Data Centres: Boom and Backlash
26NOV

PJM wants 50 MW loads curtailable

2 min read
18:00UTC

A Federal Register notice on 4 August opened comment on PJM's Interim Resource Adequacy Service, which would make loads of 50 MW and above curtailable as a condition of connection from June 2027.

IndustryDeveloping
Key takeaway

PJM would make curtailment a standing condition of connection for loads above 50 MW.

PJM Interconnection, the grid operator that runs wholesale power markets across 13 Mid-Atlantic and Midwest states, filed at the Federal Energy Regulatory Commission (FERC, which regulates interstate electricity transmission) on 31 July under docket ER26-3380-000. The filing bundles the Reliability Backstop Procurement we covered with an Interim Resource Adequacy Service (IRAS), which makes loads of 50 MW and above curtailable as a condition of connection from 1 June 2027 unless they bring their own capacity. The Federal Register notice opening comment published on 4 August, comments close at 5pm Eastern on 21 August, and PJM asks for an effective date of 29 September⁠1.

PJM's capacity auction fell 6,623 MW short in July. That shortfall is the arithmetic sitting under both halves of the docket: one half procures backstop capacity, the other reduces the load the system has to guarantee.

Draw a line no source draws. IRAS writes curtailability into the terms of connection and stays there until FERC changes it, a market rule of indefinite duration. The Department of Energy's Section 202(c) grant to PJM, which let the operator cut backup-equipped data centres during a heat event, ran as an emergency order under statute, temporary and exceptional by design. Different instrument, different authority, different permanence.

For a developer, the practical consequence lands in the financing model rather than in the engineering. A load that accepts IRAS accepts curtailment as its ordinary condition of service, which changes the availability assumption a lender underwrites, and the escape route, bringing your own capacity, means generation on site or contracted firm supply. Comments close before the operator can know how many will take it.

Deep Analysis

In plain English

PJM Interconnection runs the electricity grid across 13 US states and Washington DC. On 4 August, the government's Federal Register published PJM's request to make any electricity user drawing 50 megawatts or more, enough to power tens of thousands of homes, subject to being switched off during grid stress unless it has its own backup power. The rule would take effect from June 2027 and would replace the emergency curtailment orders regulators have already used twice this year with a permanent, standing requirement.

Deep Analysis
Root Causes

PJM's 2027/28 capacity auction cleared 6,623 MW short of its reliability requirement in July, and a separate 6,831 MW shortfall against the 2028/29 delivery year is what PJM's reliability backstop auction, filed in the same docket as IRAS, is trying to close. IRAS addresses the demand side of that gap: rather than paying more generators to exist, as the backstop auction does, it makes large loads bring their own capacity or accept curtailment.

The structural driver behind both halves of docket ER26-3380-000 is the same shortfall counted two ways. PJM's reliability requirement has outpaced the generation actually connecting to its grid, which is why IRAS addresses demand while the backstop auction addresses supply, and neither alone closes the gap on its own.

What could happen next?
  • Precedent

    IRAS would convert emergency curtailment, used twice by DOE in 2026, into a standing condition of grid connection.

First Reported In

Update #13 · GPUs now collateral as Nebius borrows $775m

Federal Register· 14 Aug 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.