
Brasscom
Brasscom
Sergio Sgobbi of Brazil's technology industry association says investors face uncertainty until the Redata rules are public. Members need rulings on gas and the CDE levy after Lula said data centres must build their own power.
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
He told the Dewan Rakyat in October that data centres pay for all the grid capacity they reserve and fund upgrades to TNB's network. Google's 4 November pledge repeats those terms as its own.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.