How did a missing grid connection cost Loughton a $3.22bn Microsoft data centre?
Timeline for Loughton
Lost its grid connection date
UK Startups and Innovation: Nscale filing values lost Microsoft dealBackground
Loughton is a town in Epping Forest District, Essex, north-east of London, whose civil parish had 33,346 residents at the 2021 census. It sits on the London Underground's Central line and borders Epping Forest.
In September 2025 Nscale announced an AI data centre at Loughton for Microsoft's Azure cloud: 50 MW, expandable to 90 MW, with 23,040 Nvidia GB300 chips due from early 2027. Microsoft withdrew in October 2026 after UK Power Networks warned grid capacity might not be available until the 2030s, and confirmed on 19 October that the exit covered Loughton only.
Nscale's amended US listing filing of 12 November 2026 values the terminated Microsoft work at $3.22bn and blames the withdrawn connection date. Nscale says it remains committed to Loughton and is looking for other power sources.
Why did Microsoft pull out of the Loughton data centre?
How much was the Nscale Loughton contract worth?
What was planned at the Loughton data centre?