Ireland refuses €1.5bn Mayo data centre

1 min read
18:00UTC

Ireland's planning appeals body refused a €1.5bn data centre at Killala, County Mayo, because the developer showed no fixed grid connection and no renewable power contract.

IndustryAssessed
Key takeaway

Ireland's planning appeals body refused a data centre that could not prove grid capacity or renewable supply.

An Coimisiun Pleanala, Ireland's national planning appeals body, refused a €1.5bn data centre at Killala, County Mayo, on 17 September, overturning Mayo County Council's 2025 grant⁠1. The applicant, Mayo Data Hub, is backed by Avaio Digital.

The board found the developer had shown no fixed grid connection agreement and no proof that the grid could serve the site, RTE News reported. It also found the project had not shown it would meet the objectives of Ireland's Climate Action Plan 2025, citing the absence of any corporate PPA (power purchase agreement) with a renewable supplier.

Ireland's energy regulator, the Commission for Regulation of Utilities, had been consulting on grid-code obligations that EirGrid would impose on large demand sites such as data centres. Killala moves those tests forward to the planning stage. An Irish applicant now faces a demand for grid and power-purchase evidence at the planning stage, before any connection offer.

Deep Analysis

In plain English

Ireland's national planning appeals board rejected a €1.5bn data centre planned for Killala in County Mayo, even though the local county council had already approved it last year. The board's reasons were about power, not politics: the developer had no confirmed grid connection agreement, and no signed contract to buy renewable electricity. This matters beyond Mayo because it shows Ireland's appeals process is now applying the same tough grid and renewable-energy tests used around Dublin to projects anywhere in the country, even regions once seen as an escape route from Dublin's stricter rules.

Deep Analysis
Root Causes

Ireland's grid has operated under an effective restriction on new large-load connections around Dublin since 2021, pushing developers toward the regions; Mayo Data Hub tried to build outside that constrained zone but still needed the grid operator to confirm the west of Ireland's thinner transmission network could serve a €1.5bn campus, and went to appeal without that confirmation in hand.

The refusal also rests on the absence of a corporate power-purchase agreement, a financing instrument rather than a planning requirement in most jurisdictions; treating a missing PPA as grounds for refusal signals Ireland now expects developers to prove renewable electricity is contracted, not merely available, before construction can begin.

First Reported In

Update #15 · Texas freezes data-centre permits

RTE News· 24 Sept 2026
Read original →
Causes and effects
This Event
Ireland refuses €1.5bn Mayo data centre
In An Coimisiun Pleanala's decision, missing grid-capacity evidence and a missing renewable PPA became grounds to refuse planning permission, ahead of any grid connection.
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.