Data Centres: Boom and Backlash
8SEP

xAI wins 41 gas turbines for Colossus

4 min read
13:06UTC

xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus complex; Meta's El Paso project will run on a 366 MW behind-the-meter gas array.

IndustryDeveloping
Key takeaway

xAI, Meta and Wonder Valley are committing decades of fossil generation behind the meter to bypass the grid queue.

xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus data centre complex outside Memphis. 1 Meta's El Paso project will run on a 366 MW behind-the-meter (BTM) natural gas array. Kevin O'Leary's Wonder Valley campus in Alberta, announced at $70 billion, has a 7.5 GW bring-your-own-power (BYOP) gas plan attached.

"behind-the-meter" describes generation built on the customer's side of the grid connection, dispatched to serve the customer's load directly without selling into the wholesale market. "Bring-your-own-power" is the operator-led variant: a campus is sited specifically to host its own generation rather than wait for transmission upgrades. Both routes solve the same problem: years-long waits for new transmission interconnection. Both also commit the operator to a fossil-fuel asset that runs for decades. A combined-cycle gas turbine ordered today comes online late in this decade and is depreciated over a twenty- to thirty-year operating life.

Colossus is xAI's Memphis training cluster, the site that hit roughly 100,000 H100 GPUs in late 2024 and was reported at 200,000 by mid-2025. Its previous power supply attracted complaints from the Southern Environmental Law Center over Clean Air Act permitting on its existing turbines. The March 2026 approval is the formal regulatory consent for the larger 1.2 GW build-out. Meta's El Paso project sits inside ERCOT, the Texas grid that has explicitly relaxed large-load interconnection rules to attract data centre demand the rest of the US grid will not connect.

The BYOP build-out runs alongside hyperscaler net-zero commitments published to investors and ESG indices. The cooling-water and renewables work covered in their sustainability reports does not retire the gas plant the same operator just queued behind the meter. Wonder Valley's 7.5 GW would meet the entire peak demand of a mid-sized European country, attached to a single private campus. Whether this gas capacity ever runs at the contracted load factor depends on how fast renewable interconnection clears, but the contracts are being signed now, and turbine lead times mean the bet is locked in.

Deep Analysis

In plain English

Most buildings get their electricity from the public grid, the network of power stations and cables that delivers electricity to homes and businesses. Large data centres need so much power that getting connected to the grid can take three to five years. Behind-the-meter gas is a different approach: the operator builds its own gas-fired power stations on or next to the data centre site, generating electricity directly without ever connecting to the public grid. The gas comes from a pipeline; the turbines convert it to electricity on site. xAI, the AI company founded by Elon Musk, won approval for 41 of these turbines at its Colossus facility in Memphis, totalling 1.2 GW. Meta and Kevin O'Leary's planned Wonder Valley campus in Alberta are taking the same route. The advantage is speed: turbines can be delivered and installed in 18-24 months. The disadvantage is that they burn fossil fuel and emit carbon and local air pollutants.

Deep Analysis
Root Causes

Grid interconnection timelines in the US average three to five years for large industrial loads. AI data centres require power delivery on 12-18 month deployment cycles to remain competitive. The gap between what the grid can deliver and what operators require has made BTM gas economically rational even at the cost of higher per-MWh fuel prices, permitting complexity, and reputational risk.

The secondary cause is the GE Vernova backlog: gas turbines are deliverable within 18-24 months (subject to queue position), whereas new grid connections in congested areas are not. Equipment manufacturers have pulled forward delivery capacity that transmission planners cannot match.

What could happen next?
  • Consequence

    The IEA's 15-27 GW US onsite gas projection by 2030 is now on track to be achieved early: xAI alone accounts for 1.2 GW, Meta El Paso for 0.37 GW, and Wonder Valley (if built) for 7.5 GW.

    Medium term · Medium
  • Risk

    Memphis's minor modification permitting pathway for 41 turbines is now the subject of EPA regional scrutiny; if challenged successfully, it could invalidate the approval and strand capital already committed.

    Short term · Medium
  • Precedent

    Three major BTM gas commitments in a single quarter establishes BTM self-generation as the default model for AI campuses above 300 MW, which will shape utility planning and grid investment models for the next decade.

    Long term · High
First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

Data Center Frontier· 26 Apr 2026
Read original
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.