Data Centres: Boom and Backlash

What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.

Happened 2 · Unresolved 1 · Open 75 · Corrections 132

What we told you to watch

Happened · 2

  • Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.

    From the 8 Sept briefing · Judged 22 Oct 2026

    SEA's Alto Jahuel case file is available and was checked.

  • Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.

    From the 8 Sept briefing · Judged 22 Oct 2026

    CRU approved MPID 345 on 22 September 2026.

Unresolved · 1

  • NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .

    From the 24 Sept briefing · Judged 22 Oct 2026

    Final ballot passed; Board adoption and FERC filing remain pending.

Still open · 75

Show the 10 most recent
  • Whether the county-level moratorium wave forces a statewide response in Indiana

    From the 7 Jul briefing

  • Whether Chevron takes a final investment decision on Project Kilby by the end of 2026, or the GE Vernova turbine queue pushes first power past 2028.

    From the 28 Jun briefing

  • Whether FERC's six grid operators meet the 17 August show-cause deadline, or seek extensions that push any binding rule deep into 2027.

    From the 28 Jun briefing · Deadline: 17 August

  • Whether another state copies Virginia's behind-the-meter tax now that one jurisdiction has a working model.

    From the 28 Jun briefing

  • Whether Texas locks the Batch Zero cohort before its 438 GW queue grows enough to make the autumn 2027 plan obsolete on arrival.

    From the 28 Jun briefing

  • Whether Virginia's 22 June Senate session breaks the exemption deadlock before the 30 June deadline, and whether the Lucas generator fee survives into the final budget or dies as a negotiating gambit.

    From the 17 Jun briefing · Deadline: 22 June

  • Whether the Oregon PUC holds PGE's 29% large-load rise at its 7 July decision, or trims the figure and reopens the cost-attribution framework.

    From the 17 Jun briefing · Deadline: 7 July

  • Whether Virginia DEQ attaches any PFAS testing condition to Amazon's Lake Anna discharge permit, which the 9 June hearing left undecided.

    From the 17 Jun briefing · Deadline: 9 June

  • Whether FERC issues the RM26-4-000 interconnection rule by end-June or lets its own deadline pass.

    From the 17 Jun briefing

  • Whether the Virginia Department of Environmental Quality (DEQ) attaches any PFAS (per- and polyfluoroalkyl substances, the persistent 'forever chemicals') testing condition when it finally rules on Amazon's 280,000-gallon-a-day Sedges Creek discharge into Lake Anna; the 9 June hearing produced objections but no decision.

    From the 10 Jun briefing · Deadline: 9 June

  • Whether Virginia's 18 June special session breaks the $1.9bn tax-exemption deadlock before the 30 June fiscal deadline, with the Senate demanding full elimination and the House insisting on environmental conditions.

    From the 10 Jun briefing · Deadline: 18 June

  • Whether FERC issues its RM26-4-000 large-load interconnection rule by end of June, or lets the self-imposed deadline pass.

    From the 10 Jun briefing · Deadline: end of June

  • Whether any PJM-territory state publishes a cost-allocation framework before the September backstop procurement, or whether costs keep drifting to households by default.

    From the 10 Jun briefing

  • Whether any PJM-territory state publishes a data-centre cost-allocation framework before the September Reliability Backstop Procurement, or lets the costs default to ratepayers.

    From the 2 Jun briefing

  • Whether a Texas court grants RCM Hill's injunction against the Hill County moratorium, the first test of a Fifth Amendment taking claim against a US data-centre pause.

    From the 2 Jun briefing

  • Whether Virginia DEQ approves Amazon's Sedges Creek permit after the 9 June hearing, and whether it adds any PFAS testing condition.

    From the 2 Jun briefing · Deadline: 9 June

  • Whether Virginia's 18 June special session resolves the data-centre tax exemption or triggers a partial state shutdown by 30 June.

    From the 2 Jun briefing · Deadline: 18 June

  • Whether FERC settles the RM26-4-000 permanent co-located-load rule by its end-June deadline, and whether it shields BTM generation or confirms its new role as interruptible reserve.

    From the 26 May briefing

  • The Virginia budget resolution and whether any abatement cut applies retroactively to commitments already made.

    From the 26 May briefing

  • Whether a third DOE Section 202(c) curtailment order lands during the summer peak, turning two orders into a settled pattern.

    From the 26 May briefing

What each side claimed

Claims are what a named side said at the time. We record them as said and judge them only against later evidence.

No claims recorded yet.

What we got wrong

Show the 10 most recent
  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.

    What was true

    On 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.

  • SignificantCorrected 1 Oct 2026
    We said

    Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.

    What was true

    On 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.

    In DOE lets PJM switch off data centres

  • MinorCorrected 24 Sept 2026
    We said

    Hill County, Texas is now defending against RCM Hill's $100 million claim

    What was true

    RCM Hill dismissed the case after Hill County dropped its ban (KWTX, 15 July 2026)

    In Loudoun drafts a pause on data centres

  • SignificantCorrected 8 Sept 2026
    We said

    Total contracted offers in the UK demand queue reached 125 GW by mid-2025, carried as an established queue total.

    What was true

    The 125 GW cannot be reproduced from the register it is usually checked against. Lowdown counted NESO's Transmission Entry Capacity register on 8 September 2026: of 2,202 entries, 106 (4.8%) carry any demand component and none is demand alone, so the register cannot yield a demand-queue total. The figure traces to a NESO presentation attributing it to Energy Networks Association connection data, an image-only document we could not verify at source. NESO's own reformed connections pipeline reports 99 GW of transmission-connected demand.

    In UK queue: 50 GW DC vs 45 GW peak demand