The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
FERC rules on a large-load plan: By 31 January 2027, FERC issues an order accepting at least one of the large-load plans the six grid operators filed between 13 and 20 November, with conditions allowed.
From the 26 Nov briefing · Deadline: 2027-01-31
Alberta passes Bill 42: By 31 December 2026, Alberta's legislature passes Bill 42, with its 600 m setback from homes and its exemption for projects already approved and those before the commission.
From the 26 Nov briefing · Deadline: 2026-12-31
Spain repeals its decree: By 30 June 2027, Spain's government repeals the data-centre royal decree approved on 20 November 2026, ending the 80% hourly renewables test.
From the 26 Nov briefing · Deadline: 2027-06-30
Brazil Redata decree: Brazil publishes the Redata implementing decree in the Diário Oficial da União by 30 November.
From the 15 Nov briefing · Deadline: 2026-11-30
NEXTDC spill: No spill meeting is called at NEXTDC's annual meeting on 20 November.
From the 15 Nov briefing · Deadline: 2026-11-20
Irish High Court: The Irish High Court gives judgment on the challenge to the CRU's large energy users connection policy by 31 March 2027.
From the 15 Nov briefing · Deadline: 2027-03-31
Norway concession scheme: Norway's government sends its data-centre concession scheme out for public consultation by 31 March 2027.
From the 15 Nov briefing · Deadline: 2027-03-31
Loudoun pause: Loudoun County's supervisors adopt the 12-month pause on new data-centre and substation applications at their meeting on 17 November.
From the 22 Oct briefing · Deadline: 2026-11-17
NEXTDC sites: NEXTDC announces the sale of at least one development site by its annual meeting on 20 November.
From the 22 Oct briefing · Deadline: 2026-11-20
Korea grid code: South Korea issues its AI data-centre grid code by 31 December with a transition period for projects already under way.
From the 22 Oct briefing · Deadline: 2026-12-31
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.
What was trueOn 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.
- SignificantCorrected 1 Oct 2026We said
Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.
What was trueOn 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.
- MinorCorrected 24 Sept 2026We said
Hill County, Texas is now defending against RCM Hill's $100 million claim
What was trueRCM Hill dismissed the case after Hill County dropped its ban (KWTX, 15 July 2026)
- SignificantCorrected 8 Sept 2026We said
Total contracted offers in the UK demand queue reached 125 GW by mid-2025, carried as an established queue total.
What was trueThe 125 GW cannot be reproduced from the register it is usually checked against. Lowdown counted NESO's Transmission Entry Capacity register on 8 September 2026: of 2,202 entries, 106 (4.8%) carry any demand component and none is demand alone, so the register cannot yield a demand-queue total. The figure traces to a NESO presentation attributing it to Energy Networks Association connection data, an image-only document we could not verify at source. NESO's own reformed connections pipeline reports 99 GW of transmission-connected demand.