Data Centres: Boom and Backlash
4AUG

PJM cuts backstop target to 9 GW

3 min read
10:53UTC

PJM restructured its September reliability backstop to a bilateral-first model targeting roughly 9 GW, down from 14.9 GW, per a Jefferies estimate published around 19 May.

IndustryDeveloping
Key takeaway

PJM shrank its September backstop to 9 GW, pushing data centres to contract their own firm power.

PJM Interconnection, the largest grid operator in the United States, serving roughly 65 million people across thirteen states, revised its September Reliability Backstop Procurement to a bilateral-first structure targeting roughly 9 GW, down from a prior 14.9 GW target, according to a Jefferies estimate published on or around Tuesday 19 May. 1

The backstop is the mechanism by which PJM secures emergency capacity to keep the lights on when demand outpaces supply. A bilateral-first design pushes large loads to strike their own supply contracts before the grid steps in to procure the remainder centrally, which is how the target shrank by nearly six gigawatts. The change followed directly from the warning PJM's board sent thirteen state governors that grid-reinforcement costs would otherwise drift onto household bills .

For data-centre operators, the revision narrows the pool of capacity the grid will backstop on everyone's behalf and widens the share they must arrange themselves. It is a quieter version of the same cost-allocation fight Oregon settled by tariff: who lines up the power, and who pays when the grid has to fill the gap.

Deep Analysis

In plain English

PJM Interconnection is the company that runs the electricity grid serving 65 million people across 13 US states, from Illinois to New Jersey. Every year it buys a reserve of extra power capacity to cover emergencies, called the Reliability Backstop Procurement (a backup supply purchase). Think of it like buying extra emergency generators for the whole grid. In May 2026, PJM changed how it runs this process. Instead of a competitive auction where power suppliers bid against each other, it switched to a bilateral-first system, meaning it negotiates direct deals with individual generators rather than running an open competition. The target amount of backup power dropped from 14.9 gigawatts to around 9 gigawatts. This reduces the cost that might otherwise land on household electricity bills, but critics say it also reduces price transparency, because direct deals are private rather than openly priced.

What could happen next?
  • Consequence

    PJM's bilateral-first backstop sets a precedent that competitive capacity auctions are politically unacceptable when data-centre load is the primary driver of reliability gaps, potentially reshaping how all 13 PJM-state utilities procure backup capacity.

  • Risk

    Bilateral contracts' confidential pricing removes the cost-attribution transparency that PJM's 19 May governor warning was designed to establish, creating information asymmetry between generators and state regulators at the moment regulators most need cost data.

First Reported In

Update #6 · Oregon bills data centres, not homes

Utility Dive· 10 Jun 2026
Read original
Causes and effects
This Event
PJM cuts backstop target to 9 GW
The shrunken target shows PJM leaning on operators to contract their own firm power rather than the grid procuring it centrally, narrowing the volume households might end up paying for.
Different Perspectives
Government of Odisha
Government of Odisha
Odisha signed a $1.5bn agreement with HCLTech and Sarvam AI on 24 July for a sovereign AI data centre in Bhubaneswar, targeting 2028 operations. While regulators elsewhere price developers out of the queue, Odisha is bidding state financial assistance to bring capacity in, betting the AI infrastructure boom is worth courting rather than rationing.
Switch Datacenters and Uithoorn
Switch Datacenters and Uithoorn
The developer, the municipality, Liander and dozens of greenhouse growers signed a waste-heat agreement letting a 60 MVA facility proceed under a provincial rule that bans sites above 5 MVA. The public-interest exception argues the site relieves rather than adds to grid congestion, working around a standing ban from inside rather than waiting for it to change.
Iskandar Puteri residents
Iskandar Puteri residents
Residents protested in February over falling water pressure they attribute to ZDATA's 300 MW construction; ZDATA disputes causation and has not yet resolved the dispute with its wastewater-only pivot. The complaint sits unadjudicated while the operator advertises compliance to state authorities the residents cannot address directly.
Microsoft
Microsoft
DC Byte reports Microsoft looking to the Nordics for new capacity while Dublin's regional share falls to 15 per cent, though this is a market-intelligence inference rather than a company statement. Microsoft keeps its existing Dublin cloud region, which is costly to relocate, while directing new investment where power is cheaper and the queue is shorter.
ISO New England
ISO New England
ISO-NE proposed excluding new large loads from its Installed Capacity Requirement entirely, forcing data centres to bring their own generation or accept curtailment, even though New England's demand has been flat or falling for a decade. The reform is pre-emptive, written before the region has felt the strain PJM and MISO already report.
Ofgem
Ofgem
Ofgem opened its Data Centre Commitment Fee consultation on 29 July, arguing that free options on grid capacity let developers bank places on ten sites and abandon nine, crowding out projects that would build. It expects the deposit to filter the queue before the rule even takes final form.