Timeline

PJM Interconnection

US grid operator; 2027/28 capacity auction cleared 6,623 MW short of its reserve target.

20 of 20 entries (19 events, 1 interactions)

Filters
#13 3 Aug

Filed a curtailment rule for 50 MW-plus loads at FERC under docket ER26-3380-000

Data Centres: Boom and Backlash: PJM wants 50 MW loads curtailable
#12 31 Jul

PJM's backstop auction opens at $555

Data Centres: Boom and Backlash
#13 31 Jul
StatedFFERC
filed with
Data Centres: Boom and Backlash · source event
#11 21 Jul

Fell 6,623 MW short in its 2027/28 capacity auction, setting a 21 July procurement deadline

Data Centres: Boom and Backlash: PJM auction falls 6,623 MW short
#10 19 Jul

FERC sets a 20 July adequacy deadline

Data Centres: Boom and Backlash
#11 15 Jul
#11 15 Jul
#10 6 Jul
#10 29 Jun

Ireland codes a 900 MW load-loss limit

Data Centres: Boom and Backlash
#8 22 Jun
#8 18 Jun

Received show-cause order to justify or reform large-load tariffs across five categories

Data Centres: Boom and Backlash: FERC delays its grid rule to 2027
#8 18 Jun

Mentioned in: Texas queue swells to 438 GW

Data Centres: Boom and Backlash
#6 4 Jun
#5 28 May

Operated the curtailment authority granted by the DOE order

Data Centres: Boom and Backlash: DOE curtailment order faces taking claim
#6 19 May

Revised September backstop to a bilateral-first structure targeting approximately 9 GW

Data Centres: Boom and Backlash: PJM cuts backstop target to 9 GW
#5 19 May
#3 18 May

PJM faces Monday FERC tariff deadline

Data Centres: Boom and Backlash
#4 18 May

activated DOE-granted curtailment authority over data centres during a heat event

Data Centres: Boom and Backlash: DOE lets PJM switch off data centres
#4 18 May

75 GW added, PJM still hit an emergency

Data Centres: Boom and Backlash
#5 9 Apr

Mentioned in: Texas grid queue hits 410 GW

Data Centres: Boom and Backlash