Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Data Centres: Boom and Backlash
17JUN

DOE curtailment order faces taking claim

3 min read
10:13UTC

Parties challenging the DOE's Section 202(c) curtailment order filed a rehearing on 28 May, calling it a physical and regulatory taking of property without compensation.

IndustryDeveloping
Key takeaway

The DOE 202(c) rehearing tests whether emergency curtailment counts as a compensable seizure of property.

Parties challenging the DOE (Department of Energy) Section 202(c) curtailment order, Order 202-26-06, filed a rehearing request on 28 May 2026 arguing it is "both a physical taking and a regulatory taking" of property without just compensation. The order is the same emergency authority that PJM now wields over backup-equipped data-centre generators. The petition lands at FERC (Federal Energy Regulatory Commission), where resolution is not expected before 2027.

This challenge borrows the constitutional weapon RCM Hill aimed at Hill County the same week, but the federal facts cut the other way. A construction moratorium stops a project that never started; curtailment reaches into a running facility and orders its operator to shed load on command, which is why the petitioners frame it as a physical seizure of generating equipment, not merely a limit on use.

The counter-argument rests on a century of utility law. Section 202(c) of the Federal Power Act lets the DOE compel generation and load-shedding during a grid emergency, and courts have long treated emergency curtailment as conditional regulatory power rather than a compensable taking. DOE lawyers argue a data centre running a backup generator accepted that reliability condition the day it interconnected. Whether FERC and the courts accept the seizure framing will set the price of every future emergency order against a data centre.

Deep Analysis

In plain English

The US Department of Energy has the power, under a law called Section 202(c) of the Federal Power Act, to order certain large electricity users to cut their power use during a grid emergency, like an extreme heat event. In May 2026, DOE used this law to allow PJM, the grid operator, to switch off backup generators at data centres if needed. Now, the companies affected are arguing that this is unconstitutional. They say the government is effectively taking their property, the backup generators they own, without paying them compensation. Under the US Constitution's Fifth Amendment, the government must pay fair value when it takes private property. The same constitutional argument appears in the Hill County case {{EVREF:/t/data-centres/2/twinsburg-and-ypsilanti-use-utility-hookup-denial/}}, making this a coordinated legal challenge across two different levels of government.

Deep Analysis
Root Causes

Section 202(c) of the Federal Power Act predates the data-centre era by nearly 90 years and was written for fuel-supply and physical-plant emergencies affecting public utilities. It grants the Secretary of Energy authority to order temporary generation and load-curtailment measures during a reliability emergency, but its legislative history contains no reference to private commercial buildings, behind-the-meter backup generation, or AI compute loads.

The absence of a settled statutory framework for managing large dispatchable private loads, precisely the gap that FERC's Docket RM26-4-000 is meant to close, forces the DOE to use emergency authority as a workaround.

The taking challenge will not resolve before 2027 because it depends on FERC's RM26-4-000 rulemaking establishing the permanent framework. Until that rule sets what obligations data-centre operators carry as a condition of grid connection, every 202(c) order is litigable as either an overstep of emergency authority or a regulatory taking of property that was never explicitly made subject to grid-control conditions in the first place.

What could happen next?
  • Risk

    A court ruling that repeated use of Section 202(c) for a structural load-management problem violates procedural requirements would force the DOE to pursue notice-and-comment rulemaking, removing emergency curtailment as a tool until a formal rule is in place, potentially through 2028.

    Medium term · Suggested
  • Precedent

    If the taking theory survives threshold review and reaches a damages assessment, it would set a price for all future grid emergency curtailments applied to private commercial buildings, changing the risk calculus for every future DOE 202(c) order.

    Long term · Suggested
  • Consequence

    Uncertainty over curtailment authority accelerates data-centre operators' investment in physical islanding, where a campus generates and stores its own power and reduces reliance on grid-connected backup, to remove the regulatory handle DOE is using.

    Short term · Suggested
First Reported In

Update #5 · Who pays when the grid bends for AI

PJM Interconnection· 2 Jun 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.