xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus data centre complex outside Memphis.1 Meta's El Paso project is planned to run on a 366 MW natural gas plant dedicated to the site, which El Paso Electric has asked Texas regulators to approve. Kevin O'Leary's Wonder Valley campus in Alberta, announced at $70 billion, has a 7.5 GW bring-your-own-power (BYOP) gas plan attached.
"behind-the-meter" describes generation built on the customer's side of the grid connection, dispatched to serve the customer's load directly without selling into the wholesale market. "Bring-your-own-power" is the operator-led variant: a campus is sited specifically to host its own generation rather than wait for transmission upgrades. Both routes solve the same problem: years-long waits for new transmission interconnection. Both also commit the operator to a fossil-fuel asset that runs for decades. A combined-cycle gas turbine ordered today comes online late in this decade and is depreciated over a twenty- to thirty-year operating life.
Colossus is xAI's Memphis training cluster, the site that hit roughly 100,000 H100 GPUs in late 2024 and was reported at 200,000 by mid-2025. Its previous power supply attracted complaints from the Southern Environmental Law Center over Clean Air Act permitting on its existing turbines. The March 2026 approval is the formal regulatory consent for the larger 1.2 GW build-out. Meta's El Paso project sits outside ERCOT, the main Texas grid: El Paso Electric is part of the Western Interconnection, and the 366 MW gas plant for the site still needs approval from the Public Utility Commission of Texas.
The BYOP build-out runs alongside hyperscaler net-zero commitments published to investors and ESG indices. The cooling-water and renewables work covered in their sustainability reports does not retire the gas plant the same operator just queued behind the meter. Wonder Valley's 7.5 GW would meet the entire peak demand of a mid-sized European country, attached to a single private campus. Whether this gas capacity ever runs at the contracted load factor depends on how fast renewable interconnection clears, but the contracts are being signed now, and turbine lead times mean the bet is locked in.
