Timeline
PJM Interconnection
US grid operator; 2027/28 capacity auction cleared 6,623 MW short of its reserve target.
20 of 20 entries (19 events, 1 interactions)
Filters
#13 3 Aug
Filed a curtailment rule for 50 MW-plus loads at FERC under docket ER26-3380-000
Data Centres: Boom and Backlash: PJM wants 50 MW loads curtailable#12 31 Jul
PJM's backstop auction opens at $555
Data Centres: Boom and Backlash#13 31 Jul
#11 21 Jul
Fell 6,623 MW short in its 2027/28 capacity auction, setting a 21 July procurement deadline
Data Centres: Boom and Backlash: PJM auction falls 6,623 MW short#10 19 Jul
FERC sets a 20 July adequacy deadline
Data Centres: Boom and Backlash#11 15 Jul
Mentioned in: New Mexico vetoes Jupiter gas pipeline
Data Centres: Boom and Backlash#11 15 Jul
Mentioned in: MISO's second grid emergency in July
Data Centres: Boom and Backlash#10 6 Jul
Mentioned in: Oregon clears a 29% big-load surcharge
Data Centres: Boom and Backlash#10 29 Jun
Ireland codes a 900 MW load-loss limit
Data Centres: Boom and Backlash#8 22 Jun
Mentioned in: Virginia taxes power behind the meter
Data Centres: Boom and Backlash#8 18 Jun
Received show-cause order to justify or reform large-load tariffs across five categories
Data Centres: Boom and Backlash: FERC delays its grid rule to 2027#8 18 Jun
Mentioned in: Texas queue swells to 438 GW
Data Centres: Boom and Backlash#6 4 Jun
Mentioned in: Oregon bills data centres, not homes
Data Centres: Boom and Backlash#5 28 May
Operated the curtailment authority granted by the DOE order
Data Centres: Boom and Backlash: DOE curtailment order faces taking claim#6 19 May
Revised September backstop to a bilateral-first structure targeting approximately 9 GW
Data Centres: Boom and Backlash: PJM cuts backstop target to 9 GW#5 19 May
Signed and dispatched a board letter to 13 governors warning of residential cost transfer absent state frameworks
Data Centres: Boom and Backlash: PJM warns 13 governors on grid costs#3 18 May
PJM faces Monday FERC tariff deadline
Data Centres: Boom and Backlash#4 18 May
activated DOE-granted curtailment authority over data centres during a heat event
Data Centres: Boom and Backlash: DOE lets PJM switch off data centres#4 18 May
75 GW added, PJM still hit an emergency
Data Centres: Boom and Backlash#5 9 Apr