Senate Finance chair L. Louise Lucas proposed a $35-$45 per-kilowatt charge on data-centre diesel generators around 16 June, the first US levy aimed at installed fallback capacity rather than the power a campus draws.

IndustryDeveloping
Key takeaway

Virginia would tax the generators a campus installs, not the power it draws, reaching gas that grid billing misses.

Virginia's Senate Finance Committee proposed a tiered fee of $35 to $45 per kilowatt on the diesel backup generators inside data centres around 16 June, the first US levy designed to tax installed fallback capacity rather than the electricity a campus draws 1. Finance chair L. Louise Lucas floated it as a compromise: operators keep the $1.9bn sales-tax exemption but pay a per-kilowatt charge on backup generation, projected to raise $582m in FY2027 and $1.2bn in FY2028. The committee has not voted the fee through, and the 22 June Senate session could let it lapse.

The charge falls on installed capacity a campus may never run. This is the behind-the-meter (BTM, on-site generation sited next to the load rather than drawn through the public grid) gas fleet the Department of Energy has switched off twice in 2026 under Section 202(c), the Federal Power Act's emergency-curtailment authority . Federal power can cut that gas off in a heat event; it cannot price it. A per-kilowatt fee reaches the part of the build that consumption billing never sees, because a generator sitting idle draws nothing to meter.

The 30 June fiscal deadline is forcing the pace. The House of Delegates cancelled its 18 June budget session, with Speaker Don Scott saying no agreement had been reached, and Governor Abigail Spanberger sided with The House the same day against any early end to the exemption. Virginia has already lost projects to this fight before any fee existed: Compass Datacenters abandoned two site searches over tax uncertainty , and Danville approved the Berry Hill campus only on condition that the exemption survives . The fee is a wager that a new revenue line can hold the budget together where ending the exemption outright cannot.

Deep Analysis

In plain English

Virginia gives data centres a big tax break; they pay no sales tax on equipment worth about $1.9 billion a year to the industry. The state legislature has been arguing about whether to cancel that break since early 2026, and the argument has blocked the whole state budget. The Senate's new idea is a middle path: keep the tax break, but charge data centres a fee on the diesel backup generators they use when the electricity grid fails. The fee would be $35 to $45 for every kilowatt of backup capacity installed. A large data centre might have hundreds of megawatts of backup power, so the annual bill could run into the tens of millions of dollars. The House of Representatives side of the legislature cancelled its budget meeting the same day, and the governor said she is against the idea. If no deal is reached by 30 June, some Virginia government services could be temporarily shut down: a rare event called a partial government shutdown.

Deep Analysis
Root Causes

Virginia's fiscal impasse rests on three structural conditions. First, the original 2000-era tax exemption was written with no sunset clause and no per-site revenue or employment threshold, meaning the state has never had a legal mechanism to recover costs as data-centre power density increased beyond the assumptions of the original legislation.

Second, the separation of powers between the Senate and House is unusually evenly balanced on this issue: the Senate Finance Committee controls revenue instruments while the House of Delegates controls budget appropriations, and neither chamber can move the budget without the other.

The Berry Hill conditional approval and Compass site abandonment show that the external industry response is already embedded in the political calculus, with operators treating the state-level standoff as a site-selection risk.

Third, the DOE's Section 202(c) curtailment orders targeting behind-the-meter backup gas make the generator fleet simultaneously a federal regulatory target and the chosen base for Virginia's new fiscal instrument, creating a structural tension between what the state wants to tax and what the federal government wants to switch off.

What could happen next?
  • Risk

    If enacted, the $35-$45/kW fee creates a template other states can adopt without touching the headline exemption, spreading capacity-fee instruments beyond Virginia.

    Short term · Suggested
  • Risk

    The 30 June budget deadline raises the prospect of Virginia's first partial government shutdown, which could accelerate or collapse the generator-fee proposal unpredictably.

    Immediate · Assessed
  • Consequence

    Operators sizing new Virginia campuses will need to model the generator-fee liability as a fixed annual cost, shifting break-even assumptions on large campuses by up to $20 million per year per 500 MW of backup capacity.

    Short term · Suggested
First Reported In

Update #7 · Virginia taxes the backup, not the draw

Bloomberg Tax· 17 Jun 2026
Read original
Different Perspectives
Government of Odisha
Government of Odisha
Odisha signed a $1.5bn agreement with HCLTech and Sarvam AI on 24 July for a sovereign AI data centre in Bhubaneswar, targeting 2028 operations. While regulators elsewhere price developers out of the queue, Odisha is bidding state financial assistance to bring capacity in, betting the AI infrastructure boom is worth courting rather than rationing.
Switch Datacenters and Uithoorn
Switch Datacenters and Uithoorn
The developer, the municipality, Liander and dozens of greenhouse growers signed a waste-heat agreement letting a 60 MVA facility proceed under a provincial rule that bans sites above 5 MVA. The public-interest exception argues the site relieves rather than adds to grid congestion, working around a standing ban from inside rather than waiting for it to change.
Iskandar Puteri residents
Iskandar Puteri residents
Residents protested in February over falling water pressure they attribute to ZDATA's 300 MW construction; ZDATA disputes causation and has not yet resolved the dispute with its wastewater-only pivot. The complaint sits unadjudicated while the operator advertises compliance to state authorities the residents cannot address directly.
Microsoft
Microsoft
DC Byte reports Microsoft looking to the Nordics for new capacity while Dublin's regional share falls to 15 per cent, though this is a market-intelligence inference rather than a company statement. Microsoft keeps its existing Dublin cloud region, which is costly to relocate, while directing new investment where power is cheaper and the queue is shorter.
ISO New England
ISO New England
ISO-NE proposed excluding new large loads from its Installed Capacity Requirement entirely, forcing data centres to bring their own generation or accept curtailment, even though New England's demand has been flat or falling for a decade. The reform is pre-emptive, written before the region has felt the strain PJM and MISO already report.
Ofgem
Ofgem
Ofgem opened its Data Centre Commitment Fee consultation on 29 July, arguing that free options on grid capacity let developers bank places on ten sites and abandon nine, crowding out projects that would build. It expects the deposit to filter the queue before the rule even takes final form.