Data Centres: Boom and Backlash
26NOV

Ireland writes the grid rules into contracts

2 min read
18:00UTC

Ireland's utility regulator closed its consultation on EirGrid's MPID 345 on 29 July, a modification that would make data centres ride through voltage dips rather than trip to backup generators.

IndustryDeveloping
Key takeaway

Ireland would oblige connected data centres to ride out grid faults, with a 24-month exemption route for laggards.

Ireland's Commission for Regulation of Utilities (CRU), the state body that regulates energy and water utilities, shut the comment window on EirGrid's Grid Code Modification MPID 345 on Wednesday 29 July, and says it will decide as a matter of urgency. That account reaches us through a regulatory digest published by the law firm Arthur Cox rather than from CRU directly⁠1.

MPID 345 sets the compliance and derogation framework for three technical obligations on transmission-connected demand facilities. Fault ride through requires a site to stay connected through a brief voltage dip instead of tripping to onsite backup generators. Robustness to RoCoF concerns the rate at which grid frequency changes. Active power recovery governs how quickly a site returns to normal draw once a fault has cleared. Operators unable to meet them can seek a derogation, a time-limited exemption, through a streamlined group route lasting 24 months and applied via a Demand Utilisation Threshold, a measure of how much of its connected capacity a site actually draws⁠2.

EirGrid and SONI, which operate the transmission grids in the Republic and Northern Ireland respectively, issued the fault-ride-through curtailment procedure itself on 30 June. MPID 345 is the compliance machinery arriving underneath it. A regulator that drafts a two-year escape hatch into a rule before the rule bites is telling you what it expects the queue of non-compliant operators to look like.

The distinction matters commercially. A campus that trips to diesel every time the grid wobbles is a liability the system operator must plan around; one that rides the dip is a customer. Ireland is now pricing that difference into the terms of connection rather than settling it at the admission gate.

Deep Analysis

In plain English

Ireland's power grid needs everything connected to it to behave predictably when something goes wrong, like a brief voltage dip. New rules from Ireland's grid operator, EirGrid, say data centres must be able to ride through these dips without suddenly switching off, because switching off a data centre that uses tens of megawatts is like flicking a giant switch that can destabilise the whole grid. The regulator, CRU, has just finished asking the public what they think, and is giving existing data centres up to two years to catch up if they cannot comply straight away.

Deep Analysis
Root Causes

The structural condition making this necessary is that fault-ride-through and rate-of-change-of-frequency rules were written for generators, not large, synchronised demand. Data centres drawing tens of megawatts can trip offline simultaneously during a grid disturbance, removing load faster than the system was designed to absorb, which is a different stability risk to a generator disconnecting.

The 24-month derogation exists because compliance requires hardware and control-system changes at facilities already built or under construction, a physical retrofit rather than a policy change alone; CRU cannot simply mandate instant compliance without risking forced facility shutdowns.

What could happen next?
  • Consequence

    Data centres unable to meet the new technical standards within 24 months face compliance risk to their existing Irish grid connections.

First Reported In

Update #12 · Ofgem prices the grid queue by the megawatt

Arthur Cox· 4 Aug 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.